After centering the beam on SR2 and on the OFI, HAM6 iris closer to HAM5 was temporarily removed to the side.
ZM2 was adjusted so that the beam is centered on it while the reflection goes to the center of the HAM6 iris closer to VOPO.
HAM6 iris closer to HAM5 was put in place, it went to slightly different location than it was originally at, but that's perfectly acceptable.
We checked the beam position in HAM6 in the OMC path and moved OM1 and OM2. What we did is mostly consistent with what I wrote in alog 39504 right after the septum window was rotated 180 degrees:
After this,
As soon as we put the fast shutter in place, though, it was apparent that the beam from HAM5 was too close to the fast shutter structure (see attached). This could be mitigated by pushing OM2 back into -X direction by 10mm or so. This will push the OM1-OM2 line by about 4mm or so in -X direction at the fast shutter position, so the clearance will be that much larger, and the clearance between OM1-OM2 line and OM3 cage should still be OK.
Before we actually did this exercise we were afraid that there would be no good solution because of the fast shutter unless we push OMC in -X direction, but we convinced ourselves that moving OMC is unnecessary.
OM2 is in its non-final location, and it only has two dog clamps right now because the original dog clamp was too short for this new position. We might need a longer one.
Lock IMC and send a stable beam into HAM6.
Reposition everything so that the entire beam path has OK clearance from any edge (push OM2 in -X by 10mm or so, rotate OM1, rotate OM2, reposition fast shutter).
Rotate OM3.
Fine-tune to send the beam to both of the QPDs on OMC. For this, we probably have to remove OMC shroud.
Reposition OM2 transmission beam dump.
Move all mirrors/lens/ASC-AS_C in OM1 transmission path by 14mm in -X direction.
Do the OMC REFL path beam dump properly.
(Kyle R, Gerardo M)
Last night while doing some work around the HAM5 I noticed the door cover for HAM5 being "sucked in" (see photo), that occurred every time someone removed the door cover to any other HAM chamber (4,3 or 2), it turns out that the new cleanroom creates great positive pressure causing the door cover for HAM5 to appear as being "sucked in". So I ran a little test, while one of the other door covers was off and HAM5/HAM6 door covers on, I pushed some of the cleanroom curtains open, and that relieved some of the positive pressure created by the cleanroom HEPA fans, that allowed the purge air to "balloon" the door covers on HAM5, and as soon as I closed the curtains the door covers went back to getting pushed in towards the chamber.
Today Kyle and I used a long ladder to get access to some of the HEPA fans, there are 20 of them on that cleanroom, we dialed down 7 of them and there is a noticeable difference already, we plan to dial down some more tomorrow as work on that chamber allows it.
You guys should check that the gap at the foot of the curtains is correct - refer to PSI drawings - this is intended to exhaust the air without building pressure in the cleanroom. It may be better to leave the flows at nominal and relieve pressure that way. By dialing back the hepa units you are decreasing the volume flow rate of clean air which may not be the right thing to do.
This cleanroom is the "gerbig" style with 20 HEPA filters and 1 ft clearance at bottom (non adjustable legs). We checked the particle count after dialing down flow; cleanroom is still running well below Class 100.
Thanks!
Noted that at about 10 am - 10:04 am PST on top of End Y, the anemometer was pointing to about 20 deg to the -Y of +x and that sensor is not moving very smoothly.
The sensor is on the upper roof, about 1/2 way along Y, and about 8 feet from the +x edge, and about 6 feet up.
10 am = 1196013618 for 600 sec - epics data says that EY is about 360. so this is = north
Perhaps the EY sensor is aligned with north, but need to recheck.
tconvert 11:00:00 pst -> 1196017218
at 10:59 am, the EX sensor was pointed in the +x direction. It then moved to point in the -Y direction.
at GPS time 1196017200, the direction reading for EX is 183 deg.
at ...17254, it moves up to 271 degrees. I think this means that EX wind direction is aligned with the observatory coordiatates. That wind coming from the +x direction reads +180, and wind coming from the -Y direction readys 270. This is not crazy, since wind blowing from -x towards +x would read 0.
The EndX direction monitor is moving smoothly. I also note that the black hat thing has come off. looks like it used to cover a wire wound resistor and a toggle thing. I do not know what it is supposed to do, but it will probably be happier with the cover replaced.
I assume the black black hat thing is the cone that collects the rain. The toggle thing is the rain gauge. The heating resistor is there to melt the snow.
Went back and checked the EY anemometer this afternoon. Looks like the direction indicator for that one is not working correctly. At 3:39 pm I held the direction indicator so that it should read wind from the +X direction (180 according to Robert's site standard, see alog 28456 ). I held it there for about a minute, then pointed it so that it appeared to be a wind from the -Y direction, and should read 270. Held again for about a minute, then pointed back to +x (which is about where I found it, and where the wind is actually coming from). In the attached plot below, you can see that it isn't reading correctly, and also seems pretty noisy. (at about t=0, it should read 180, not 240, and around t=60, it should move up and read about 270, not 340)
Anyway, the EY anemometer direction is not to be trusted until Richard has a chance to take a look.
S. Dwyer, K. Kawabe, J. Kissel, B. Weaver, G. Moreno, C. Vorvick We've completed the by-hand alignment work needed with the PSL beam, picking up where we left off yesterday (LHO aLOG 39553). That means, we've reconstructed an alignment (using steps 1-11 in LHO aLOG 39547) to get a well-aligned PSL beam from the IMs, centered through SRM and coming out of the OFI well, and then repeated steps 12-14 from LHO aLOG 39553 which where unsuccessful yesterday: (12) make sure ZM2 was well aligned by (a) inserting the temporary half-wave-plate into the output apeture of the OFI faraday rotator, then (b) mechanically adjusting ZM2 to hit the last (most -Y, closest to the future VOPO) iris on HAM6 as shown in Figure 4 of E1500469, then (c) sealing in the alignment reference by placing the other iris (most +Y, closest to HAM56 septum) in the beam path and aligning it to the beam. (13) make sure that SRM is well-aligned by (a) first mechanically adjusting the alignment *some* this morning with the aux laser -- see LHO aLOG 39556, then (b) further mechanically adjusting the alignment the *rest* of the way, using the well-aligned PSL beam, then (c) fiddling with the sliders, until we see fringing patterns at SR2 with the SRY cavity aligned again. Because Betsy is awesome, we see fringing with zero digital alignment bias on SRM. BOSS!! (14) make sure that PRM is well-aligned by (a) driving it digitially with slider bias, (b) looking for fringe fringe patterns at one of the ITMs (we chose to misalign ITMX, and look for fringing on ITMY from the PRY cavity) (note, chronologically, today, we did steps 14, then 13, then 12). Attached is a screen shot of OSEMs and sliders once we got SRM aligned, and SRY was flashing. PRM and ITMX are mis-aligned during this screen shot: their slider values should be PRM -995.6 in pitch (yaw should be as shown), and ITMX should be +189.3 in Yaw (pitch should be as shown). Notes: - We're still using only one set of cables to control the OFI, OMs 1-3, or ZMs 1-2, and they all are fed into the CDS system as OM1. We had last used that set of cables to test the OFI (see LHO aLOG 39033). Which means when Betsy and Travis plugged in that set of cables into ZM2 to align and center ZM2's OSEMs this morning, the control system was still configured for an OFI. I've fixed all that, and it's now working as a standard HTTS, and we've confirmed that we can push ZM2 to steer the beam as needed into HAM6, AND, I've confirmed that damping works (though just with a quick look at the MEDM screen). I attach a screen shot of ZM2 functional in the OM1 infrastructure, functionally running as an HTTS. - As of writing this log, Keita, Sheila, and Gerardo are still out there making the changes to the OM1, OM2, and OM3 alignment, as described in LHO aLOG 39504. I attach some notes about their re-assessment of the plan this evening, which had to be re-measured because LHO aLOG 39504 was thought out before the septum window was rotated. Great work again today team, and good luck to those still out there!
While alignment work was happening in other areas, Travis and I worked on getting the ZM2 OSEMs useful. Fil and Richard helped me hook ZM2 satellite cable up to the OM1 since the ZM2 medm is all white. We took the OLVs and then set all 4 BOSEMs to the 50% OLV mark.
Note, since the cables between the rack and the chambers have not yet been run, we will have to move the 1 temp cable between boxes, one at a time for OM1, OM2, OM3, ZM2, and the OFI during the imminent closeout testing.
ZM2 BOSEM Details:
Location | S/N | OLV | 50% OLV |
UR | 280 | 31000 | 15500 |
UL | 252 | 30200 | 15100 |
LR | 259 | 32767 | 16383 |
LL | 027 | 28000 | 14000 |
Cables used are:
D1000234 S/N S1000694
D1000225 S/N S1106781
smoke test at EndX - Brian Lantz, Jim Warner, Siddhesh Pai, Brijesh Pant
Nov 29 2017, about 2:08 pm local
used 1 2B candle from superior signal
burn is ~60 sec.
https://youtu.be/XbouhfAK1Mg
smoke candle is ~10ft in front of the fence,
The smoke candle is about 11 ft. up off the ground, close to the vertical center of the fence material. The picture below shows the pole we used w/ Jim as scale standing next to the fence - The smoke emitter will be placed at the height of the blue tape on the pole.
We took several videos, the one from Brian's phone is linked above.
The smoke trail clear to the fence, but often difficult to see downstream of the fence. Why?
1. partly due to blue sky behind early trail and clouds behind late trail. note this for future film angles
2. trail is darker behind fence - might be some shade?
3. trail is getting bigger.
4. the place where the candle burned though was next to the post.
- next tests we might try 2 candles together, and try to shoot against blue sky. i'm not sure I have enough candles to use 2 each for all my desired tests.
We see that the smoke moves through the fence. It seems like the fence might be "softening" the edges of the trails my generating lots of short scale mixing, but the structure at the ~1 foot scale seems unaffected by the fence.
Is the air moving more slowly behind the fence? Maybe? I sort of looks this way, but I can't understand how this would be true, if none of the air flow is getting diverted up-and-over or sideways-and-around the fence.
1. It is not going up over the fence -> if you assume the same density, then conservation of mass suggests that the speed on the two sides needs to match.
2. It might be slipping sideways instead of going over - this could allow slower speeds and would not be visible from this camera view -
3. It sort of looks slower - this could be the result of the smoke getting further away from the camera as it moves downwind. how to watch for this at EY?
- maybe have a camera on the ground at the corner of the building looking up?
4. The structure of the plume moves right though this fence. The fence can't be adding large, immediate changes to the vertical velocity
More videos and pictures will be added, and we are planning to do some additional tests on Friday.
Jim set up an anemometer a bit (something like 50 feet) upwind of the fence to record the wind speed. Data download is pending.
Attached plot shows the wind speed recorded by the upstream ground anemometer during the smoke test. I'm also including the CSV data from the sensor. Apparently the alog won't allow CSVs, so I renamed it to a text file. w/e
TITLE: 11/29 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC STATE of H1: Planned Engineering LOG: 16:48 UTC Terry to squeezer bay, laser hazard (all day) 16:49 UTC Peter to optics lab 17:22 UTC Nutsinee to squeezer bay 17:37 UTC Kyle to mid stations 17:38 UTC Rakesh, Brian and Jim to end X 17:39 UTC TJ to LVEA and then optics lab 17:40 UTC Betsy and Travis to LVEA, start of SRM alignment Filiberto to CER, cabling for ZM2 17:57 UTC Kyle to end stations 18:09 UTC Hugh to HAM6, CPS shortening issue 18:33 UTC Karen and Vanessa to mid Y to clean 18:37 UTC Kyle back. Kyle and Gerardo to LVEA to check orientation of gate valves. 18:37 UTC TJ out of optics lab 19:00 UTC Jason to HAM5 to build AWC mounts 19:09 UTC Peter out of optics lab 19:16 UTC Rakesh, Brian and Jim back 19:28 UTC Kyle out of LVEA 19:29 UTC Karen and Vanessa leaving mid X 19:50 UTC Greg to TCSY table 20:24 UTC Keita and Jeff K. to LVEA 20:37 UTC Travis and Betsy back 20:38 UTC Jason back 20:47 UTC TJ to optics lab 20:58 UTC Corey taking guest on tour through LVEA 21:03 UTC Betsy to LVEA 21:15 UTC Jim and Brian to end X to take videos of smoke trails 21:48 UTC Betsy and Richard to CER 21:54 UTC Corey back, taking guest to overpass 22:09 UTC Gerardo to HAM5 22:51 UTC TJ back 22:54 UTC Jim and Brian back 23:00 - 23:38 UTC Site weekly meeting 23:52 UTC Hugh to HAM5, cabling for OFI
All doors that were removed (HAM2,3,4,5,6 N and S, and BSC 3 and BSC1 biergarten side) had proper viewport protectors on them either already, or when the tables were disconnected and removed. See pictures of all doors that are hanging around LVEA, removed from chambers.
This assay is in response to something LLO brought up in FRS https://services.ligo-la.caltech.edu/FRS/show_bug.cgi?id=9479
LIGO-M1100039-v5 (LHO HAM Door Removal and Installation Procedure) and LIGO-M1100068-v5 (LHO BSC Door Removal and Installation Procedure) already require that the Lexan shutters be in the closed position prior to door removal/installation.
The TCS CO2 tables have had the new periscope optic mount installed. Y-arm required a small modification to allow parts D1600106-V1 and D1201310-V2-01 to fit together. These new pieces have not been aligned to the table, or in-vacuum as yet.
FAMIS 6926 ETMY_ST1_CPSINF_H2 and ETMY_ST2_CPSINF_V2 are elevated. Plots posted for end X and end Y. All others ISI platforms are locked.
Travis and I spent the morning realigning the SRM suspension in order to bring the pitch up onto IFO beam paths. We used the red visible AUX1 laser to do this since it was much easier to hunt in the HAM4-5 Tube. After walking the ~3" diffuse beam around everywhere we finally managed to set it on the right path. We realigned all of the OSEMs which then saw this repointing and then looked at a few quick TFs to see that it still looked free. We're handing back off to IR alignment team who are re-mapping the PSL beam to HAM5 for continued OFI alignment.
FAMIS 6551 Added 200 mL H2O to the crystal chiller. The fault light on the diode chiller is not lit and the water level indicator on the controller screen indicates the water level is OK. The canister filters appear white and free of debris.
Since the reflection of IR beam on septum window AR is so small, we shot a red laser pointer beam from HAM5 through septum so the beam clears the HAM6 iris closer to HAM5, and falls on the second iris closer to VOPO within a mm from the center. Sheila calculated the deflection difference between IR and red, and it's so small it doesn't make much difference over the lever arm (a meter or two) in this case.
There were two beams coming through the septum, we took the first one (brighter, and towards +X) as the main beam.
There were three beams reflected off of the septum into HAM5. We took the first two towards +X as the main beams to dump.
We also confirmed that the scribe mark showing the thickest side of the septum is -X for the ZM path and +X for the OMC path.
Pictures will be added later.
1. Looking at the zm path septum window from HAM6. Laser pointer is in HAM5, already aligned. The beam spot on the septum is all inch or so away from the +X edge.
2. How the two AR reflections are on the beam dump but the third beam which should be AR of AR is not caught. This should be ok.
3. ZM path in HAM5.
4. ZM path septum scribe mark, -X.
5. OMC path septum scribe mark, +X.
SYSTEMS alert:
Potentially, the location of the HAM5 septum baffle needs to be adjusted accordingly because the septum window for the main OMC path is rotated 180 degrees WRT the design.
The first reflection by the septum window is not affected but the second reflection (i.e. reflection by the surface on the HAM6 side) will move from -X side to +X side of the first reflection.
TJ is contacting systems to figure that one out.
Pictures were taken after the FS was placed as close to OM3 as possible and aligned.
1: FS viewed from HAM5 side. The beam from HAM5 is very close to the edge of the aluminum structure of FS. It's hard to see from this but the clearance between the beam and the wire is good.
2: FS and OM2 viewed from OM1 side. The beam reflected by OM1 is actually hitting the center of the FS mirror though you cannot see it in this picture.
3: FS from OM1 side, with a card to show the beam position on the FS mirror. The wire loop on the right is more or less how I expect it to be, but the loop on the left is not. The left loop is actually going under the left stopper arm. You'll understand this better if you look at the first picture again (note that left on this picture is right on the first picture). Should we fix this?
Position of ham6 zm path iris closer to vopo (1st) and to HAM5 (2nd).