LHO General
thomas.shaffer@LIGO.ORG - posted 19:51, Wednesday 19 August 2026 (91604)
Ops Day Shift End

TITLE: 08/19 Day Shift: 1430-2000 UTC (0730-1300 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Oli
SHIFT SUMMARY: GV6 & 8 were opened this morning, so we now have a full IFO to commission. Commissioners have been hard at work aligning to the arms. 
LOG:                                                                                                                                                                                         

Start Time System Name Location Lazer_Haz Task Time End
16:32 SEI Jim, Huyen LVEA - H2 y CRS wrapping 17:56
16:32 DAS Reinhardt LVEA y Fiber checks 19:55
16:39 FAC Randy LVEA y Craning scissor lift and 3IFO container 18:00
17:09 VAC Gerardo LVEA y Isolating turbos then opening GV6 & 8 18:05
17:16 JAC Jennie LVEA Y JAC table meas 18:03
17:16 DAS Jenne LVEA y Checking in with Reinhardt 17:30
17:29 PEM Robert, Miranda LVEA y Check on acc. name 17:36
18:03 SQZ Camilla, Ryan S LVEA y HAM7 area cleanup 19:19
18:19 ISC Jennie Opt Lab n Plug in power meter 18:45
19:08 SAF Jackie Ends n Taking pictures of first aid kits 20:08
19:20 ISC Camilla Opt Lab n Clean up 19:29
Displaying report 1-1 of 1.