Today, we measured the violin modes of the new monolithic ETMy with the goal to determine what contributed to the large-ish pitch offset we were seeing. Nothing egregious was found from violin modes themselves, so we decided to attempt to fix the pitch by re-stress-relieving the stock welded to the horns. This technique has been done before, once here at LHO and once at LLO with success. This time around, we went from ~5mRad differential pitch to ~500 uRad differential pitch. Now, if only we could get a factor of 10 improvement in other aspects of LIGO in the course of a day. . .
Jim and I went in today and tried our hand at some of the bolts on the periscope. We had high hopes since the 3IFO periscope looked good and the bolts freed easily. Unfortunately, these bolts had their hexes almost stripped on many, if not most, of the bolts (see attachments). With some breaker bars we managed to get out all of the ones we need for the vibration absorbers, and then we started on some for the baffle panel brackets with Betsy guiding us to the correct ones. Overall it was a good success with more work tomorrow. And we only bent 3 wrenches in the process!
Also, I didn't get any pictures of where we left off, check back tomorrow.
TITLE: 01/25 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
16:03 Christina out to LVEA
16:45 Hugh out to LVEA - working atop HAM6
16:50 Set Very Large EQ button because of 5.8mag of the coast of N Cali
16:53 reset ACT SEI trip at ETMX
16:57 reset MC1 wd, HAM2 ISI CPS trip, and ITMY ACT trip. The latter has been problematic this morning.
18:03 Jeff K out to LVEA - talk to Hugh on top of HAM6
18:04 N out to squeezer bay
18:13 Marc out to LVEA - check on ZM1; pull TTFS unit from squeezer bay.
18:22 Betsy Tj Jeff K and Jim out to EY - B&K Hammer and Reaction chain
18:27 Sheila ou to optics lab
18:29 Travis called from EY - the welding team is out there (Danny, Angus and him)
19:43 Noticed Fil out on LVEA floor at output.
21:32 Richard into CER - HV supplies
21:36 Marc out to LVEA - SUS rack by HAM5
21:50 Sheila out to optics lab
21:54 Betsy out to EY
22:04 Jim and TJ out to EY
22:45 Kissel back
22:53 Marc back
23:13 Kyle out to MY and EY
23:38 Jeff B out
23:59 Greg out to TCSY table to reset the LASER
24:00 EOS
Commissioning -
Squeezer -
TCS -
Vacuum -
Fiber Welding -
Pcal -
SEI -
CDS Electronics -
Facilities -
Terry, Nutsinee, Daniel, Sheila
LAYOUT
Attached is the current layout of ISCT6 at LHO that is an almost identical copy of LLO. Differences at time of writing are as follows:
1) A quarter wave plate was added after the laser to reduce the elliptical polarisation out of the Mephisto and increase the transmission through the isolator to > 95% and reduce the back reflection that is awkward to dump because the rejected beam from the isolator goes vertically down and is close to the isolator mounting post.
2) Two 100 mm & two 150mm lenses were used to mode-match the LO and PSL LO paths (instead of four 100 mm lenses) and the seed path has two 75 mm lenses instead of two 100 mm lenses as we had run out of 100 mm lenses. This made the LO path from the PSL about 50 cm longer and the seed path a few cm shorter. The seed path was routed as originally proposed in D1500297-V5 as a lens mount was in the way and made it difficult to keep an exact copy of the LLO beam path.
3) The SHG is about 5 inches closer to the fiber coupled output end of the table than at LLO. This was just a positioning error on the table and did not compromise the setup and once the SHG was mode matched I did not feel it was worth changing.
4) The fibre couplers are about 3 inches further away from the end of the table (I accidentally left myself a little too much room to play with).
5) The fast AOM has 70% diffraction efficiency (as opposed to 80% at LLO).
6) To get more RF power on the TTFSS detector BS5 and BS9 have been swapped from their original positiions at LLO (alog 40249)
I'll post the mode-matching solutions shortly but the coupling efficiencies into all the fibres are about 80%.
PARTS LIST
The parts in red have to be replaced with superpolished mirrors and the parts in yellow are also not superpolished but are less critical.
Still waiting for fibres from couplers on table to patch panel and fibre switch (using temporary patch cables at the moment).
After Jenne's experience with the Kamchatka earthquake last night, I've added the requested seismic recovery button the ISI_CONFIG screen, shown on attached image. The new, green Recover EQ button is just above the old, red Very Large EQ button, and mostly just reverses the operations of the red button. If any platforms are tripped, you'll have to reset watchdogs. There's also a long standing issue of the HAM2&3 GS13 gains, which for some reason can't be stably managed by the ISI guardians, so there will be SDF differences after recovering from an bad earthquake. I've also added the low frequency Z blrms for EX&EY STS2s to the stripchart on the lower right. If all 4 channels (LSC-CPS, & 3x .03-.1hz gnd blrms) on that display are headed off the stripchart, it's a pretty good indication of a large earthquake arriving.
Ed, Jim
Excursions in BRSX include Krishna's initial visit and a code crash at the end of December
TITLE: 01/25 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
Wind: 8mph Gusts, 7mph 5min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.35 μm/s
QUICK SUMMARY:
The laser tripped around 1:20 am because of the Wachhund. I increased the diode currents by 1A for heads 2, 3, and 4. Things seemed to have come back okay.
Changed temperature of DB1D3 from 23.7 degC to 22.5 degC.
Daniel, Terry, Nutsinee
While playing with the TTFSS we found that very little s-pol came out of the faraday isolator before going into EOM1 (responsible for laser locking and 35.5MHz modulation for SHG locking). Sticking in a PBS cube we found 6mW of s-pol reflected and ~1W of p-pol transmitted through. We placed a half wave plate to correct for the polarization and mostly s-pol is now going through the EOM. In addition we swapped the EOM to troubleshoot a mystery 780kHz peak and phase dip in the TTFSS transfer function (it was 760kHz for the spare EOM). The peak was a result of the wrong polarization going in. Even with the correct polarization the peak was there but the phase was no longer a dip towards 180deg.
As a result, SHG locking signal needed a sign flipped and the gain needed tweaking at the beginning of the common path.
Jenne, Sheila, Thomas
We went back into HAM6 this afternoon after the PSL came back and we convinced ourselves that we couldn't find the beam on the OMC QPDs.
Fast shutter:
Still to do:
I'm not sure what "very large" means for earthquakes when it comes to something that seems borderline-ish, but it seems like this 6.4 in Kamchatka might qualify, so I clicked the very big Very Large Earthquake button. It was after the S-waves had arrived, but about 400 sec before the R-waves were expected.
The IMC unlocked, and ITMY's ISI tripped, although I'm not sure if that was before or after the transition was complete. I leave it to Team Seismic to investigate further if they feel so inclined.
It occurs to me that perhaps we need a "go back to regular" button, somewhere near the large earthquake button. Maybe this will be less relevant when we have operators who already know what to do, sitting in the chair. But, for now we'll leave it this way overnight since the EQ is still ringing down.
I've been planning on a wax on / wax off script to do this, but haven't done it yet because I wanted to be clever about it. I can put a dumb version on the ISI config screen tomorrow, but for now, going to the SEI tab on sitemap, opening the Transition_all_SEI (or something like that) and pushing the button to re-isolate all the chambers, and moving SEI_CONF back to WINDY will probably be close enough. This will miss some sensor gains, but they probably don't matter all that much. HAM6 and ETMY will probably trip because they are locked & their hepi iso gains are forced to zero on the secret slider. You could take both of those chambers OFFLINE after pushing the other buttons, or just let them trip.
Also, looking at the wall blrms, I don't think the transition was needed for this eq, just going to SC_OFF or LARGE_EQ for SEI_CONF would have been safe. It would be helpful to know what seismon predicted for the surface velocities.
A. Bell, J. Oberling, D. Sellers, T. Sadecki, K. Toland
The final 2 fibers were welded to the new ETMy. The monolithic was successfully suspended and IAS measurements were taken. I'll let Jason fill in the numbers, but the differential pitch is a bit larger than we generally hope for but not grossly so. Good work team!
Violin mode measurements to commence tomorrow.
Final alignment numbers for the new ETMy monolithic. All measurements were done with the ETMy suspended; the PUM and UIM were both locked. All numbers assume the reader is looking in the -Y direction (i.e. at the AR surface of the ETMy); this is opposite the notation used in the alignment notebook, which is done from the perspective of the aligment equipment (i.e. looking at the HR surface of the ETMy). The pitch measurement was done after this afternoon's correction of the differential pitch; before the correction the differential pitch was 5.53 mrad down.
The serial numbers of the fibers used and their locations in the monolithic are as follows:
[Gerardo, Kyle, Chandra]
This afternoon we reconfigured GV11's gate annulus ports (two 1-1/3" mini CFF half nipples). The (building) north side port is blanked off and the south side has a metal valve, all leak tight. We pumped out the gate annulus, knowing there is an outer o-ring leak; the right angle valve will remain in place during the CP4 bake.
To do this exercise we valved in small IP connected to CP1 and soft closed GV10, and then valved out IP9 and valved in main turbo pump. Y1-arm pressure alarmed temporarily. Valves are back to normal configuration (GV10 open, turbo valved out, IP9 valved back in). CP1's IP is still valved in.
Gerardo, Patrick Ran svn update in C:/SlowControls on h0vacmr, h0vaclx, h0vacly, h0vacmx, h0vacmy, h0vacex Ran svn update in C:/SlowControls/trunk/TwinCAT3/Vacuum/LHO/MEDM on h0vacey Done to propagate Gerardo's update to the vacuum overview medm screen.
Turned the RF driver and the power supply on for the CO2Y laser, also connected the IR sensor, and was getting green lights for the control board. Using the PWM controller I tried to turn the laser on but wasn't getting any results on the power monitor. After double checking the power supply was set to 28V and 28A limit, and the RF driver was set to 40.68MHz, Fil and I found that the wrong RF cable was plugged in. After plugging the right one in the laser powered up in PWM mode and I was able to verify the rotation stage is working as well. Tomorrow I will check that the alignment hasn't changed significantly and that the periscope picomotors are operating correctly.
CO2Y is now running in remote operation mode. The beam is dumped before the periscope though. I quickly checked the beam path and everything looks clear, although I did remove the alignment laser as it could possibly be clipping the IR camera path. When the laser proves to be running stably with the new chiller the beam dump will be removed.
CO2Y ran for just under 3 days before faulting out to a flow rate trip. A quick inspection of the chiller shows nominal water level and no faults indicated, so flow rate sensor is the main suspect. Also note the odd drop in the power supply and power output. Not sure why that happened.
See final alignment numbers at this alog.