TITLE: 08/13 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Ibrahim
SHIFT SUMMARY:
HAM7 close out work with both doors being installed and even the Annulus Ion Pumps pumping on the doors
Detector locking had DRMI locks---longest was around 5min! So troubleshooting continues.
LOG:
- Before shift Randy moved forklift to East Bay near HAM7
- 1412 BS ISI tripped. 1546 Camilla untripped the BS and it returned to FULLY ISOLATED NO ST2 BOOST
- 1458-1605 tech cleaning (kim)
- 1620-1702 FCES cleaning (kim)
- 1504-1520 checking "lvea local" laser status (corey)
- 1525-1718 HAM7 closeout work: backscatter meas (sheila.camilla.ryanS)
- 1542-1552 Rehoming a snake from LVEA north bay outside
- 1600-1612 transitioning East Bay back to Local Laser Hazard (barriers back up, signs flipped to laser hazard, and remove covers for beam from HAM7 to HAM6 in-air; last night this area was made SAFE for forklift move for Randy this morning (camilla)
- Reservation System noting LVEA Local is HAZARD
- 1655-1800 FAMIS checks (chris)
- 1705-1711 opening Ion Pump at HAM1 (gerardo)
- 1715-1744 Transitioning LVEA East Bay back to SAFE (camilla)
- 1718-1724 Beckhoff restart (for JAC heater) [Daniel]
- 1720-1728 Picking up PSAMs part in east bay (ryanC)
- 1726-1730 LVEA walkthru (betsy)
- 1732-1911 Unlock, balance, & run post-chamber-close measurements (jim)
- 1756-1803 LVEA walkthrough looking for IAS stuff (jason)
- 1804-1858 Inventory checks (mitch)
- 1840-1847 Checking CRS connections out at rack (shoshonna,huyen)
- 1859-1904 heading back in (shoshonna,huyen)
- 1843-1850 bypass HAM7 high voltage (fil)
- 1854-1909 measuring cables in lvea (carlos)
- 1906-1950 ground loop checks at rack (fil.betsy)
- 1915-1940 Turning laser off at rack (shoshonna,huyen)
- 2012 Turning on at the rack (shoshonna)
- 1920-1938 Moving a table out of the way at HAM7 (camilla)
- 1928-1943 Grabing something (washer) out from the bottom of HAM7 (jim)
- 1932-2325 Prep/Install both HAM7 doors and start pumping down AIPs to check doors. Also installed flanges on HAM7 west door (randy)
- 1940 travis joining
- 2000-2325 gerardo joining
- 2141 Randy out (both doors on)
- 1949-1953 grab pelican case (ryanC)
- 1957-2016 Dropping off large item in the recycling bin outside of hi-bay (christina)
- 2203-2220 Picking up pans/parts around HAM7 (ibrahim)
- 2307-2312 fixing accelerometer cables in CER (dave.miranda)
- 2322 CRS measurements at CER & HAM3 rack (shoshonna,huyen,jim)