LHO VE (VE)
jordan.vanosky@LIGO.ORG - posted 17:57, Wednesday 16 September 2026 - last comment - 18:46, Friday 18 September 2026(91945)
EX Pumpdown 9-16-26

After closing up BSC9 yesterday we started pumpdown of the EX volume this morning using the two mobile ISP1000 scroll pumps.

There was minimal overpressure in the system, so I could not get a good dewpoint measurement of the blow down air.

It took ~6 hours to rough the system down from atmosphere to ~500 mtorr, where we start the turbopump.

The cooling water was adjusted on the turbopump stand so that the pump and controller pressures were <= 40C. Once the turbo was at full speed and the inlet pressure ~5e-5 Torr, I switched the backing pump to the dedicated ISP250 on the turbo stand.

Setpoints were adjusted to 5E-2 Torr on Channel 1 (Foreline) and 5E-5 Torr on Channel 2 (Turbo inlet).

We will need to leak check the TMDS port gate valve since it was removed to verify the gate o-ring was in place.

 

Also, the EX cleanroom was powered off at ~3:10 pm local time.

Images attached to this report
Comments related to this report
gerardo.moreno@LIGO.ORG - 18:46, Friday 18 September 2026 (91983)VE

Pumpdown update for X-End volume.

At this point only the turbo pump continues to pumpdown.  See attached plot for progress.

Images attached to this comment