HAM 7 HEPI Install

The North end of HAM 7 has had the weldments and crossbeam attached. It was a very tight fit to move the crossbeam between the two chambers. Some creativity was called for, but installing the crossbeam for HAM 8 may require even more. The next steps will be to finish the clamp on the crossbeam and torque the bolts all of the bolts.