Monday 13 JAN 2014
-Windy conditions all day, 20-30mph
-X-Arm impassable due to tumbleweeds. Y-arm passable with caution. Bailing crews at work on both arms.
-920-940 Apollo using sawzall at BSC1
-919 AndresR looking for parts in around HAM4/5
-950 EY transitioned to laser HAZARD for welding operations
-957 LVEA transitioned to laser SAFE
-1000 Koji/DickG/DanielS working on electronic racks at H1PSL; unk completion time (1200?)
-1009 Bubba opening LVEA outside exit door at NE corner
-1019 TravisS, BetsyW, Giles and JasonO begin welding ops at EY
-1026 -1200 Hugh/JimW/Mitch working at HAM4
-1030-1600 Filiberto working on documentation at HAM6
-1244 DaveB and JimB swapping out hardware watchdog in the CER
-1330-1600 Mitch, JimW, HughR continuing SEI work at HAM 4
-1358-1445 JohnW, Sheila going via offroad route to EX
-1459 Sheila, Alexa, DanielS to EX (on the road to MX, then offroad)
-1512-1545 JimB and DaveB returning to CER to work on HWWD