Jennie W
While trying to debug some other SPI readout problems I noticed that the main SPI overview screen had one of the readback channel names wrong.
The 'DISP OUT' block in red at the right of the screen should readout the channel 'H1:SPI-H23_DIFFDISP_DIAG_INMON' and 'H1:SPI-H23_DIFFDISP_DIAG_OUT16' in its bottom row.
These were reading out the channel above 'REFNULL' in boith cases. I corrected this in SPI_CUST_OVERVIEW.adl file and committed to the svn. In the picture the readouts are circled on the right with the channels they readout shown on the left in the filter banks.
TITLE: 07/10 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
IFO is in IDLE for MAINTENANCE
Pumpdown continues - see attached screenshot
Ryan S, Sheila and Daniel also did some work at SQZT7
In other news,
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 14:57 | VAC | Jordan | LVEA | N | Continuing Pumpdown | 23:56 |
| 15:12 | SEI | Shrey | LVEA | N | Seismometer Tests | 18:06 |
| 15:19 | FAC | Dawn, Kim | LVEA | N | Technical Cleaning | 16:00 |
| 16:01 | FAc | Kim | LVEA | N | Technical Cleaning | 16:59 |
| 17:26 | SQZ | Daniel, Sheila, Ryan S | LVEA | N | SQZT7 | 18:19 |
| 18:19 | SUS | Mitchell | LVEA | N | \ | 18:29 |
| 20:19 | SQZ | Ryan S | LVEA | Local | Transitioning to local laser hazard, then SQZT7 periscope mirror moving | 22:37 |
| 20:33 | SQZ | Daniel | LVEA | Local | SQZT7 | 20:39 |
| 20:39 | SQZ | Sheila | LVEA | Local | SQZT7 Periscope mirror moving | 22:37 |
| 20:46 | FAC | Randy | LVEA | Local | Checking on fitted plates | 21:00 |
| 23:09 | PCAL | tony | PCAL Lab | Local | Sorting | 00:09 |
Ibrahim
Got a message at 14:58 UTC to "Check HEPI pump station pressures".
At 14:58,
I checked the End Stations too but nothing was seen (also attached).
TITLE: 07/10 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 7mph Gusts, 3mph 3min avg
Primary useism: 0.01 μm/s
Secondary useism: 0.08 μm/s
QUICK SUMMARY:
IFO is in IDLE for MAINTENANCE
No specific tasks today since it's RDO Friday for most
Corner pumpdown yesterday afternoon (alog 90979)
(Jordan, Travis, Richard, Filiberto, Randy, Gerardo)
Corner pumpdown started Thursday afternoon, around 4:40 pm local time.
We setup the twin mobile ISP-1000 scroll pump stations at the YBM turbo station, we chose this area due to the real estate available, the other 2 stations are a bit crowded. After setting up all of the required equipment the pumpdown was started with procedure E2300169, to setup the turbo pump unit for the pumpdown, then Jordan and Filiberto covered procedure M1300464 to make sure all high voltage DC power supplies were off, then continued following E2300443 to start the pumpdown with the ISP-1000 scroll pumps through the YBM turbo pump. Pumpdown was done for about 2 hours taking us down to 340 Torr. The pumpdown was stopped at 7:02 pm local time for the night.
No issues to report during the startup of the pumpdown, however something to note is that during the blow down of the vacuum envelope the system was not pressurized, last minute work on the different chambers did not allowed to pressurize the envelope.
As per WP 13401. In preparation for upcoming daqd upgrades I'm working to move the run number server off of h1daqscript0 and onto the HA container cluster. I have the new instance running with the current run number database. I just need to configure the framewriters to point to it. I will do that next week. The run number server helps keep the run number that is put into the frames consistent between the two frame writers.
This is a step to retiring the h1daqscript0 machine once we remove the daqd's px dolphin.
TITLE: 07/09 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Preparations continued today for corner volume pumpdown.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 14:39 | FAC | Randy | LVEA | - | Craning pump carts to W-bay | 14:51 |
| 15:13 | FAC | Kim | LVEA | - | Technical cleaning | 16:28 |
| 15:29 | SQZ | Sheila | LVEA | Local | SQZ beam measurements | 17:05 |
| 16:07 | FAC | Randy | LVEA | - | Craning boxes | 17:58 |
| 16:12 | VAC | Gerardo | LVEA | - | Checking on HAM3 annulus | 16:17 |
| 16:26 | PEM | Carlos, Shrey | LVEA | - | Checking on seismometers | 18:26 |
| 16:28 | SUS | Rahul | LVEA | - | Prep for ZM5 swap | 17:58 |
| 16:33 | SAF | Betsy | LVEA | Y | HAZARD/SAFE transitions | 17:10 |
| 16:34 | TCS | Matt | OptLab | - | Looking for stage driver | 16:59 |
| 16:43 | TCS | Camilla | PrepLab | Local | CHETA work | 16:48 |
| 16:43 | SEI | Shoshana | LVEA | Y | CRS health check | 16:56 |
| 16:48 | ISC | Camilla | LVEA | - | Camera can reattachment | 16:57 |
| 16:51 | TCS | Madi | OptLab | - | Checking lenses | 18:46 |
| 16:57 | TCS | Camilla | PrepLab | Local | CHETA work | 17:40 |
| 16:59 | TCS | Matt | PrepLab | Local | CHETA work | 17:37 |
| 16:59 | SAF | Fil | LVEA | - | Safety cabling on HAM1/2 | 22:31 |
| 17:05 | VAC | Gerardo | LVEA | - | Prepping pumps | 21:07 |
| 17:17 | VAC | Jordan, Travis | LVEA | - | Viewport covers at HAM7, HAM3 (Travis out @ 19:23) | 20:09 |
| 17:37 | FAC | Eric | FCES | - | Checking AHU | 17:47 |
| 17:37 | AOS | Mitchell | LVEA | - | 18:10 | |
| 17:40 | TCS | Camilla | OptLab | - | Checking lenses | 17:46 |
| 17:59 | SUS | Ryan C | LVEA | - | Dropping off parts at HAM7 | 18:03 |
| 18:03 | SEI | Jim, Shoshana | LVEA | - | Packing up CRS parts | 19:12 |
| 18:07 | SAF | Richard | LVEA | - | Checking in w/ VAC | 19:31 |
| 18:11 | SUS | Rahul | LVEA | - | Unplugging ZM5 breakout board | 18:17 |
| 18:47 | TCS | Camilla, Matt | PrepLab | Local | CHETA work | 19:13 |
| 19:17 | SEI | Shoshana | LVEA | - | Putting away parts | 19:24 |
| 19:29 | FAC | Randy | LVEA | - | Craning skid box | 20:29 |
| 19:49 | SUS | Rahul | LVEA | - | Resistance measurement at HAM7 racks | 20:41 |
| 19:53 | PEM | Carlos | LVEA | - | Checking seismometers | 21:53 |
| 21:07 | VAC | Jordan, Travis | LVEA | - | Pumpdown prep | Ongoing |
| 21:10 | TCS | Madi | OptLab | - | HWS lens measurements | Ongoing |
| 22:15 | SAF | Richard | LVEA | - | Checking on VAC | 22:31 |
| 22:20 | TCS | Camilla, Matt | PrepLab | Local | CHETA work | 23:07 |
| 22:31 | SEI | Jim | CER | - | Checking electronics | 22:44 |
| 22:44 | SUS | Rahul | LVEA | - | Turning on ZM4/5 chassis | 22:52 |
| 22:58 | SEI | Jim | LVEA | - | Troubleshooting L4C | 23:17 |
| 23:07 | TCS | Camilla | OptLab | - | HWS lens measurements | Ongoing |
| 23:11 | PEM | Carlos, Shrey | LVEA | - | Seismometer checks | 23:20 |
A couple days ago I noticed that HAM3 HEPI H4 L4C had almost 0 signal compared to the other L4Cs on that chamber. I didn't have time until this afternoon to look at it. L4C proof masses can get stuck (or something) so I tried waking it up by tapping on the L4C casing or (gently) slapping the locked crossbeam. Neither seemed to work, so I powered off the interface chassis on the pier, and swapped the cables between the H4 and V4 L4C. This seemed to work. The H4 L4C still worked when I swapped the cables back. Probably need to watch this down the road, maybe think about adding a famis task to monitor, because this is the second "stuck" L4C I've found on the IMC HAMs.
Matt, Sophie, Camilla
CHETA uses a Linear translation stage with a 100mm range. +50mm is moving L2 upstream (towards M3), -50mm is moving downstream (towards M4).
Currently if a position out of this range is requested, the translation stage becomes frozen. The only way we've found to reset it is to unplug from the chassis and plug into the Newport Driver (ESP300), turn MTR ON and then press home for Axis 1. We are working with the Beckhoff team to hard code limits so this will not happen in the future.
Chamber side testing of the PSAMS shows that the Strain Gauge (SG) voltage of ZM5 has railed at -28V (which indicates an open circuit.). I am able to drive and measure the PZT voltage from 0 to 200V, however the strain gauge voltage always remains at -28V (strangely the SG resistance still shows the correct 700ohms and 360 ohms values) - so I am not sure how, but perhaps there is some loose connection.
To further confirm this - I tested ZM4 (which shares the chassis with ZM5) and I was able to drive the PZT voltage from 0-200V and correspondingly get SG voltage of 3.5 - 7.7V (which ties up with my previous measurements in performed 2023). To rule out an issue in ZM5 electronics chain I hooked up ZM5 to the healthy electronics chain of ZM4 and repeated the above measurement and still obtained an open circuit for ZM5.
Hence, ZM5 PSAMS is broken and needs immediate replacement. Work to replace PSAMS is currently ongoing.
Per FRS 38164, the unused viewport located at A1F1 and A2F1 on HAM7 have been removed and blanked off. These viewports are being moved to HAM3, so serial number, etc. will be recorded in a separate aLog.
The HAM3 A1F3 viewport was a coated ZV-800 which had many small scratches on the vacuum side of the window, we replaced this with the HAM7 Uncoated ZV-800 SN R136. The A1F4 viewport was a D1100999 High Quality viewport (O-ring sealed), it was determined that this port no longer needs the high quality viewport and was then swapped with the other removed viewport from HAM7 (ZV-800 Uncoated R134).
Per Betsy, both of these ports are only used for views inside the chamber, so Uncoated viewports could be used to replace the two coated viewports which were removed.
The viewports removed from HAM3 will be inspected on the bench and if they pass inspection criteria they will be put into spares inventory.
After confirming with Jordan, the comment above has a small typo: The viewport that came off of HAM7 port A2F1 is recorded in LHO's inventory lists (LIGO-T1200220 and LIGO-E2400096) as SN R146 (not R136 as listed above).
As a visual indicator of these swaps:
HAM7 A2F1 SN R146 → (removed and moved to) → HAM3 A1F3
HAM7 A1F1 SN R134 → (removed and moved to) → HAM3 A1F4
Late entry for VAC - Gerardo, Travis, Jordan, Tyler and Randy put the doors on HAM3 yesterday afternoon. They did -Y first, then +Y. Getting the doors craned over and transferred to the Forklift could only happen at the corner near the TCSy table, so was a tight fit at that transfer point.
These were the last doors to go on for this vent window.
Well done team.
(Travis, Jordan, Tyler, Randy, Richard, Gerardo)
We did not touch the blue cross members.
Doors went on as smooth as they could. The first door -Y side, where the bulky optical lever next to HAM3 adds a degree of difficulty to install the door (maybe more than one degree). Nothing to report, flanges look good on both sides, door and chamber, O-rings have lots of tiny metal shavings incrusted on them, however they did not cross the sealing surface, we opted not to poke at them. We found a small hex key inside the chamber, finders keepers. The second door for +Y side went on good, after we figured the angle of attack for the forklift, we running out of turning room next to this chambers. On this side of the chamber as we were removing the aluminum O-ring protectors a small section of O-ring decided to pop out of its groove around 6 O'clock, when Jordan was working to place the O-ring back in he found a tiny, very tiny metal washer, he grabbed it and we handed it to Richard, we also found a peek wire clamp at the bottom of the chamber (example shown at the bottom of the second photo), that one we just tossed out of the chamber. No issues noted with the flanges on door and chamber. O-rings have similar particulate on them as the O-rings on the -Y door, did not poke at them either.
For both doors we inspected their respective viewports from the inside, we found a viewport with a high density of scratches on the coating, and we decided to remove it and replace it, see entry Travis' entry.
A nice feature that we noticed and made world of difference from previous installations is the enhancement to the cleanroom, it sits a bit taller allowing for good clearance of forklift's mast during the installation of both doors, and we did not have to move the cleanroom.
Ken, Preeti, TJ
We've made transfer functions to see and compare the level of cross coupling between P and Y at both sites for the top stage of BBSS. The L1 traces were rescaled to match the H1 magnitude for the PtoP comparison at 0.1Hz. The scaling factor was 3.72. This was done to compensate for the DAC differences between the sites. All of the L1 traces were multiplied by this scale factor. All plots are found in the attached PDF.
TF plots corrected to have consistent axis scales
LHO data taken from /ligo/svncommon/SusSVN/sus/trunk/BBSS/H1/BS/SAGM1/Data/2026-07-06_1500_tfs. BSC2 ISI was locked and measurements are taken in air
LLO data is taken from /ligo/svncommon/SusSVN/sus/trunk/BBSS/L1/BS/SAGM1/Data/20260706_BBSS_1TOR. BSC2 ISI was fully isolated and the chamber was under vacuum at about 1 Torr.
This morning, with Mitch and Shoshana, I went into the nozzle between HAM3 and BSC2, via the HAM3 door to fix the broken H3 actuator. I had to remove a couple baffles to get in and get access to the hatch over the H3 actuator, once the hatch was off, I found the pin on the back of the actuator terminal block had come lose, probably when I was in there to do the CPS upgrade. I probably should have checked this wire after I finished that swap, but it there was no way to see that anything was wrong, I had to grab the wire and pull on it. Once that was reconnected and I put everything back together, we did a quick chamberside test and H3 was driving again. I've now completed close out tfs, attached image, and run a CPS linearity measurement to check the new cpses. The linearity test plots failed in a way that didn't save the data, but I do have the terminal output of the test which agrees with HAM7:
'Actuator H1 to CPS H1'
Linear regression y= 1.862 x + 245
'Actuator V1 to CPS V1'
Linear regression y= 1.890 x + -771
'Actuator H2 to CPS H2'
Linear regression y= 1.845 x + -271
'Actuator V2 to CPS V2'
Linear regression y= 5.105 x + 2771
'Actuator H3 to CPS H3'
Linear regression y= 5.073 x + 1543
'Actuator V3 to CPS V3'
Linear regression y= 5.119 x + 2882
At some point after doors go on, I will want to try to fix the cps linearity test script and run it again, among the many other measurements I will need for HAM3.
Arnaud helped me get Huyen's update of this script, which worked after restarting a stale matlab session. Linearity of the new cpses still look good, slopes of cps vs actuator output are all consistent in a way that makes sense.
'Actuator H1 to CPS H1'
Linear regression y= 1.865 x + 225
'Actuator V1 to CPS V1'
Linear regression y= 1.883 x + -803
'Actuator H2 to CPS H2'
Linear regression y= 1.849 x + -316
'Actuator V2 to CPS V2'
Linear regression y= 5.521 x + 3170
'Actuator H3 to CPS H3'
Linear regression y= 5.470 x + 1383
'Actuator V3 to CPS V3'
Linear regression y= 5.556 x + 3076
I will try to get long tfs of the ISI this weekend, to see if loops need touching up.
[Jim, Shoshana]
The CRS is currently aligned, suspended, balanced, and unlocked on HAM3!
I aligned each HoQI as well as I could on the table, HoQI2 is slightly better than HoQI1, but it shouldn't be an issue. I also lowered the resonant frequency as much as possible, but I ended up running out of mass that I could easily remove from the bottom, so right now the resonant frequency is at ~25Hz. It's possible this raised frequency is because these flexures (21, 22) might be slightly thicker than the previous ones as they came from a different batch.
Tested the picomotor, moving the X value positive moves the mass to the left (towards HoQI1). We had it do three revolutions in both directions and the picomotor was able to couple with the mass adjuster while at maximum range (tilting fully to either side). We've also discovered that the GS13s outputs go crazy when the picomotor is running, which is something to be aware of.
We've verified that voltage makes it to the damping capacitor plates on either side. We've also confirmed that in the HOQI{1,2}_DIST data increases as the corner cube gets closer to either interferometer (i.e. when the left corner cube (wing) gets closer to HoQI1, the HoQI1_DIST channel data increases)
Attached are various photos of the CRS on the table for future reference, as well as a guide to all the balance masses currently on it.
Notes on CRS commissioning tonight :
The overnight measurement is slightly better, but we are missing coherence below 15mHz which is probably due to too much air currents. The measurement is still good enough to fit and allow us to extract some physical parameters. Attached are updated data, scripts and the latest fit.
The zpk coefficients for this fit are :
zpk([0.0009 + 0.0766i 0.0009 - 0.0766i],[-0.0005 + 0.1584i -0.0005 - 0.1584i],1.0262)
My fitting script agrees. Looks like a delta value of 10 um.
CRS laser was turned on for ~5 minutes this morning to make sure the flexures didn't break while the doors were being put on HAM3, and it survived!
It's still pretty rung up, but that's unsurprising as there was a good amount of motion going on around the chamber
Filing a late report, last week I measured the resistance of the strain gauge on the PSAMS for ZM5 suspension in HAM7 chamber. This is to investigate the inconsistent behavior (voltage drop/open loop issues) of the strain gauge attached to the PSAMS on ZM5 - details posted in LHO alog 90783.
To measure the resistance of the strain gauge and confirm if anything is broken, I decided to check it chamber side (on the racks in the LVEA). To locate the chassis in the LVEA I referred to the A+ SUS HAM 7 (sush7) System Wiring Diagrams (D2000202_V12), page 04 (ZM5, M2 PSAMS). This document pointed me towards SQZ-R1, Slot U2, where the chassis D2000555 was located. At first, I switched off the chassis and then unplugged cable no 6 which was connected to the JIG Box (J8-Metal PCB Jumper Box DB25 Male female). Then I connected a breakout board to cable no 6. For measuring the resistance of the strain gauge, I looked into D2000383 to find the correct pins (Camille Makarem (CIT) also talked to the vendor and sent me the pin number, as given in E2500225). This is as follows,
700 Ohms between Ex+ and Ex-
350 Ohms between signal+ and Ex-.
From the pinouts in https://dcc.ligo.org/LIGO-E2500225, this should be
700 Ohms between pins 1 and pins 3/2
350 Ohms between pins 6 and pins 2/3
Chamber side this comes to be pin 12 & 25 and pin 11 & 25. Using a multimeter, I got the following readings,
Pin 12 & 25 = 706 Ohms (looks good)
Pin 11 & 24 = 360.5 Ohms (looks good)
The chassis was powered on after the measurements were complete and cable 06 reconnected to the JIG box and secured using two screws (which were missing). The above measured numbers are as per the strain gauge manufacturer. However, It could be possible that the soldering is coming off and giving us open loop sometimes, if not all times. We will continue to investigate this issue and if we are not able to fix it then the plan is to replace it with a spare unit. A spare ZM5 PSAMs unit is currently being prepared by Camille Makarem and should be shipped to LHO within a day or two. We will then start working on swapping out the faulty unit with spare one, in-situ.
Typo above - correct pins are 12 & 24 = 700 ohm
and pin 11 & 24 = 360ohms
(Jordan, Owen, Jake, Gerardo)
The cryotrap cooldown continues, we continue to pump on the cryotrap volume with a turbo pump, the turbo is backed with a SS500 aux cart.
Small changes were the removal of the calibrated leak from the RGA tree, along with the removal of other components in preparation to install an incoming small ion pump next week.
Current pressure in the cryotrap volume is 7.38X10-10 Torr.
Jordan, Jake, Owen
The RGA tree was removed and replaced with the dedicated 75 l/s Starcell ion pump and a pumpdown port for the pump tree.
All flanges were helium leak tested, no He signal above the leak detector background were found. (~1.5E-10 Torr-l/s)
Volume is currently being pumped by a small aux cart, and the ion pump will be powered on tomorrow. The volume will then be introduced to the cryopump volume once the pump pressure reaches ~E-9 Torr on ion pump alone.
Update for CP1.
Last Tuesday 7/7/26, Jordan removed the turbo pump and introduced the small ion pump to the CP1 vacuum volume, this closed the warm up of CP1. Attached plot of small ion pump controller and pressure reported by the cold cathode at CP1.
Due to a mistake in past CHETA models there is more astigmatism then expected on the tables and a change in beam size at the ITM. The astigmatism can be fixed by rotating L1 around the vertical axis and the beam size can be changed by movind L2 using the translation stage in each setup. Using a modified Fintrace model the required rotation angle and translation for each table as they are currently populated at LHO (0922, 0918) and LLO (0919, 0851) have been calculated and are shown below.
The tables below give the current astigmatism and then the angles and translations such that the x and y beamsize on the ITM is 52.7mm with no astigmatism.
This code is avaliable in the CHETA modelling repository.
| Unit | Current astig [mm] | Rotation angle of L1 [deg] | Translation [mm] | ITM wx [mm] | ITM wy [mm] |
| 0922 | -7.69 | 10.17 | -0.12 | 52.7 | 52.7 |
| 0918 | -4.02 | 11.84 | -12.89 | 52.7 | 52.7 |
| 0919 | -7.55 | 12.17 | 3.81 | 52.7 | 52.7 |
| 0851 | -5.76 | 11.13 | 3.73 | 52.7 | 52.7 |
Without translating of L2 astigmatism can be removed but the beam size is still unoptimised.
| Unit | Current atig [mm] | Angle [deg] | ITM wx [mm] | ITM wy [mm] |
| 0922 | -7.69 | 10.17 | 52.75 | 52.75 |
| 0918 | -4.02 | 11.18 | 55.39 | 55.39 |
| 0919 | -7.55 | 12.03 | 50.95 | 50.95 |
| 0851 | -5.76 | 11.24 | 51.80 | 51.80 |
Sophie updated these predications to minimize astigmatism, see attached.