thomas.vo@LIGO.ORG - posted 09:23, Friday 17 January 2014 - last comment - 09:32, Friday 17 January 2014(9349)
Richard into PSL @ 9:20 AM PT
Install control converter for Lighthouse dust monitors.
Comments related to this report
thomas.vo@LIGO.ORG - 09:32, Friday 17 January 2014 (9352)
Work finished at 9:30 AM PT.