TITLE: 08/03 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 11mph Gusts, 7mph 3min avg
Primary useism: 0.01 μm/s
Secondary useism: 0.07 μm/s
QUICK SUMMARY:
The well pump was not working today due to some electrical issue. Last I heard FAC had a contractor on site to check on the well. So there is limited amounts of water here. Many folks were asked to work from home if they can.
GRB-Short E644098 @ 17:29 UTC
Jonathan started working on the FrameWrite0 today, installing Deb12 OS.
End stations were misaligned today to some tests that Camilla was doing.
ITMX ISI Stage 1 & 2 WD tripped twice today. Jim went out to the CER today to fix this.
Vac Team did some work on the GV6 Gate Valve today and GV6 is currently Open on the Y arm, But GV5 is still closed so the corner volume is still not open to the Arms yet.
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 15:10 | FAC | Kim | LVEA | y | Technical cleaning & resupply | 17:00 |
| 15:41 | CDS | EJ | Remote | N | Test on OAF | 15:42 |
| 15:43 | FAC | Tyler, Eric, & contractors | EY | N | Working on the well | 20:39 |
| 15:48 | SQZ | Camilla | LVEA HAM5 | YES | Opening ViewPort on HAM5 | 15:55 |
| 16:10 | FAC | Kim | Mid X | N | Tecnical Clkeaning & resupply | 17:01 |
| 16:11 | SEI | Jim | LVEA | n | working on SEI near BSC2 | 18:08 |
| 16:41 | VAC | Jordan & Travis | LVEA GV6 | N | Working on the Gate Valve | 18:39 |
| 17:20 | SEI | Jim | remote CER | N | Tests on HAM2 & looking at Wiring | 18:22 |
| 17:25 | VAC | Gerardo | LVEA | N | Checking on GV6 work | 19:25 |
| 17:45 | CDS | Partick | MSR | N | CDS work? | 18:06 |
| 18:39 | FAC | Kim | HAM Shaq | N | technical Cleaning & Resupply | 19:07 |
| 19:05 | CDS | Jonathon | Remote | N | Re-imaging FW0 | 22:04 |
| 19:59 | SEI | Jim | Remote | N | Tests on HAM3 | 21:25 |
| 20:03 | VAC | Jordan | LVEA | N | Getting pics of GV6 | 20:07 |
| 20:51 | VAC | Travis & Gerardo | End Y | N | Using the pump cart for Anulus work. | 21:28 |
| 21:10 | SQZ | Camilla & Ryan S | LVEA HAM7 | YES | Beam Profiling with M2**2 profiler. Ryan Out early | 23:10 |
| 21:12 | SEI | Jim | CER | N | troubleshooting ITMX ISI WD trips. | 21:24 |
| 21:43 | VAC | Jordan | LVEA GV6 | N | Checking on GV6 status | 22:28 |
| 22:41 | VAC | Jordan & Gerardo | LVEA GV6 | N | Opening GV6 | 00:11 |
| 22:46 | SQZ | Sheila | LVEA HAM7 | YES | Working on the Power budget | 00:16 |