Here is the list of commissioning task for the next 7-14 days:
Green team:
-
Noise measurement between red and green.
-
Switch the arm cavity locking to red.
-
Make a mode scan of the red resonances.
-
ETM drive diagonalization
-
Commission the length feedback path to the ETM top suspension point to suppress microseism.
-
Asses the status of the reference cavity temperature controls.
Red team:
-
Center the red QPDs in EX.
-
Optimize 3f locking.
-
Investigate the robustness of the 3f lock in presence of an arm cavity.
-
Start commissioning the alignment system.
-
Optimize the thermal compensation of ITMY.
-
Investigate the REFLAIR45 whitening filter issue.
Blue team (ISCTEY):
-
Complete the feedthrough panels.
-
Install the on table cabling.
-
Prepare for move to the end station.
-
Check out ALS electronics in EY.
TMS:
-
Finish up with beam dumps and alignment.
SEI/SUS team:
-
Improve stability under high performance in ETMX.
-
Continue working on ITMY and BS.