Displaying reports 44181-44200 of 84061.Go to page Start 2206 2207 2208 2209 2210 2211 2212 2213 2214 End
Reports until 16:02, Thursday 15 March 2018
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:02, Thursday 15 March 2018 (41026)
Ops Day Shift Summary
Ops Shift Log: 03/15/2018, Day Shift 15:00 – 23:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for maintenance and upgrades
Intent Bit: Engineering
Support: X
Incoming Operator: N/A
Shift Summary: Maintenance and upgrade work continues apace across the site.    
 
Activity Log: Time - UTC (PT)
15:00 (08:00) Start of Shift
15:06 (08:06) Terry – Going into LVEA to work on Squeezer
15:14 (08:14) Vanessa – Going into the LVEA for cleaning
15:58 (08:58) Hugh & Betsy – Going to HAM6 to talk to Squeezer folks
16:06 (09:06) TJ – Going to HAM6
16:12 (09:12) Jason & Ed – Going into PSL Enclosure to work on 70W alignment
16:26 (09:26) Gerardo – Into the LVEA looking for a septum cover
16:34 (09:24) Hugh & Corey – Unlocking and balancing HAM6 tables
16:45 (09:45) Jeff K. – Going to HAM6 area
16:45 (09:45) Gerardo – Out of the LVEA
16:46 (09:46) TJ – Out of the LVEA
16:46 (09:46) Marc – Going to CER and PSL rack (WP #7419)
16:47 (09:47) Nutsinee – Going to HAM6 area
17:04 (10:04) Pepsi on site to service vending machines
17:06 (10:06) Nutsinee – Out of the LVEA
17:10 (10:10) Peter & Arijit – Peter escorting Arijit into PSL Enclosure
17:32 (10:32) Filiberto – Into LVEA and Mechanical building cabling for TCS Beckhoff
17:50 (10:50) Dave – Going to H2 Electronics building
18:00 (11:00) Marc – Out of the LVEA
18:15 (11:15) Georgia – Turning on TCS- X and TCS-Y Lasers
18:22 (11:22) Richard – Going to HAM6 to talk with Hugh
18:26 (11:26) Karen – Cleaning in the H2 building
18:40 (11:40) Peter & Arijit – Out of the PSL Enclosure
18:47 (11:47) Jason & Ed – Out of the PSL Enclosure
19:01 (12:01) Karen – Out of the H2 building
19:20 (12:20) Elizabeth – Going to both mid and end stations to work on network switches
20:54 (13:54) Elizabeth – Back from mid and end stations
20:58 (13:58) Greg – Going to work on TCS-X laser table
21:00 (14:00) Jason & Ed – Into the PSL Enclosure for mode matching work
21:00 (14:00) Cheryl – Going into the PSL Enclosure to modify ISS dog clamps (WP #7421)
21:08 (14:08) Betsy – Going into the LVEA to look for parts
21:30 (14:30) Betsy – Out of the LVEA
21:40 (14:40) Marc – Back into LVEA to work on RF90 cable
21:57 (14:57) Jason – Out of the PSL Enclosure
22:00 (15:00) End-Y being transitioned to laser hazard
22:08 (15:08) Lockout/Tagout lock in Bubba’s name on End-Y PCal laser. Spoke with Bubba – He gave verbal permission for the PCal crew to remove his lock. Notified Darkhan by phone of same.
22:21 (15:21) End-Y has been returned to laser safe. Lockout/Tagout has been restored to its original condition.
22:40 (15:40) PCal crew back from End-Y
22:55 (15:55) Jeff K. – Out to talk with HAM6 SEI crew
23:00 (16:00) End of Shift
   
H1 CAL (CAL)
darkhan.tuyenbayev@LIGO.ORG - posted 15:47, Thursday 15 March 2018 (41025)
PCALY beam alignment check

Niko, Darkhan,

We checked the alignment of the Pcal beams at EY by looking at the beam positions at the RxPD integrating sphere input port (in the Pcal receiver module). As was expected, the beams are well centered on the port.

Note: To do this check we needed to temporary turn on the Pcal laser (for which we removed the lock from the module with Bubba's permission). After the work was completed we switched off the laser and put Bubba's lock back on the Pcal AOM and laser power supply module.

Images attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 15:06, Thursday 15 March 2018 (41024)
CP4 Regeneration update
Today I lifted the three heater element wires from the terminal strip located within the Regeneration Control Panel and used a "High Potential" tester to apply 1000 volts between each wire and ground.  I varied the current limiter throughout its range (0.3mA - 12mA) while the high voltage was being applied and did not detect a short to ground - good!  Next, I terminated the 4-20mA CDS wires on to the SCR unit and energized the Regeneration Control Panel - no faults.  Finally, and without any GN2 flow, I enabled the CDS PID control with a setpoint of 50C and proportional gain of 7.  The Regeneration Temperature rose -> 24.1C,  24.2C, 24.3C, 24.4C, 24.5C - over the course of 5 minutes or so before the control panel tripped with a "HIGH LIMIT" fault.  This is as expected considering the absence of GN2 flow to remove the heat from the heating elelments.  The thermocouple used for the "HIGH LIMIT" is in contact with the heating elements ballast mass while the thermocouple used for the PID control "Regeneration Temperaure" is several inches downstream of the heating elements and it samples the GN2 flow.  

So, it looks like the Regeneration Control Panel is working again (for the time being!).  We are installing a second in-duct cartridge heater tomorrow and will have to shut down the forced-air heating unit so maybe Monday we can try to start up the regeneration flow again and start dumping some Joules into that CP4 bad boy!
LHO VE (VE)
david.barker@LIGO.ORG - posted 14:17, Thursday 15 March 2018 - last comment - 16:03, Thursday 15 March 2018(41023)
bypassing CP4 REGEN Interlock alarm until Monday

Kyle confirmed that the CP4 regen overtemp interlock alarm will be in the alarm state from now through Monday. I have bypassed this channel from sending cell phone texts until that time. Email alerts for this alarm will continue to be sent.

Comments related to this report
david.barker@LIGO.ORG - 16:03, Thursday 15 March 2018 (41027)

CP4 TE253A, which is currently following the ambient temperature (with ROC alarm levels of +/-5.0 degC per Hour) generated an alarm earlier today when the outside temperature increased at 5.5 degC/hr for a short period of time (when the Sun came out possibly). If this becomes a nuisance we can consider raising the alarm levels.

H1 General
jeffrey.bartlett@LIGO.ORG - posted 13:30, Thursday 15 March 2018 (41021)
13:00 Vent Meeting Minutes
PSL:
Closing in on mode matching alignment
Next up - connecting the 70W laser
 
HAM6:
SEI crew unlocking and balancing the HAM6 table
Squeezer work continues
Commissioning of the VOPO is working through several issues
 
VAC:
Installed a new NEG pump at End-Y
End-Y door is on
There is additional vacuum work to complete before pump down can start
 
End-X:
PCal periscope alignment
Prep work for Quad LS extraction
 
CDS:
Working on replacing suspect POP RF90 cable
Connecting TCS Chillers to RS232
 
Tuesday Maintenance:
Video cameras for HAM6/Squeezer
ISI model reboot  
H1 PSL (PSL)
cheryl.vorvick@LIGO.ORG - posted 21:35, Wednesday 14 March 2018 (41019)
PMC dog clamp rework complete, one more to add if access becomes possible

I modified the one and only dog clamp on the PMC foot on the NW corner, from angling up toward the contact point with the PMC foot, to angling down.  Should the ISS box need to be removed, a second dog clamp on the NW foot would be advised.  There is room at the table level, but not for both tools and hands between the ISS box and the PMC while both are installed.

Previous changes to dog clamps in alog 40822.

Images attached to this report
H1 IOO (IOO, PSL)
cheryl.vorvick@LIGO.ORG - posted 21:08, Wednesday 14 March 2018 (41018)
GigE camera install on the PSL table

I removed my O2 GigE camera installation, and have moved the cameras to their O3 locations.  GigE camera 1 is now positioned to look at the beam coming out of the PMC, and GigE camera 2 is positioned to look at the transmitted beam of the bottom pericope mirror.  Both are blocked by beam dumps until the beam is restored for alignment.

I rerouted the AOM RF cables that were curved to go around the high power beam dump, to go in front of the high power beam dump.  Attached pictures show 2013, the original install, and today, which shows the cable with only one curve, from the connectors to the table.  One the table, the cables are secured to prevent them from making contact with other components/bases, and to be as straight as possible.  Some cooling lines and other cables were also moved and re-secured.

Images attached to this report
H1 SQZ
daniel.sigg@LIGO.ORG - posted 18:39, Wednesday 14 March 2018 (41017)
OPO locked in-air

Nutsinee Terry Daniel

We were finally able to lock the OPO in air. We took the output of the common mode board and send it to the laser PZT via a Thorlabs PZT driver (gain of 15).  The ugf we achieved is 10kHz. With all 3 boosts engaged the lock is reasonably tight. The attached screenshot shows the CMB settings.

The noise spectrum indicates a strong acoustic peak around 1.1kHz that needs a large driving range.

We also measured the transfer function from the OPO PZT to the laser PZT. The first resonance is at ~6.0 kHz as expected—confirming that the 1.1kHz peak is not an inline resonance.

Some of the problems we encountered along the way:

Images attached to this report
LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 18:32, Wednesday 14 March 2018 (41016)
Y-End NEG Pump Installation

Installed a new type of NEG pump at BSC6 port C90G3.  Housing still needs a gauge.  Also, electronic/power components still need to be installed.

Images attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 17:30, Wednesday 14 March 2018 - last comment - 17:37, Wednesday 14 March 2018(41014)
Replacement SCR also "shorted" after brief operation
Chandra R., Kyle R. 

Chandra attempted to re-establish heated GN2 flow through CP4's empty LN2 reservoir this morning (assists bake-out of CP4 currently in progress).  The original SCR had "shorted" after only days of use so we replaced it yesterday with one we removed from CP3's Regeneration Control Panel.  This time the SCR failed (shorted) after only minutes?  Tens of minutes?  

According to the SCR manual, this failure results whenever there is load current detected (sensing coil on one phase) in the absence of a 4-20mA control signal or when the load current is present and not a function of the 4-20mA control signal.  I investigated and found that the three delta-connected heating elements all measured 30 - 31 ohms between each other and Megaohms to ground, i.e. weren't shorted when the low voltage VOM output was applied.  I did not do a High Potential (HiPot) test.  Next, I lifted the CDS wires supplying the 4-20mA control signal and then energized the unit.  Still, even with the input removed, the SCR indicated an "SCR SHORTED" fault.  Long story short, all of my investigating suggested a shorted SCR vs. a problem in the associated external wiring.  

As such, I replaced this second SCR with a third one borrowed from CP5's Regeneration Control Panel and installed it.  This time, I did not land the CDS 4-20mA leads but, instead, left them "hanging".  I energized the Control Panel and did not experience the troublesome fault.  The Measured supply voltage was found to be 498 VAC which is quite high.  I recall that this is a known "feature" from "back in the day..." and seem to remember it was due do the Xformer tap that we use.  In any case, this shouldn't be an issue as the SCR is rated up to 600 VAC.  I also measured 9.4V between the 4-20mA control wires while not terminated.  Hmmmm... the CDS PID control is off.  Should there be voltage across these without a PID output?  

I'll try out this third SCR tomorrow and attempt to do so in small incremental outputs while monitoring as many pertinent metrics as possible.  If this third unit also shorts, we'll abandon the "dream" and concentrate on minimizing air leak losses to the room and adding more heat to CP4's insulated bake-out enclosure.  
Comments related to this report
kyle.ryan@LIGO.ORG - 17:37, Wednesday 14 March 2018 (41015)
Upon further consideration, two of the three phase currents get regulated by the SCR, the third phase does not.  Additionally, this unregulated phase is the one sampled by the sensing coil.  Hmmm... I'll definitely do a HIGH POTENTIAL test to make sure that there isn't a short to ground when hundreds of volts get applied.  This would explain the symptoms but seems far-fetched.  
H1 CDS
david.barker@LIGO.ORG - posted 16:57, Wednesday 14 March 2018 (41013)
vac alarms customized to tonight's operating conditions

Kyle, Dave:

to prevent nuisance cell phone alarms for out-of-nominal conditions overnight, we have reconfigured the alarms:

H0:VAC-MY_CP4_TE253A_REGEN_TEMP_DEGC is running cool, reduced its LOW alarm limit from 70C to 0C

H0:CDS-ROC_VAC_MY_CP4_TE253A_REGEN_TEMP_DEGC_1HOUR_R is trending towards ambient at a rate higher than 1.0 CperHour. Increase alarm rates to +/- 5.0CperHour

H0:VAC-MY_CP4_253_REGEN_TEMP_ALRM_INTLK will be in alarm overnight. Sends its alarms to emails only, not to cell phones.

H1 AOS
jeffrey.bartlett@LIGO.ORG - posted 16:02, Wednesday 14 March 2018 (41012)
Ops Day Shift Summary
Ops Shift Log: 03/14/2018, Day Shift 15:00 – 23:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for maintenance and upgrades
Intent Bit: Engineering  
Support: X
Incoming Operator: N/A
Shift Summary: Happy Pi Day! End-Y is closing out while activity ramps up at End-X. Vacuum bake out continues at Mid-Y. Film crew from Royal Astronomical Society of Canada on site.   
 
Activity Log: Time - UTC (PT
14:43 (07:43) Mark – Moving snorkel lift to Mid-Y
15:00 (08:00) Start of Shift
15:29 (08:29) Mark – Back from Mid-Y
15:39 (08:39) Rick – Going to End-X to recover equipment
15:40 (08:40) Hugh – Going to End-X to work on HEPI
15:57 (08:57) Richard & Filiberto – Going into the CER
16:05 (09:05) Richard & Filiberto – Back from CRE
16:17 (09:17) Filiberto – Going to the CER & HAM6 area
16:27 (09:27) Rick – Finished at End-X – Is leaving the lights on
16:53 (09:53) Film crew on site to meet Amber
16:58 (09:58) Karen – Cleaning at Mid-Y
17:01 (10:01) Marc – Going to Mid-Y to look for parts
17:15 (10:15) Jason – Going into the PSL Enclosure
17:20 (10:20) Cheryl – Going into the PSL Enclosure
17:30 (10:30) Amber – Taking a film crew into the LVEA
17:35 (10:35) DOE well survey team on site
17:55 (10:55) Filiberto – Working on the access control system in MSR - will be lifting tiles
18:21 (11:21) Amber – Film crew out pf the LVEA
18:28 (11:28) Chris – Going to End-X to get equipment
18:32 (11:32) Marc – Back from Mid-Y
18:52 (11:52) Terry – Going into the LVEA to work on Squeezer table
19:20 (12:20) Jason – Out of PSL
20:06 (13:06) Cheryl – Out f the PSL
20:19 (13:19) Mark, Mark, & Betsy – Going to HAM6 area
20:28 (13:28) Kyle – Going to Mid-X
20:41 (13:41) Dave – DAQ restart (WP #7420)
20:47 (13:47) Hugh – Going to End-X for HEPI pump station work
20:48 (13:48) Mark, Mark, & Betsy – Out of the LVEA
20:51 (13:51) Jason – Going into the PSL Enclosure
21:29 (14:29) Cheryl – Going into the PSL Enclosure
21:36 (14:36) Hugh – Back from End-X
21:48 (14:48) Kyle – Finished at Mid-X – Going to Mid-Y
22:16 (15:16) Jason & Cheryl – Out of the PSL Enclosure
23:00 (16:00) End of Shift
 
H1 CDS (DAQ, SQZ)
david.barker@LIGO.ORG - posted 13:53, Wednesday 14 March 2018 - last comment - 14:18, Wednesday 14 March 2018(41010)
Fixed guardian INJ_TRANS, added 3 SQZ nodes, DAQ restart

WP7420 New SQZ guardian nodes and DAQ restart

Daniel, TJ, Dave:

TJ created the three new SQZ guardian nodes (SQZ_CLF, SQZ_OPO, SQZ_LO).

We also re-created the INJ_TRANS node after fixing the NFS mount issue between h1guardian0 and h1hwinj1.

The DAQ was restarted to use the new H1EDCU_GRD.ini This was urgent, the loss of the INJ_TRANS channels from the frame files was causing Det Char issues with their summary page generation.

Comments related to this report
thomas.shaffer@LIGO.ORG - 14:18, Wednesday 14 March 2018 (41011)

Here's a shot of the GUARD_OVERVIEW.adl with the new SQZ nodes. They get their own sub-box.

Images attached to this comment
H1 PSL
jeffrey.bartlett@LIGO.ORG - posted 10:52, Wednesday 14 March 2018 (41008)
PSL Chiller Check (FAMIS #6566)
   Check chiller water levels and filters. I added 100ml on Tuesday (aLOG #40984); no additional water was needed today. No change in the filters. The Diode chiller filters are clean. The Crystal chiller filters need to be replace when the 70W work is finished.
H1 CDS (CDS)
keith.thorne@LIGO.ORG - posted 10:40, Wednesday 14 March 2018 (41007)
Counting active IPCs in front-end models
As we get back to commissioning, we are again actively changing IPCs in front-end models.  This can cause the number actually in use to vary from those in the static lists, that only get pruned manually or when re-building all models. At present, we are limited to 512 IPCs per type (Shared memory, PCIe, RFM-X, RFM-Y).  I updated a script 'find_used_ipc_channels.py' started by Joe Betzwieser to go over all the in-use models (using the rtsystab file) and list all the IPCs in use in files.

After running it at LLO (see aLOG 38202 ). I have run this for H1 today with the following:

 Found 197 SHMEM IPCs - list in ipc_shmem_channels.txt
 Found 414 PCIE IPCs - list in ipc_pcie_channels.txt
 Found 31 RFM0 IPCs - list in ipc_rfm0_channels.txt
 Found 31 RFM1 IPCs - list in ipc_rfm1_channels.txt

I have attached the channel lists.  These are somewhat lower that LLO usage.
Non-image files attached to this report
H1 SEI
jeffrey.bartlett@LIGO.ORG - posted 10:04, Wednesday 14 March 2018 (41006)
ISI CPS Noise Spectra Check (FAMIS #6941)
   Posted are the weekly ISI CPS noise spectra. Did not see any egregious anomalies. Closing FAMIS #6941  
Images attached to this report
H1 SUS
betsy.weaver@LIGO.ORG - posted 13:47, Tuesday 13 March 2018 - last comment - 10:32, Thursday 15 March 2018(40995)
ETMY BSC10 door closed

Today, I went in and pulled the 2nd First Contact sheet after the reapplication yesterday afternoon.  Unfortunately, the 2 small glint blemishes that I didn't like yesterday were still there.  So, they are either in the coating, scratches, or are not coming off.  So, I then completed the closeout steps of:

1) N2 blow, measuring charge (details below)

2) Placing the 1" witness optic on the side of the QUAD structure

3) Jim unlocking ISI

4) Placing 3" horizontal wafer below ETMY QUAD on floor

5) Mounting 3" vertical wafer on lower front of QUAD structure

6) Wiping the floor on the way out

7) Removing tools

8) Kissel running TFs - 3 per suspended chain - all good

9) Launching door crew

Door on by lunch, started work at ~9:30am.

Comments related to this report
betsy.weaver@LIGO.ORG - 10:32, Thursday 15 March 2018 (41020)

Details of the N2 deionization during this closeout:

Measuring at the back of the AERM surface, the measured voltage started at ~8v, measured in the Center, UL, LR positions.  We then pulled the FC and blew everywhere around the ETM and AERM for many minutes.  Measuring again, the charge at these locations was down to ~2.5v.  Another round of blowing, with a check of the zero of the meter in between, and the charge then read 1.3v in the Center and UL and 2.1v at the LR position.

5 minutes later we remeasured and found the charge at 0.4 in the center and -0.6v at UL.

Displaying reports 44181-44200 of 84061.Go to page Start 2206 2207 2208 2209 2210 2211 2212 2213 2214 End