Here is the list of commissioning task for the next 7-14 days:
Green team:
-
Measure difference between red and green locking offsets.
-
Commission the common mode hand-off including the AO path.
-
Make an exact measurement of the cavity length.
-
Complete the noise model for ALS X by adding PDH and COMM servos.
-
Commission a relief script for the angular offsets in the initial alignment controls.
-
Commission the length feedback path to the ETM top suspension point to suppress microseism.
-
Asses the status of the reference cavity temperature controls.
Red team:
-
Angular decoupling optimization for PR2 and PRM.
-
Lock the PRMI using 1f and 5f signals.
-
Lock the PRMI using the 3f signals.
-
Arm cavity alignment for the red beam.
-
Mode matching measurements using ISCT1 and maybe IOT2R.
-
Mode cleaner characterization: Absorption, heating and scattering.
-
Track down the 0.5 Hz feature in the seismic isolation system.
-
Investigate the REFLAIR45 whitening filter issue.
TMS:
-
Repair and exchange the in-vacuum cable for the beam diverter.
ISCTEY (starting next week):
-
Complete the feedthrough panels.
-
Install the on table cabling.
-
Prepare for move to the end station.
-
Check out ALS electronics in EY.