H1 SYS
daniel.sigg@LIGO.ORG - posted 12:53, Monday 10 February 2014 (9951)
Commissioning calendar for next 2 weeks

Here is the list of commissioning task for the next 7-14 days:

Green team:

  1. Noise measurement between red and green.
  2. Switch the arm cavity locking to red.
  3. Make a mode scan of the red resonances.
  4. ETM drive diagonalization
  5. Commission the length feedback path to the ETM top suspension point to suppress microseism.
  6. Asses the status of the reference cavity temperature controls.

Red team:

  1. Center the red QPDs in EX.
  2. Optimize 3f locking.
  3. Investigate the robustness of the 3f lock in presence of an arm cavity.
  4. Start commissioning the alignment system.
  5. Optimize the thermal compensation of ITMY.
  6. Investigate the REFLAIR45 whitening filter issue.

Blue team (ISCTEY):

  1. Complete the feedthrough panels.
  2. Install the on table cabling.
  3. Prepare for move to the end station.
  4. Check out ALS electronics in EY.

TMS:

  1. Finish up with beam dumps and alignment.

SEI/SUS team:

  1. Improve stability under high performance in ETMX.
  2. Continue working on ITMY and BS.