(Corey, Eric, Jeff, Jim, Mick V.)
Stage2 Work
After part of Stage1 was put on the Optics Table, continued to build up Stage2. The Mid-Plate was installed, Upper Hex Assembly installed, and then we moved back to Stage1 work....
Stage1 Work
After the Stage2 Mid-Plate/Upper Hex Assembly was installed, the Stage1 Close-out Plate & Close-Out Plate Cover were installed (still need to put in bolts and torque the latter).
Subassembly Status
Misc.
Top-Facing Keel plate was put on the Granite Table (lots of helicoiling for it!)