15:00 M&M to ham6, testing platform
15:40 Tvo starting TCS table to work on guardian
16:10 M&M to HAM6
16:10 Fil to LVEA
16:30 Chandra & Kyle to MY
16:30 Corey & Hugh to HAM6
16:45 Betsy Travis to EX
16:45 Chris to LVEA
17:30 Mark to EX for beckhoff safety breaker
18:00 Fil & Patrick to CS mezzanine
18:30 Ed, Peter, Georgia to PSL
20:15 Chandra, Kyle & Mark to MY
21:30 Sheila, Terry, Arijit to HAM6
22:00 Hugh Corey to HAM6
22:15 Fil to MY
This morning, Travis, Mark D and I mated the ETMX lower QUAD to the install arm/elevator which is attached to the chamber door (see renderings in E1100832 BSC Arm user guide if interested). We then made the final structure disconnections between the lower and upper QUAD structures and then pushed and rotated the lower unit out of the chamber. The ACB was swung back for this (using the wedge), however the TMS was not. Like at EY last month, the elevator is able to just slide in and rotate around the QUAD which sits sandwiched between the ACB adn TMS. As is the typical sequence, we then used the blue Genie duct jack to pluck the lower unit off of the arm/elevator and place it onto a LSAT (lower structure assembly tooling) cradle and trolley (picture attached of final placement for the day).
This afternoon, Travis and I got the AERM out of it's air bake oven (epoxy curing air-baked last Fri), put it in it's cake tin, and took it to the end station for install.
We then started rearranging the furniture in the cleanroom area designated for the fiber welding scheduled to start next week. However after shuffling things many times, we are still struggling to work out how to make safe maneuvers with fragile fibers in this space. (Every weld cleanroom ends up being configured differently because each time we're in a different area with different room parameters - the hidden "beauty" of mobile fiber welding. In the current case, we are using part of a big cleanroom which has the beam tube, VE and OPLEV equipment running through it, with a joining smaller ~10' cleanroom attached.) We aborted the effort at the end of the day with no great solution - Travis will get with Bubba in the morning to see if another round of CR shuffles will help.
Vacuum pumps at End-X and CS are running fine. Temps and vacuum pressure are well within spec. Found the Pump at End-Y had failed. Found the backup pump has also failed, which is very strange as it had not been run since it was tested before going into backup. There was very little carbon dust in the pump housing, which is expected in a pump that had just been put into service. Will investigate why the vanes, which were not worn had fractured. Put the backup pump from End-X into service at End-Y and am ordering the necessary repair parts to get the two backup pumps back into warm standby state.
WP 7400
Installation of cables and fibers for the access controls system continues. List of the electronics that have been installed:
DCC # | Title | Serial Number | |
MSR | D1600176 | Safety System Controls Chassis | S1610044 |
LVEA | D1600176 | Safety System Controls Chassis | S1610045 |
LVEA | D1800016 | Safety Interlock Assembly | S1800550 |
END X | D1600176 | Safety System Controls Chassis | S1610447 |
END X | D1800016 | Safety Interlock Assembly | S1800551 |
END Y | D1600176 | Safety System Controls Chassis | S1610446 |
END Y | D1800016 | Safety Interlock Assembly | S1800552 |
TCS MEZZ | D1600379 | TCS Safety Interlock Assembly | S1800549 |
E. Castrellon, F. Clara, R. McCarthy, M. Pirello
I've expanded my TCSY glitch investigation to include L1 TCS signals. The attached plots recreate my H1 plots in alog 41039, and now include the corresponding L1 TCS signals. Most noteable in the L1 TCS LASERTEMPERATURE signals is a noise pattern on top of the DC temperature signal, and in H1 TCSX has regular noise glitches, both directions, and TCSY appears to have the same glitches, just constantly. The FLOWRATE signals in H1 and L1 are very similar. The QPD B SEG4 INMON signals in H1 show instantaneous level changes, and some downward spikes, and the L1 signals show some upward spikes, but no level changes. All plots show raw data, each is about 10 minutes in duration, H1 signals in blue, L1 signals in red.
TCSX and TCSY QPD segments are glitching every 15 minutes. The absolute drop in the signal during the glitch varies between 6 and 15 counts, and the shape on the segments and on TCSX and TCSY are the almost identical. These glitches are also happening in L1 TCSX and TCSY QPDs. Plot attached shows a TCSX glitch on the left and TCSY glitch on the right.
L1 TCS QPD glitches: up instead of down, and in one QPD more than another, but overall shape is very similar to glitches in H1 TCS.
Kyle, Dave:
The regen overtemp interlock is still bad, we are bypassing cell phone alarms for this channel for a futher 24 hours (expire Wed Mar 21 11:41:33 PDT 2018)
Added 150ml water to PSL crystal chiller. Diode chiller water level is OK. No changes in the filters.
(Gray, Radkins)
BACKSTORY:
After the major balancing & floating of the HAM6 ISI (due to adding the new OPO to HAM6) last Thurs, we have not been able to isolate HAM6. The thought is there is a mechanical issue (i.e. cable pulling on system?). Another symptom (related?) is related to the Capacitive Position Sensors (CPS). This is relegated primarily to Corner 3's horizontal (H3) CPS; it has a large value on the order of -13000 counts (roughly an order of magnitude more than normal).
YESTERDAY'S ACTIVITIES:
Before working in the chamber Hugh did some electrical checks:
Saw some minor change with the cable jiggling at the flange. But for the most part no change. This is when Hugh went in to look at possible cables pulling the system & to also clean up/remove the spools of newly-added Squeezer Silver cables. The Squeezer cables were removed from the ISI and tie-wrapped to the wall tabs of the HAM6 chamber). Since these cables were pulled off the ISI, we will need to add weight to the table and then re-balance.
After removing the cables above, unfortunately still saw the large H3 CPS values. So this remains an issue. This is where we ended the day on Monday.
TO DO LIST:
NikoL, RickS
With the removal of the ETM camera relay mirrors from the Pcal periscopes, the Pcal ETM cameras are no longer useable.
Thus, we removed these systems from the A7 Adapter ports at both end stations.
Before/after photos attached.
Note that the red-anodized gates (guillotines) for the viewport protectors are still in place. These have round pieces of black glass glued in rececces in the side facing the viewport.
This morning I got a little bit of time to try some more debugging of ZM1. Jeff Kissel's last alog (lhoalog41034) showed a big feature in the Y to Y measurement and a possible issue with the LL flag/magnet. After team SEI was done with their work and locked up the table, Corey and I checked all around the the suspension for anything that might look or feel wrong. I looked all around the LL OSEM for anything that might cause a problem but didn't find anything. I recentered the OSEMs on their flags and then we ran the measurements again. No change.
During a lunchtime talk with Betsy, she suggested that I try to run the Y to Y measurement with the top OSEMs backed out and not actuating, and then do the same with the bottom. When I tried it, it looked like the lower frequency feature was much smaller when the top OSEMs were backed out (see attached). I got excited and tried this for pitch as well, but didn't notice much of a difference. This ended my day in HAM6 as I had other teams nipping at my heels.
These templates have been moved to /ligo/svncommon/SusSVN/sus/trunk/HTTS/H1/ZM1/SAGM1/Data/ 2018-03-19_2144_H1SUSZM1_M1_WhiteNoise_Y_0p01to50Hz_bottomosemsout.xml 2018-03-19_2144_H1SUSZM1_M1_WhiteNoise_Y_0p01to50Hz_rightosemsout.xml 2018-03-19_2144_H1SUSZM1_M1_WhiteNoise_Y_0p01to50Hz_toposemsout.xml
16:45 JeffB transition LVEA to laser safe
17:00 Hugh & Corey to HAM6 for CPS work
17:00 PeterK & Ed to PSL enclosure
17:30 TJ to HAM6
17:45 JeffB to LVEA
17:45 Betsy & Travis to EX
19:30 Sheila found sqz and isct6 lasers still on after morning laser safe transition
20:15 Betsy & Travis to EX
20:15 M&M to HAM6
21:30 Peter to PSL
21:30 TJ to HAM6
22:00 Fil to LVEA
22:15 RickS Niko to EX, EY to remove PCAL Camera
22:15 M&M to HAM6
22:45 Sheila transition LVEA to Hazard
Laser Status:
SysStat is good
Front End Power is -0.003262W (should be around 30 W)
HPO Output Power is -0.04724W
Front End Watch is RED
HPO Watch is RED
PMC:
It has been locked 0 days, 0 hr 0 minutes (should be days/weeks)
Reflected power = 0.008512Watts
Transmitted power = -0.02508Watts
PowerSum = -0.01657Watts.
FSS:
It has been locked for 0 days 0 hr and 0 min (should be days/weeks)
TPD[V] = 0.06625V (min 0.9V)
ISS:
The diffracted power is around 3.3% (should be 3-5%)
Last saturation event was 14 days 2 hours and 58 minutes ago (should be days/weeks)
Possible Issues:
Front End Power is Low
FSS TPD is low
LRA out of range, see SYSSTAT.adl
The HEPI trends script was broken this morning when I launched it from the weeklies screen. This was caused by the changes to the EX channel names from the switch over to Beckhoff at that station. I updated the channels to my best guess but it's a little hard to say because the new overview doesn't seem to give a good map compared to the old overview.
Today, Betsy and I prepped the ETMx Quad for removal of the lower structure tomorrow. We swung back ACB, locked down all optics and masses, and disconnected all cables and wire segment necessary for removal of the lower structure. We are in good shape for extraction from chamber tomorrow morning.
Following the installation of the improved TEC controller for the SHG, we started tuning the loop.
Figure 1: A single pole at 0Hz, a zero at 100mHz and with 10mHz selected in the ugf box. There is a fair amount of overshoot and it takes a long time to settle.
Figure 2: The zero has been moved down to 10mHz.
Figure 3: The zero has been moved down to 5mHz.
Figure 4: The zero has been moved down to 7mHz. The overshoot is about 20%. We are sticking with this value for the zero.
Figure 5: Pole at 0Hz, zero at 7mHz, another pole at 1Hz, gain of -1, ugf box set to 30mHz.
Figure 6: Response measurement at 30mHz, indicating that the ugf is around this frequency.
Nutsinee Terry Daniel
OPO locking:
Fibers:
Translation stage:
Next:
Taking the 62% dip in reflection at face value, we can calculate the crystal loss assuming we know the input coupler (nominally 98% reflectivity) and neglecting any effects from mode mismatch:
R input coupler | Crystal Loss | Finesse | Power buildup | Crystal Loss | Finesse | Power buildup |
0.975 | 0.60% | 200 | 103 | 10% | 48 | 6.1 |
0.980 | 0.48% | 250 | 129 | 8.2% | 59 | 7.5 |
0.985 | 0.36% | 335 | 173 | 6.2% | 79 | 10 |
There are two possible solutions. However, the high loss solution is not very likely.