::: EX is Laser HAZARD ::: LVEA is Laser SAFE ::: EY is Laser SAFE ::
EY: Travis doing Welding clean-up & possible Quad work (probably most of the day)
Dust: Dust #9: Calibrate failure (notified Patrick)
PSL: Went through PSL Checklist. Have a "check diode chiller" WARNING & sent an email to the PSL group email. Doug filled it up around 11:30am
Day's General Activities:
-
Before 8am: Balers continue: at LVEA, may continue with X-arm
-
8:30-1000: EX Dressing of ISC cables (Filbertro/Aaron)
-
8:50-9:30: Jeff/Andres in LVEA looking for stuff
-
10:05: Joe D (& possibly Chris S & Rick S) working in H2 PSL room on Periscope Assy
-
10:10-10:50: Andres working on SR Suspension
-
10:15: Apollo scoping out Nitrogen piping
-
10:20-11:30: EY RF ISC cabling (Filiberto/Aaron)
-
10:25: Adjust ADC Channel Numbers feds to HAM4/5 models (Hugo)
-
11:20: Praxair filling CP6 (MX)
-
1:18 - 1:51: Call for 100Area Take Cover Drill
-
Afternoon: Apollo removing piping under the H2 Output
-
1:30: HAM4 work: connecting/check out sensors, balancing, cable dressing, etc. (Hugh, Mitch)
-
1:45: Jeff/Andres searching for SUS tooling at LVEA, EX, EY
-
1:58-3:12: Powering Seismometer (Filiberto)
-
3-4pm: Rick & Keita searching for beam dump in H1 PSL