TITLE: 02/26 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Cheryl out sick, so her shift is being covered by multiple people (I covered morning & Patrick/Jeff will also help with coverage).
LOG:
Checking the ETMx OpLev in preparation for in-chamber activities starting soon, I noted that the OpLev that was re-centered on Feb. 15 (40559) is no longer centered on the QPD. We will probably want to re-center the OpLev again before removing the Quad so that we have an in-air reference to align back to. See attached trend. It appears that the OpLev Pit and Yaw are continuing to trend upwards even after the vent has completed. This is possibly due to temperature, but this gives us some (small magnitude) doubt to the reliability of using the OpLev for Quad alignment. Luckily, we also have ALS and PCal to use to verify our pointing.
Status
LVEA: VOPO Install (Corey, TJ, Alvaro with Bubba observing). And then fine tuning rest of the week. Might need beam/laser HAZARD Wed.
EX: Vented, IP12 removal (Tues), door off (wed/later?), Arm install (later in week)
EY: PCal work beginning of the week, ground loop checks, elec field measurements later in week, Vacuum install tasks next week
MY: CP4 Bakeout start this week sometime
Tues Maint:
Safety:
Trends are in a state of flux as the 70W work continues.
TITLE: 02/26 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
Wind: 12mph Gusts, 8mph 5min avg
Primary useism: 0.25 μm/s
Secondary useism: 0.51 μm/s
QUICK SUMMARY:
LVEA continues to be Laser HAZARD.
VOPO install at HAM6 is on the docket for today.
Significant pressure transition across septum viewport complete
Sheila D. Greg G.
Remotely enabled the CO2 lasers from the control room, CO2Y is in the Guardian lock laser state, while X is merely on. The integrators in the chiller control loops have been turned off, and a new chiller limit value was set to try and keep the control loop from giving the chillers a value that causes them to trip.
As seen in the attached pressure graph, the XBM pressure isn't following the expected pump down curve. Since GV2 was closed, thus isolating the XBM from the adjacent volumes, the pressure has been rising, flat or not decreasing etc.. In this configuration, IP6 and the XBM MTP are the only pumps pumping. Chandra R. had suspected previously that IP6 may be dying. Even so, I would expect that the symptom would be a loss of net pump speed. With the LVEA temperature constant, I'm wondering if this apparent increase is something else, like.....?
I confirmed that the MTP and IP6 are valved in. 4.9 x 10-9 Torr indicated at Turbo inlet -> PT170 gauge has been questioned in the past and is suspect
Here is a 10 day trend on both beam manifolds. The pressure in XBM seems to have settled. I need to follow up with the manufacturer of these gauges - an ongoing issue.
John and I spent time leak checking the XBM last year after noticing these pressure trends. No leaks found, but we didn't check welds.
The good news is that it looks like someone must have set our seismic system to the Large EQ mode before this morning's EQ hit, and none of the seismic systems are tripped now, the ISIs are set to damped with feedforward off and sensor correction seems to be off.
ITMY suspension was unfortunately set to safe, I assume this is left over from the fix earlier in the week. The attachment shows a comparison of ITMX and ITMY top mass osems (ITMY oplev beam is not on the QPD in safe mode) during the EQ, ITMY was swinging by more than 60 urad peak to peak while ITMX which had suspension damping loops engaged was swinging by about 20 urad at most.
I've turned on the damping on ITMY now. I also hit the button RECOVER EQ on the ISI_CONFIG screen, I got some errors from the script but it did take the ISIs to the windy state (screenshot attached).
It might be good to add to the operator tasks a check that suspensions and ISIs are in a good state before leaving for the night or weekend. (ie, if suspensions are not damped, operators could make sure they know that it is intentional and there is a good reason for it). Leaving our suspensions damped as much as possible will help us avoid some problems similar to what we had after the Montana EQ last summer. (For reference, while the suspensions were undamped during that EQ they were moving by 10,000 urad peak to peak, so this EQ is not really comparable.)
The original script I wrote for recovering the seismic platforms seemed to have been deleted in the svn update, so I had to write a new one and never got a chance to test it. I've fixed the recovery script, tested it and added it to the svn. With the laser down and not much going on in the way of commissioning right now, I would suggest it is safest to leave the seismic configuration in the state that the red button puts everything. The script doesn't touch the suspensions though.
This is probably my fault. I set ITMY SUS to safe on Feb. 21 before Filiberto started disconnecting cables and didn't think to set it back.
Remember that no files were deleted during the SVN 1.6 to 1.8 upgrade. The original userapps working directory was renamed userapps_1.6. If a file is needed in the new userapps area but it is not under SVN control and it should be, please add it to the repository (using userapps_1.6) and then do an svn update in userapps (please do not just copy the file across). I am happy to help.
Details in alog Link
Changes to the suspension state should be explicit in the WP and it should not be closed until all those steps are completed, I should think.
Patrick, I don't think this is anyone in particular's fault, it is just something that is not anyone's responsibility at the moment. We just need to figure out how to make it routine to check that suspensions are damped, which we hadn't had as a part of any checklist before.
I texted Gerardo and Chandra when arriving and will when leaving or 6pm, whichever occurs first. Will also finish rough pumping the Vertex. I expect to be here until around 6pm and will make a comment to this entry when leaving. I can be found in the LVEA, Mechanical Room (Kobelco area), VPW, Y-mid VEA or my office. I won't be craning, on ladders or using power equipment.
Need until 7pm
Leaving site now.
Terry, Daniel, Nutsinee
Two weeks ago ISCT6 got craned over from the SQZ bay to HAM6 (alog40588). We hooked everything back up but was only able to check the alignment when the LVEA became laser Hazard on Thursday. Pretty much everything became misaligned, from small amount of misalignment into the SHG to catastrophic amount of misalignment into the fiber couplers. Below is a summary of the work we did to get the table back to the condition it once was.
SHG
Because we got rid of the extension cables the RF35 phase shifter needed some adjustment (now 193.88 deg) and a sign flip on the common mode board was required. I tweaked the alignment to get rid of a higher order mode. The mode matching is currently 98.6% (about as good as it gets). I took a transfer function to make sure that the UGF hasn't changed (~3kHz). We also took a measurement of shot noise, dark noise, and SHG length noise (weekend, when the LVEA is relatively quiet). These measurements will be posted in a different alog.
Alignment to fiber coupler
Alignment land is still work in progress. We got every thing back up to over 60% and 70% coupling efficiency as of Saturday. For a reference, this is what we were able to achieve before (alog40342) and should be able to get them back to at least the same efficiency given more time. The pump light now has 15.8mW coming out of the fiber. CLF has 10.2 mW coming out of the fiber (still a lot of room for improvement).
CLF AOMs
For a reference, this is what we used to have when the table was in the SQZ bay: alog40198.
We are now getting more RF power coming to the amplifier (extension cables were surprisingly lossy). The top RF amp that drives AOM1 used to not have any attenuator, now has 3dB attenuator at the input. RF power measured at the output to the AOM1 is now 34.29 dBm, or 2.68W. Maximum drive power allowed for this AOM is 2.9W.
The bottom RF amp that drives AOM2 used to have a 6dB attenuator, now has 10dB attenuator. RF power measured at the output to the AOM2 is now 32.83 dBm, or 1.9W (.2dBm less than what it used to be in the SQZ bay). Maximum drive power allowed for this AOM is 2.2W. Putting 9dB attenuator would have given 33.56 dBm (2.27 W) at the output. Which is slightly more than maximum drive power allowed.
AOM1 (IntraAction ATM-200) now has diffraction efficiency of 83%, AOM2 (AA Opto Electronic MT200) now has coupling efficiency of 69.7%.
Flippers
We found that CLF and Pump flipper wasn't working. We were able to open and close the shutter by hand which implies that these flippers were not getting any power. Turns out these DC plugs from Thorlabs are very dodgy. We unplugged the cables and plugged them back in that seems to solve our power issue.
Pump flipper still wasn't working then. It was not getting any signal from Beckhoff. Turns out the new cables from the EE shop we put in for I/O1 was bad (again, how? I have no clue). SQ_259-2 was removed then replaced with a temporary cable. I suspect these bad cables are acting like something of a high resistance. Which would explain the issue we once had with the cable at the output of an RF amplifier (the signal came out to be 30dB less than what it should be). But does that explain why we're not getting any DC signal to the flipper?
Motorized Rotation stages
All working fine.
Stray beams
We went around the table and hunt for any stray beams we could find. Several additional beam dumbs have been installed. There should be no stray beam higher than a milliwatt leaving the table at this point. In fact there should't be any stray beam leaving the table at all. Both red and green.
Nominal laser box settings
Current = 2.182 A
Crystal Temperature = 25.98 C
Diode Temperature = 20.22 C