Reports until 16:59, Tuesday 14 July 2026
LHO VE (VE)
travis.sadecki@LIGO.ORG - posted 16:59, Tuesday 14 July 2026 (91034)
Corner station and HAM1 pumpdown paused overnight

We are still on scroll pumps for the corner station, so the pumpdown was paused for the night and the pumps valved out.  Pressure in the corner is ~0.5 Torr.  We should be able to get on turbo tomorrow.

HAM1 pumpdown was started today after sorting some gauge issues.  Pressure is 6e-2 Torr at COB.  This will also go onto turbo tomorrow.