Reports until 21:23, Wednesday 22 June 2011
LHO FMCS
jodi.fauver@LIGO.ORG - posted 21:23, Wednesday 22 June 2011 (965)
In-Chamber Cleaning (henceforth ICC)
The ICC Crew today: Mark Layne, Zack Haux, Chris Soike

We started the morning by inspecting the compressors with John W. and Michael L. The ICC crew had noticed moisture in the air hoses attached to the compressors. After checking the hoses and the filters, John was convinced that the moisture was water condensate and not a threat to our work. He did suggest blowing out the lines both before the beginning and end of work each day so that will be added to the procedure. John and Michael were in agreement that work should proceed.

Tasks accomplished today
-West beamtube dust barrier (iLIGO) installed
-Gaps at the top of north and south dust barriers were filled in
-Condition of chamber documented (pix)
-Pre-work particulate samples taken
-Particulate depletion samples taken
-Soft dome cover removed and soft roof retracted
-2 sections of the collar area cleaned
-Soft door/dome covers re-installed
-Hoses blown out at end of work
-Materials consolidated to provide room for HAM 5/6 door lay-down