Reports until 16:01, Tuesday 07 January 2014
H1 General
andres.ramirez@LIGO.ORG - posted 16:01, Tuesday 07 January 2014 (9141)
Ops Shift Summary
Fire Department on site doing maintenance
Installation and alignment of the GigE cameras at the HAM2 and HAM3 spools – Kiwamu
Centering SR2 BOSEMs at LVEA – Jeff B.
Baffle work at LVEA West bay – Mitchell
Electrician working at H1 electronics room
Work at End X – Sheila/Koji/Alexas
Turning Off aLOG, SVN, and awiki services due to hardware problems – Jonathan
Work on H1 PSL diode room – R. Savage
Cable pulling from Electronics room to HAM2 – Luis
aLOG, SVN, and awiki services have been turned ON – Jonathan
Remove the HAM1 viewport covers and/or camera cans – Keita/Kiwamu/Sheila/Koji/Alexa
Soft-close GV20  at End X- Kyle
Removing yellow cover from viewports on HAM1, HAM2 and HAM3 – Stefan
Fix to the ETMX, ETMXY, TMSX and TMSY models – Jeff K.
Hardware cabling at End X - Richard