Reports until 18:24, Friday 10 January 2014
H1 SEI (INS, SEI)
jim.warner@LIGO.ORG - posted 18:24, Friday 10 January 2014 - last comment - 19:18, Friday 10 January 2014(9216)
HEPI Position loops installed on ETMX

Lots of work on ETMX HEPI today. Because of the potential for HEPI pump glitches to feed into the BSC ISI's St1 T240s, we worked on installing position control on HEPI. These loops are now working and we have left the entire SEI platform (HEPI & ISI) in an isolating cofiguration. This does mean that commissioners will have to enter their offsets in a somewhat different manner, but Fabrice has explained it to Kiwamu. We have also attempted to put HEPI back in it's tilted state, it's not exactly where it was, but its pretty close. Monday, we will have to update safe.snaps for HEPI.

Comments related to this report
hugh.radkins@LIGO.ORG - 19:18, Friday 10 January 2014 (9217)

The tilting required to get the ETMX TMS pitched back to the corner is now done as usual in that the value is in the target of the BIAS screen.  This value is -610000.  Please call me if there are issues--H