Writing this alog to clarify some mistakes we have made regarding the naming of DCPDs. Jeff clarified to us on call this morning that the naming convention is A- photodiode on reflection, B- photodiode on transmission.
Therefore, here is the now corrected information about which high QE photodiodes are installed where, along with cabling and pin numbers:
OMCA (SN 103)
OMCB (SN 105)
Fri Mar 27 10:10:14 2026 INFO: Fill completed in 10min 10secs
I've added a "degraded state" indicator to the VACSTAT block on the CDS Overview MEDM (magenta oval in attachment). This circle is either the same light green as the block colour, or is a darker green to show at least one gauge has been disabled.
Currently we are running with HAM1 PT100 disabled in VACSTAT due to the vent.
The VACSTAT detailed MEDM (snippet in lower part of attachment) has a "NUM_GAUGES_DISABLED" line added, which turns RED if non-zero.
TITLE: 03/27 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 4mph Gusts, 1mph 3min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.27 μm/s
QUICK SUMMARY:
Since yesterday, we have received an answer from Ali and Keita, that the determination is that the cathode and anode pins are in the correct location. There is a longer explanation about what's going on here and which diagrams are wrong, but I will leave that to them. Therefore, the only cable work that needs to be done is to adjust the pins on our "bad" cable, and then switch the DCPD cables between OMCA and OMCB.
Morning (no cable work):
Oli and I pulled the first contact that we left from yesterday. We just need one 50/50 45 deg AOI mirror for BHSS, and we were able to completely clean two of this type. More of these mirrors will be needed for the greater BHD layout, so Oli and I need to revisit the other three that still are not clean. For now, they are stored on the flow bench in clean single cases.
We went to begin the BHSS alignment, and found that no laser beam was coming out of the fiber. Some time between this alog, when Camilla and Oli aligned the beam into the fiber, and now, the beam was misaligned again. We think one of the mirrors to the fiber coupler was bumped. Correcting this took a little while. Oli had to leave, so Keita and I continued with the alignment. Luckily, our downstream alignment is still good- with the iris alignment template placed on the BHSS, we can see the beam comes down the center of both irises to OMCA.
Most of the beam reflects off the OMC, so Keita and I started turning up the power into the fiber. At some point, we turned up to 20 mW coming out of the fiber. We could see a faint beam transmit from the input coupler and make it to the output coupler. However, we still had a hard time seeing any beam make it to the DCPDs, probably because the power is still very low. We set up a beam block of the OMC REFL path for now, since it just goes right back off the suspension. At this point, we realized it's probably not a good idea to put so much power into the fiber, so we lowered the power again to have about 2 mW coming out of the fiber.
Afternoon (cable work):
Keita and I proceeded to fix the cables. We first checked which cables went to which pins:
Cable D2300119 (for OMCB): longer is on trans PD, goes to pins 4/5, shorter on refl PD, goes to pins 1/2
Cable D2300118 (for OMCA): longer is on trans PD, goes to pins 1/2, shorter is on refl PD, goes to pins 4/5
We confirmed that this is the correct wiring according to D2200276
Keita opened up cable D2300119, as this is the cable with incorrect wiring- case was wired to pin 2 and pin 5 instead of pin 6 and 9
We confirmed that the cathode is correctly wired to pins 1 and 4, so we only needed to swap 2/6 and 5/9.
Keita proceeded to switch the pins (this is a very short sentence to describe a long and painful process of removing various peek parts, poking pins through holes and resetting all the peek parts once finished)
Keita reclamped the lower part of the wires and we decided that we should clamp it very tight, as there were no gaps in the clamp on the other cable.
We then swapped the cables, as 118 was incorrectly placed on OMCB and 119 on OMCA. We decided to unscrew the PCB assembly on the back of each tombstone, and then swapped cables, paying attention to which cable went to trans and refl. Note: plugging the PCB assembly back into the DCPD pins is much much easier than inserting the DCPDs from the front.
We then decided to confirm the wiring was correct so we:
- checked that the case of each PD was wired to pins 6 and 9 (pass)
- checked the diode polarity was correct betweens pins1/2 and 4/5 (pass)
- checked that there were no shorts between any of the pins in the cable (failed for cable 119)
We found a short between pin 3 and 9 on cable 119. We removed the PCB assembly from the back of the DCPD tombstone and checked again, still a short. Keita then removed the lower part of the dsub9 assembly where the wires are clamped, and there was no longer a short between pin 3 and 9. We found one wire that was a bit stripped (see photo), but this was the wire for pin 4, so that didn't explain the problem. We were not able to find anything that could cause short between pin 3 and 9. We decided that maybe the pressure of the clamp caused this problem, so Keita reclamped the wires but less tightly, no more short. We checked one more time for case wiring, polarity, and shorts and all tests passed. Done!
I took some photos of the BHSS before we started work. Here are a few to show the progress so far. OMCA was uncovered before the photo, OMCB still covered by the butterdish. All the optics in the center are randomly attached. Platform is still locked down. Tagging EPO.
Travis, Jordan
HAM1 was vented today per M1300464 and E2300169, no pressure change in the corner during the venting. Dewpoint and particle counts collected prior to air admittance (-43C dew point).
Once the laser tables were moved away from the chamber, we vented the annulus system and all but 4 bolts were removed from both +Y and -Y doors in prep for door removal tomorrow.
Closing WP 13123
TITLE: 03/26 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: HAM1 was vented and the bolts have been broken, doors should come off tomorrow. BHSS work continues, and the LVEA is now in Upgrade Laser Safe.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 14:50 | FAC | Nellie | LVEA | N | Tech clean | 16:09 |
| 14:52 | FAC | Kim | LVEA | N | Tech clean | 16:09 |
| 15:07 | FAC | Randy | LVEA | N | Checks around HAM1 | 15:35 |
| 15:54 | ISC | Betsy | LVEA | N | Parts check/search | 16:09 |
| 16:10 | FAC | Nellie | MidY | N | Tech clean | 16:52 |
| 16:11 | FAC | Kim | MidX | N | Tech clean | 17:28 |
| 16:28 | VAC | Travis | LVEA | N | HAM1 purge air dewpoint particle checks | 18:46 |
| 16:28 | FAC | Randy | LVEA | N | Craning, checking out handrails | 18:57 |
| 16:31 | FAC | Tyler | LVEA | N | Join Randy | 16:46 |
| 16:31 | BHD | Elenna, Oli, Keita | Optics lab | LOCAL | BHSS work, first contacting optics Oli out 18:55 | 20:03 |
| 16:39 | VAC | Jordan | LVEA | N | Join travis, HAM1 vent prep | 18:46 |
| 16:40 | FAC | Mitch | LVEA | N | Join Randy | 17:25 |
| 16:52 | FAC | Nellie | EndY | N | Drop off water | 17:49 |
| 16:56 | EE | Fil | LVEA | N | Cable termination, PSL racks | 20:15 |
| 17:27 | SUS | Jeff | LVEA | N | HAM3 check with CDS team | 17:30 |
| 17:27 | OPS | Betsy, Tony | LVEA | N | 17:54 | |
| 17:28 | FAC | Kim | H2 | N | Tech clean | 17:39 |
| 18:18 | EE | Tony, Marc | VAC prep/Optics lab | N | Cabling | 19:20 |
| 18:26 | FAC | Kim | LVEA | N | Tech clean | 19:16 |
| 18:37 | EE | Thomas | Vac prep lab | N | Make some invac cables | 23:20 |
| 18:53 | FAC | Tyler+contractors | MidY | N | Inspections, dpt of health+1more... | 20:23 |
| 19:43 | SQZ | Sheila | LVEA | LOCAL | SQZT7 local laser hazard for Green alignment | 19:59 |
| 19:58 | FAC | Randy | LVEA | N | Work on BSC2 platform | 21:25 |
| 20:13 | SQZ | Sheila, Sophie | FCES | Y | SQZT8, LOCAL hazard | 21:51 |
| 20:29 | EE | Marc, Tony | Optics lab | N | Cable testing | 21:17 |
| 20:49 | VAC | Jordan, Travis | LVEA | N | GV7, swap regulator | 21:50 |
| 21:11 | EE | Fil | LVEA | N | HAM3 cable terminations | Ongoing |
| 21:19 | BHD | Elenna, Keita | Optics lab | LOCAL | BHSS work | Ongoing |
| 21:39 | OPS | Betsy, Tony, Randy | LVEA | N | Turn off the SQZ laser and move the Tables by HAM1, for real this time, randy out 2215 | 22:37 |
| 22:05 | EE | Marc | LVEA | N | Join Fil in cabling | Ongoing |
| 22:08 | PEM | RyanC | CER | N | Grab DM cable | 22:15 |
| 22:37 | VAC | Jordan, Tony, Travis | LVEA | N | Anulus ion pump, then break bolts on HAM1 | Ongoing |
17:00 UTC Jordan went over the VAC checklist and I confirmed the picomoters were off, the JAC PZT scan was disabled and its Driver offset was 0, and that the ISI and HEPI were in their safe states.
17:08 UTC HAM1 pressure starts to rise
17:11 UTC ISI HAM1 wd tripped
20:27 UTC Red alarm Dustmon6 by HAM6, 10.8k and 17.5k counts for the 0.3 and 0.5 um particles
21:58 UTC The SQZ laser was keyed off, The LVEA is now in Upgrade Laser Safe
22:00 UTC The tables by HAM1 were moved
23:05 UTC HAM2 ISI tripped from the HAM1 crew breaking the bolts, and the HAM1 sw watchdog
23:09 UTC RM1 and RM2 wd tripped, the HAM1 CPSs were glitching as well
23:31 UTC HEPI HAM1 watchdog tripped
I reset a PT100 VACSTAT alarm at 10:12 and disabled HAM1.
Thu Mar 26 10:11:54 2026 INFO: Fill completed in 11min 50secs
On Monday, Randy, Jordan and the FAC team craned the HAM3 cleanroom over into the appropriate place for HAM3 entrance for installation planned next week. The cleanroom is now up against the BSC2 Platform. As well, Kim and Nellie have been cleaning the HAM3 cleanroom. On Tuesday, Randy craned into place and attached the new Installation Platform Sections G and F to the BSC2 platform. Handrails will be installed next. These platforms allow access from the eMod cleanroom to the BSC2 cross flow Dome cleanroom and platform, as well as provide added walking space between BSC2 and BSC3. They also form 2 sides of the BSC3 platform which will be needed in subsequent vents. Recall, this new LHO BSC2 Installation setup is part of the readiness review for install at https://dcc.ligo.org/E2400329-v1, and is part of a bigger plan to add sections around BSC3 and BSC1 to make a larger platform instead of moving them and encountering interferences other items like racks, trays and equipment.
Tagging for EPO photos.
TITLE: 03/26 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: USEISM
Wind: 6mph Gusts, 4mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.55 μm/s
QUICK SUMMARY:
"It is a truth universally acknowledged, that a single man in possession of a good fortune, must be in want of a wife"
- Jane Austen, opening line of Pride and Prejudice
But unfortunately for both us and them, sometimes those men are winged termites in the Optics Lab.
As Elenna and I were cleaning up our work in the back optics table this afternoon, we noticed a few winged termites, and ended up finding maybe almost 10 in total walking around on the floor in the back area of the optics lab near the wall mounted cabinets between the two cleanrooms. We got rid of them but couldn't find where they had come from. I'm wondering if they're maybe coming from an opening under one of those cabinets? Last year this happened but those came out from under the flow benches along the wall - not sure if this is part of that same colony that survived or a different colony.
Yesterday (Mar 26), as we cleaned up after BHSS work, I looked around for more termites. I found only one in the corner of the lab near a circle of power cables, just underneath where we hang BNCs and other cables. It appeared to be dead. Not sure if it's new or I missed it the day before.
To summarize the ongoing issues from yesterday:
Keita and I have decided that swapping cables can possibly be done without removing the DCPDs. We're going to determine OMC A and OMC B based off of the PZT cable, and then swap the DCPD cables. We're waiting to hear the final verdict on the diode polarity to do pin adjustments and cable swapping.
In the meantime, Oli and I installed OMCB on the suspension and bolted it down using the OMC alignment template. We have placed the butterdishes over OMCA and B, but we haven't secured them yet with viton clamps while we continue to do work on the OMCs. The cables are only loosely clamped.
Next, Oli and I worked first contacting the remaining optics for BHSS- two HRs and one 50/50 splitter. The HRs were finished today, installed in their mounts, and placed randomly on the platform. The 50/50 splitter is still being FCed and should be ready in the morning. Once that optic is installed, we will proceed with the alignment of the OMCs and optics.
One vertical clamp is still missing from OMCB, but we should be able to install it once the helicoils and such arrive.
Sheila, Camilla.
We decided to pause on looking for the FC alignment and look at SQZ alignment into the IFO. To check our irises and possibly look for scattering shelves.
Locked SEED_DITHER with 75mW into fiber. Moved ZM3 to get OPO_IR PD up to max 0.9mW. Opened BeamDiv and after aligning SRM, mis-aligning SR2, could see beams on AS_A,B and C. AS_A and B had a similar size ~60 to reported before (e.g. 86965), but there was less power on AS_C: 4e-4 rather than the previous 7e-4.
We used Ryan's DRMI time from 89573 to put OM1, OM2 and SRM back. The with the SQZ SEED injected, we tried to use SQZ centering loops to center on AS_A and AS_B, this didn't work quite as expected. ZM4 kept saturating although these loops had worked Janaury 19th, before moves were done on the VOPO to help with clipping e.g. 88966.
Then went back to alignment on Jan 31st with 88976 with ZM1,2,3, 4,5,6 FC1. And took OM1,2,SRM to the January 19th positions. However here we saw no light on SQZT7 OPO IR PD, HAM7 WFs or in HAM6 on the AS_A,B,C diodes. This was done at 23:10 UTC. Comparisons of osems attached. The sliders to get these osems values are fairly different, see attached, so I also tried going to these slider values, that gave me some light on SQZT7 IR PD, HAM7 WFS and FCES with SEED injected, see attached. HAM6 AS diodes saw nothing.
Sophie, Camilla
This morning, starting from this vented slider alignments, I randomly moved ZM1 until we had IR and green light on the FCES PDs. I misaligned FC1 and FC2 to single pass light. Then I could move ZM3 in pitch from P,Y (-324,-200) to (-506, -200) to get max light on IR FCES PD. In both these positions, we get scattered light on the camera and light on both IR and green PDs. This makes me think the best position in pit h is in the middle of these, ZM3 (-415, 200). We tried to repeat this excise in yaw but only could get the one edge. Even after movingZM1 in YAW in both directions, I couldn't find the other side of the yaw clipped beam. Attached is the sliders when we thought we were centered in pitches and clipping the coating on one side in yaw.
We need 4 things for the squeezer to operate:
Continuing from where Sophie and Camilla left off, I confirmed that the green I see on the FCES green camera is a single pass beam by misaligning both FC1 and FC2, they do not move this beam, and also confirmed that it's green by toggling the fiber input. I moved ZM3 to bring this to center on the camera, as we have not disturbed this FCES green path since O4. Then I did a raster on FC1 to get the IR seed reflected onto the SQZT7 IR PD (screenshot).
After moving FC2, I could see some green and IR on the FCES cameras. For IR, this is not the single pass beam but some reflections off FC1, for green we still see the single pass beam and a second beam coming close to the single pass beam, but it seems to have a very different beam size. screenshot. After this I went to SQZT7 and saw that the FCGS refl beam is making it to the table and aligned it onto the diode. Now we have 2.5 of the 4 things we need for the squeezer to work: green on SQZT7, IR on SQZT7, and the green single pass is heading towards FC2 well, which is part of what we need to get green flashes.
Sophie and I went to FCES. We tried moving FC2 to see what happened on the green transmission, we can see the beam reflected off FC2 leaks around the edge of the FC2 coating for some alignments, but that we can overlap them for some alignments, but do not see cavity flashes.
Camilla moved ZM3 back to the alignment where she found the green centered between the two places where it goes over the edge of the coating. This was a simlar situation in green.
In IR, we did see a single pass beam on the camera when Camilla steered ZM3. In 986 ZM3 is in the position where Camilla thinks IR is centered on FC2, you can see two green spots, and to the right and slightly below a very faint IR beam (I had to clean the laptop screen, turn the brigthness up to see it). In 988 ZM3 was at -506 P, -200 Y, the negative pitch clipping, you can see the brighter IR beam where it is transmitting through the uncoated part of FC2. 990 is ZM3 -324 P, -200 Y, going over the lower edge of the coating. 994 is with FC1 + FC2 in the aligned guardian state, moving FC2 until we saw something on the IR camera. 996 is for FC2 359 P, 28 Y, there was light on the IR diode, but the photo is dark.
We previously reported that the wiring to ground on the OMCA DCPD dsub9 cables seemed odd, see 89562. There appears to be two conflicting diagrams of the pin wiring, D2200276 and D2300119. Neither of these diagrams follow the correct pin naming practice either.
Today, Oli and I checked the ground connectivity for the OMCB DCPD dsub9. The case ground is wired to what is labeled pins 6 and 9, according to both of the diagrams above and also proper convention. However, this is different from OMCA, where the case ground is wired to pins 2 and 5 (following the incorrect naming of the diagrams above), or pins 1 and 4 (following correct naming conventions).
So either way, we have two different wiring set ups for OMCA and OMCB. We have only checked the ground pins so far, and it seems like we should confirm the cathode and anode wiring as well.
To summarize:
- we have two different diagrams for pin wiring
- OMCA and OMCB are wired differently from each other
- the diagrams are not following proper pin naming convention which is making this more confusing
Two problems with the drawings.
1. Case grounding.
As for cable and connection drawings, D2200276-v4 wiring diagram specifies that pin1-2 and pin4-5 twisted pairs carry the photocurrent, pin1 and pin4 being cathode, and case grounds are routed to pin6 and pin9, between DCPDs and the in-vac DCPD frontend. See the 1st attachment.
D2300118 DCPD to DB9M cable doesn't agree with the wiring diagram, it routs the case grounds to pin 2 and pin 5. See the 2nd attachment.
D1300369 DB9F-DB9F cable drawing agrees with the wiring diagram in that pin1-2 and pin4-5 are twisted pairs.
D2000592-v3 in-vac DCPD frontend seems to be compatible with the wiring diagram in that it routs the pin6 and 9 to the ground.
So, D2300118 DCPD to DB9M cable drawing is singularly incompatible with others.
Below is a summary table of the above together with reality check of the DCPD-DB9m cable. It seems that there's no way OMCA cable works. Anode/Cathode check wasn't performed (yet).
| pin1 | pin2 | pin6 | pin4 | pin5 | pin9 | |
| D2200276-v4 wiring diagram | Cathode1 | Anode1 | Case1 | Cathode2 | Anode2 | Case2 |
| D2300118 DCPD to DB9M cable | Cathode1 | Case1 | Anode1 | Cathode2 | Case2 | Anode2 |
| D1300369 DB9F-DB9F cable (pass through) | compatible with the wiring diagram in that pin1-2 and pin4-5 are twisted pairs. | |||||
| D2000592-v3 in-vac DCPD frontend (outside of the enclosure feedthrough) |
Internally routed to PD1 pin1 |
Internally routed to PD1 pin2 |
Internally routed to GND |
Internally routed to PD2 pin1 |
Internally routed to PD2 pin2 |
Internally routed to GND |
| OMCA reality | Case | ? | ? | Case | ? | ? |
| OMCB reality | ? | ? | Case | ? | ? | Case |
2. Polarity of the diode seems to be wrong.
Assuming that the wiring diagram and the in-vac DCPD frontend circuit diagram are both correct, cathode1 and anode1 are routed to "PD1 pin1" and "PD1 pin2" while cathode2 and anode2 are routed to "PD2 pin1" and "PD2 pin2". So, pin1 and pin2 inside the frontend chassis are cathode and anode. Again look at the first attachment.
However, whey you look at the circuit diagram of the frontend (3rd attachment), pin2 is connected to the positive bias and pin1 is grounded (via the huge inductor). This means that the PD is forward-biased and will be unusable. Is this only in the drawings?
What to do.
First thing is to check the diode polarity in reality, i.e. if cathode is routed to pin 1 and 4 (which I expect) or to pin 2 and 5 (which I don't expect). In parallel, check with Ali/Dean that my assessment of the polarity makes sense or not.
Depending on the results of the polarity investigation, we'll determine which cable needs to be reterminated how. If we're lucky we'll just reterminate only one cable, but if the PD polarity is indeed wrong we'll have to reterminate all cables.
Here is a further update. This is based on conversations with Keita and Betsy, and emails to and from CIT and LLO.
At first, it appears one issue here is that I have made a mistake OMC placement, as D2200276 indicates that OMCB should have the DCPD cable labeled D2300119 (and PZT cable D2300121), and OMCA should have D2300118 (and PZT cable D2300120), and I installed them opposite according to the DCPD cables. This doesn't account for the wiring issue; it would only make a cable length difference.
Oli and I went into the lab to swap around OMCA and OMCB, and realized that one OMC has the DCPD cable for A (D2300118) and PZT cable for B (D2300121) and vice versa. So it's not clear which is which.
Keita has further pointed out that this wiring issue with the grounding pins could indicate cathode and anode are swapped, which means that the diode will be forward biased, which is a much bigger issue.
Therefore, we're pausing on all BHSS work for now until we can figure out how to resolve these problems.
LLO has not checked their wiring, but Oli and I did note that they paid attention to the OMC labeling since they knew the cable lengths would be different.
When our OMCs were shipped to us, the ameristat wrapping had OMC A and OMC B labels, but once we took the wrapping off, there was no indication of A and B on the boxes.
Keita, Elenna, and I just went in and tested the direction the current is flowing for the DCPD cables (D2300118 and D2300119).
D2300118 (SN S2500546)
Current direction:
- Pin 2 -> 1
- Pin 5 -> 4
D2300119 (SN S2500548)
Current direction:
- Pin 6 -> 1
- Pin 9 -> 4
We verified that there was no current flow when probes were swapped
For posterity, Ali etc. confirmed that the bias voltage is carried by pin 1 and 4 between the DCPD and the in-vac frontend: https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=80660
This means that the latest (fixed) version drawing for DCPD-D9M (https://dcc.ligo.org/D2300118-v2 and https://dcc.ligo.org/D2300119-v2) are correct, which is a good news!
This also means that the wiring diagram https://dcc.ligo.org/D2000592 is incorrect and the circuit diagram for the in-vac frontend https://dcc.ligo.org/D2200276 is incorrect or lacking information about the connection between the D9M feedthrough and the D9M connector on the board (e.g. the connection cable inside the box is not a usual cable but gender-changer type).
Elenna, Oli
Summary: OMCB has its DCPDs installed and most of its stoppers (barring one that needs to be retapped + helicoiled). OMCA has been aligned according to the OMCA / OMCB install template and is ready for laser alignment. Cabling for both OMCs should be good to go.
After last week's issue of the OMCB DCPD A (TRANS) missing a diode hole (89583), we were able to clear up the issue and fix it (89606). Elenna then installed the DCPD B (REFL) diode. Note that once again there were tiny metal shavings below where the DCPD's were installed, which we picked up with a qtip that we wet with iso. Once we had both installed (pic), we installed the rest of the stoppers around OMCB. The only one we didn't install is one of the vertical stops. This is because there was an issue with the helicoil last week, and we ended up having to remove it. We think this might be due to an issue with the threads, so we are waiting on a 3/8"-24 tap to retap the hole before installing a new helicoil. Because we don't have this stop yet, it doesn't really make sense to fasten on the butter dish, but we might just sit it on today to hinder dust accumulation.
We also realized that the PZT cables were going to be way too short to reach the cable pylons for both OMCA and OMCB, so we very carefully opened the peak cable wraps on the OMCs and took out what we think should be enough. On OMCB we noticed that the little copper wrap for one of the PZTs was not right above the PZT as it should be, but instead was on the other side of the peak cable wrap and was only wrapped loosly around one of the cables. Because of this we just removed the wrap. The cables right above the PZT are looking fine and don't look like they need anything to hold them together.
I had been confused about the OMCA / OMCB install template for the past few days, since installing it was putting OMCB further back in its slot than OMCA, but I was able to confirm yesterday in eDrawings that OMCB is actually supposed to be an extra 1 mm away from the front of its slot as compared to OMCA, so we moved OMCA into position and bolted it down.
I also went in and installed the magnet mounts for the OSEM magnets (without the magnets), as well as the big mass on the back of the BHSS.
Installed serial numbers:
OMCB (SN 105)
Tagging For EPO photos.
The naming convention listed above is incorrect. Please refer to alog 89669 for correct information.