Reports until 12:56, Tuesday 28 July 2026
LHO VE (VE)
travis.sadecki@LIGO.ORG - posted 12:56, Tuesday 28 July 2026 (91288)
Quarterly Functionality Test Performed on EX/MX Turbo Pumps

FAMIS tasks 65526 and 81155, WP 13458

Procedure checklist for both stations completed.  No issues were identified at this time.

MX: Turbo pump hours: 154
       Scroll pump hours: 243.0
       Crash bearings: 100%

EX: Scroll pump hours: 7163.2
       Turbo pump hours: 1115
       Crash bearings: 100%