Reports until 17:42, Monday 27 July 2026
H1 CDS
jonathan.hanks@LIGO.ORG - posted 17:42, Monday 27 July 2026 (91273)
Prep work for CDS RCG Upgrades

WP 13455 and prep for 13457.

Dave has been labeling machines and adnico cards.  This will help us put fibers back in the right place after we disconnect them as part of the upgrades tomorrow.

I added the new IPC switches to the DNS today.  The switches are staged in their respective buildings with all the optics.  Their config has been updated to use the production logging, network time, and to allow polling from our network management host.

We got all the ethernet cards with the proper 1/2 height adapter and added the required optic.

We brought in a W3323 systems from the test stand and staged it in the MSR this will become the new h1seih23, as we need to have another core available for the ethernet IPC.  I updated the BMC address so that it can be remotely administered on the production network.

Dave has been to the end stations with Tony to stage equipment and help finalize layouts and plans.

We had a plan review meeting this afternoon. 

Dave will probably add some more notes tonight after checking on the SDF status, filter status, and model build status.