Displaying report 1-1 of 1.
Reports until 16:34, Thursday 16 July 2026
H1 General
ryan.crouch@LIGO.ORG - posted 16:34, Thursday 16 July 2026 (91070)
OPS Thursday DAY shift midshift summary

TITLE: 07/16 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Ryan S
SHIFT SUMMARY: Outage recovery for most of the day, commissioning work ongoing on IOT2L and HAM7 as of 23:30 UTC. 
LOG:                                                                                                                                                                                                                                                                            

Start Time System Name Location Lazer_Haz Task Time End
15:09 FAC Randy LVEA N HAM3 cleanroom lights 17:36
15:42 FAC Richard Ends N Power cycle adco chassis 16:42
16:03 SEI TJ EndY, EndX N Reset hepi vfd 17:44
16:32 PEM Shrey, Carlos, Miranda LVEA N Seismometer testing 18:04
16:43 SEI TJ EndY N VFD reset 17:36
16:43 SQZ Sheila, Cory LVEA, HAM7 LOCAL HAM7 BIFURCATED LASER HAZARD work, sheila out at 18:30 19:11
16:53 FAC Randy LVEA N Craning platforms from high bay to west bay 17:53
17:02 SQZ Rahul LVEA LOCAL Join HAM7 work 20:10
17:16 SEI Mitch Ends N HEPI health check 17:45
17:34 SQZ Camilla LVEA, Vac prep LOCAL Check with / join HAM7 crew 20:17
18:03 SEI TJ EndY N ISI coil driver check, turn on als 18:50
18:12 SUS Oli CR n Restore SUS pointing 22:06
18:25 PSL Jennie LVEA N Open up light pipe, psl 18:33
18:35 SEI Shoshana LVEA N Connect cable by HAM3 18:46
18:45 EE FIl LVEA N Check interlock cabling by HAM1 19:02
18:49 SQZ Sheila LVEA LOCAL Talk with Camilla 19:11
19:02 CDS Dave EndX, then Y N Recover long range dolphin 19:42
19:03 CDS Daniel CER N Timing error investigation 19:46
18:09 SUS Ibrahim LVEA N Bier garten wrap and bag 19:22
19:36 FAC Randy LVEA N Clean up around the LVEA 20:06
19:53 VAC Travis LVEA N Disconnect anulus pump by HAM3 20:06
20:06 SEI Shoshana LVEA N CRS work 20:20
20:10 ISC Keita, Jennie, Fil LVEA N Enable pico motors, heaters, and HV, Fil out 20:20 20:25
20:12 SEI Shrey, Carlos, Miranda LVEA N Pickup equipment cases 20:32
20:23 CDS Dave EndX N Power cycle timing GPS chassis 20:51
20:25 VAC Travis LVEA N/LOCAL HAM5/7 relay tube 22:03
20:41 SUS Ibrahim LVEA N Wrap bag and tag, Bier garten 21:33
20:51 FAC Randy LVEA N Cleaning 21:40
20:51 VAC Gerardo LVEA N/LOCAL -> Y Relay tube work 22:12
21:30 PSL Jennie LVEA N Reenergize rotation stage 21:47
21:35 SAF Richard LVEA N/LOCAL Talk to Travis 22:00
21:40 SEI Shoshana LVEA N Turn on CRS laser 21:49
21:46 SQZ Camilla, Madi Optics lab N CHETA optics, lens work, Camilla out at 22:30 22:40
21:54 OPS RyanS LVEA N -> Y Laser hazard transition 22:05
22:04 TCS Matt, Cory Prep/CHETA lab N CHETA work, Cory out 22:20 23:04
22:08 ISC Jennie, Elenna LVEA Y Table work, IOT2L MC refl beam. Jennie out 22:40 00:08
22:15 SUS Ibrahim LVEA Y Wrap bag and tag 22:56
22:27 VAC Travis LVEA Y Check on pumps 22:34
22:27 SUS Rahul, Camilla, RyanS LVEA Y ZM5 aligment, HAM7 work. Camilla in at 22:40, RyanS out at 23:30 00:27
22:46 HWS TJ LVEA Y Investigate HWS 23:21
Images attached to this report