(Corey, Doug C., Eric, Jim, Ken, Mike V., Vincent)
Here is an update of work from the last few days.....
BSC#1
After floating both stages last week, work continues here to get the ISI ready for Vincent to test.
-
Clean cabling has been connected and run.
-
Holes were drilled into the Test Stand structure to mount (3) cable feed-thru interface boards.
-
Interface boards have been installed.
-
Vertical GS13's have had dowel pin holes on the base plate reamed out (these holes turned out to be too small for the Dowel Pins which are on the mid-plate of Stage2).
-
(3) Vertical GS13's were installed.
BSC#2
-
Doug & Ken reamed out holes on the Stage-2 Top-Facing Optics Table (the machine shop forgot to mill these out for us! We've had to do this for BSC#1 as well).
-
Small Actuators are practically complete (some of the mounting hardware still needs to be attached)
-
Large Actuators are about 60% complete
-
Lockers are being built.
Today we hope to get to a point where we can start assembling walls for Stage1 & Stage2 in parallel.