oli.patane@LIGO.ORG - posted 18:06, Tuesday 01 September 2026 (91782)
Ops EVE Shift End

TITLE: 09/02 Eve Shift: 2330-0100 UTC (1630-1800 PST), all times posted in UTC
STATE of H1: Commissioning
INCOMING OPERATOR: None
SHIFT SUMMARY: Commissioning ended early today as well.
LOG:                                                                                                                                                                                                         

Start Time System Name Location Lazer_Haz Task Time End
22:55 TCS Camilla Prep Lab - Labelling cables 23:41
23:48 SPI Jennie, Jim LVEA n At SUS-R2 for SPI 00:41
23:52   Cory, Camilla Roof n Grabbing camera equipment 23:55