LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 17:49, Friday 14 August 2026 - last comment - 00:04, Friday 21 August 2026(91542)
HAM7 Pumpdown Started

(Travis, Gerardo)
This morning we checked HAM7 annulus system pumpdown and the aux-cart displayed 2.6X10-05 Torr, good progress so it appears to be doing good.  We disconnected the SS-500 cart from HAM6 turbo and connected it to HAM7.  We checked all ports were "nominal", detached the active purge hose and no blowdown was done, since we had the relay tube valve (RV-2) open, took advantage of this and we let the purge air purge HAM7 overnight out RV-2.  After closing RV-2 we started the pumpdown of HAM7.  The purge valve (all metal valve) and the roughing valve at the turbo assembly were closed at 3.0X10-05 Torr.
Attached is a plot of the pumpdown thus far.

Images attached to this report
Comments related to this report
gerardo.moreno@LIGO.ORG - 00:04, Friday 21 August 2026 (91635)VE

(Travis, Gerardo)
Update.
HAM7 chamber pumpdown continues to progress, see attached plot for pumpdown trend.
AIP, the annulus system continues to pumpdown also, small can turbo attached at the annulus and a small cube aux-cart backing the can turbo, with a pressure of 7.8X10-06 Torr reported by the aux-cart, we turned the ion pump on a few days ago, and the system has made some progress, see attached plot for progress.

Images attached to this comment