Dave Barker, Jeff Bartlett Dave removed dust monitors #2, #3, #4, and #30 from the LVEA dust monitor software. These monitors have been removed from the LVEA. Currently dust monitors #5, and #6 are running to support work in HAM5/6 and dust monitor #10 is the permanent LVEA monitor in the Biergarten. I will be updating the "check monitors are working" script and AlarmHandler shortly. Closing WP #7277.
On Aug 29 & 30, while at vacuum, the elevations of the HEPI piers were measured with Optical Auto-Level--LHO aLog 38584. On Sept 20 and 27, the HAM Piers were measured again--38776 & 38810, now with the Vertex was at atmosphere. Today, after the Vertex (sans HAM6) is again under vacuum, the piers were sighted again.
The conclusion here is while there are some changes while vented and when back to vacuum, the most is a few tenths of a millimeter and amount to ~100urads of tilt in the worst case. Not necessarily tiny but not horrible. Attached are my surveying notes from today and the deltas from before, during and after.
The LVEA has transitioned to LASER SAFE.
This morning the main laser screen reported an output power of ~152 W. This is significantly down from yesterday's value of ~180 W. Decided to increase the diode current of DB1 to the maximum. The reported power jumped up by ~20 W. Other fine tuning might prolong the inevitable.
I adjusted the diode temperatures for DB1 a little. The power indicated on the MEDM screen went from 135.3 W to 141.3 W. The Beckhoff main screen indicates a power of ~184 W. D1 is 27.0 degC, was 24.5 degC D2 is 27.7 degC, was 24.5 degC D3 is 22.5 degC, was 21.5 degC D4 is 23.5 degC, was 23.5 degC D5 is 22.5 degC, was 23.0 degC D6 is 27.5 degC, was 24.5 degC D7 is 24.5 degC, was 24.5 degC Altering the temperature of D3 does not do much. D3 is pretty much dead in my opinion.
T Vo, Sheila
We aligned PRMI a little bit. We started with PRX and PRY, and saw that our PRM alignment for PRX and PRY fringes has shifted by about -300 urad in pitch since Jan 17th. We used picomotors to center the IMC WFS because we saw that there was a shift on IM4 trans QPD today around the time that Cheryl would have been on IOT2L. Centering only moved IM4 trans a small amount back to where it was before Cheryl's work. We aren't sure if this is the reason for the shift in alingment of the input beam.
I was able to see PRMI flashes, not well alinged, by moving PRM, PR2 and BS, the overall impact was to move PRM back towards the Jan 17th alignment. We now have flashes on POP 90 of around 10 counts, (there is a 10 count offset, so flashes go up to 20 counts) with 1.2 Watts into the interferometer. We should be getting something like 100 count flashes, but it might just be that we aren't well aligned yet. I haven't adjusted anything on the table or adjusted teh demod phase, although the demod phase seems OK.
The attached screenshot shows the alingment for which we get small sideband flashes in POP90.
[Keita, TVo, Jenne]
With the OMC free-swinging with no alignment slider offsets, we closed the OMC ASC loops with OM2 and OM3 as actuators. OM1 is at 0 slider offset in pitch, and a small 450urad in yaw. This told us how we needed to offload the OM2 and OM3 sliders such that we're near the center of their range.
Much of the offloading needed was in pitch. For OM2, we removed the front earthquake stop holders, loosened the setscrew for the pitch adjustment (it was already loose enough that it fell out, but Keita caught it and re-installed it). We noted the OSEM Wit value when the pitch offset slider was at its large value, set the slider to zero, then adjusted pitch to set the OSEM Wit value back to what it needed to be. Keita tightened the setscrew and replaced the earthquake stop holders. OM2 was then rotated a small amount to offload the yaw slider, and we re dogged the cage to the table. The procedure was largely repeated for OM3, although we did set some dog clamps as references, then moved the OM3 cage a little closer to the door so we had access to the pitch adjustment screw. OM3 was replaced after pitch offloading, yaw was offloaded, and OM3 was re dog clamped down to the table.
We have beam on both OMC QPDs, so should have no problem reclosing the ASC loops and then locking the OMC if we so desire.
N.b., beam height incident on OM1 was 104 mm, beam height incident on OM2 was 98 mm, beam height after reflection from OM3 was 102 mm.
To do:
YAW centering on OM3 is pretty good, if anything we could shift it (in parallel to the mirror surface) in +X+Y direction by 1mm but we didn't bother.
So, after I rebuilt the ETMY PenRe mass assembly D060341 late last week, this morning Travis went to exercise it's central Pitch adjusting bar to check for it's ease of slide, needed for in-situ alignment. He found that it was extremely difficult to move. (I hadn't thought it was so bad last week, but I used isopropanol to insert it and was able to have it slide around - probably finding the lucky and illusive "sweet spot" with these. Now, the isopropanol wasn't even helping. Once mated to the monolithic ETMy optic set we will not be able to use isopropanol to get it to slide anyways fo fear of dripping onto optic/fibers.) We've had troubles with this fit in the past and believe there is an issue with tolerances in the drawings which we never reworked, instead just "making due". Tried as we might, when dry we could not "make due" today. We even tried filing down any miniscule burrs and even swapping with the 1 remaining spare, which seemed just as bad of a fit. So, we've lost a day to this now and will need to consider something more drastic in the morning such as opening up the center hole in the main mass D060342 and rebaking the part or find a suitable spare in 3IFO inventory (not trivial because it means painfully relocating an pre-assembled lower QUAD unit into a clean space, opening it, disassembling it's PenRe and hoping for a better fit with the borrowed parts). TBC...
Today, Jim and I installed the 4 vibration absorbers on the EY PCAL Periscope. Since we only had the one type of D1600401, we had to mount them on the 45deg spokes as shown in D1200174 on the last page. See attached pictures, though kind of hard to get good shots due to access.
One issue we ran into is that the vibration absorber assembly drawing (D1002424) says to use 1/2" long 1/4-20s with a washer to mount D100895 to D1600401. We found that the screw would still poke out the back even with a thicker washer. We had to double or triple washer stacks to keep them from protruding.
I forgot to mention that we mounted the vibration absorbers on the 3rd and 5th spoke holes, counting from the inside.
Also, looking at the drawings for D1600401 and D1000895, there should be 0.54" of material for the screw to go through. With a washer on as well I am very surprised that we had any issues. The bag of screws we used was labeled as 1/2" long, and I did a quick look on a ruler to confirm, but perhaps they were really 9/16".
Tightened the (as found closed) 10" gate valve at CP4 and then vented the non-CP4 side. There may have been a slight improvement in CP4's pressure as the result of this exercise (see attached graph). I was working alone and wasn't able to observe the peak pressure on the connected pump cart when the unpumped "dead volume" of the gate valve was valved-in to the pump cart but I could tell that the gas load was enough to slow the pump cart's turbo. Tomorrow I will remove the 10" gate valve's zero-length reducer and install the turbo, gauge, valves and RGA components needed for the decommissioning of CP4 later in February.
Filiberto, Hugh, Patrick, Richard This morning Hugh and I took the end X ISI guardian to ISI_DAMPED_HEPI_OFFLINE. Hugh and Filiberto then went to end X and Filiberto moved the wiring from the existing HEPI pump controller box over to the Beckhoff box. We found some minor issues with the Beckhoff PLC code that I corrected. Restarting the PLC code tripped off the power to the HEPI pump motor and I went to end X to reset it. We have since tuned the Beckhoff PID (actually just PI) and will leave it running overnight.
Filiberto, Richard, Patrick Today we took it off of PID control and ramped down the VFD. Filiberto then went to end X and connected the VFD readback signals to the Beckhoff terminal. We then turned the PID back on. It is currently keeping the differential pressure at 70 psi.
Finished venting IP4 with bottled UHP N2 (started Friday afternoon then halted). Also vented (with bottled UHP N2) non-VE side of closed 12.8" gate valve (new VAT valve) mounted on OMC tube and having 16.5"-2.75" CFF zero-length reducer flange with 1 1/2" pump port valve. New valve doesn't leak! Chandra will be in early tomorrow to remove connected equipment and supervise installation of IP4 onto the OMC.
TITLE: 01/29 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
16:00 (8:00) Start of shift
16:15 (8:15) Hugh to End-Y -- HEPI filter change
16:22 (8:22) Ken to End-X -- Piping work
16:48 (8:48) Hugh out of End-Y
17:47 (9:47) Bartlett to termination slabs -- ITM camera work
17:57 (9:57) Phil to End-X -- Looking at cabling for HEPI
18:36 (10:36) Cheryl to IOT2L -- Align cameras
18:45 (10:45) Ed to HAM6 -- Inspect wire
18:58 (10:58) Jenne, Keita and TVo to HAM6
18:59 (10:59) Phil out of End-X
19:00 (11:00) TJ and Jim to End-Y -- PCal baffle work
19:03 (11:03) Hugh to LVEA -- Retrieve hardware
19:12 (11:12) Phil to End-X
19:15 (11:15) Hugh out of LVEA
19:45 (11:45) Cheryl out from IOT2L
20:01 (12:01) Bartlett out for lunch
20:08 (12:08) TJ and Jim out of End-Y
20:10 (12:10) Phil and Hugh out of End-X
20:20 (12:20) Jenne, TVo, Keita out of LVEA
20:59 (12:59) Bartlett to termination slabs -- ITM camera work
21:05 (13:05) TJ and Jim to End-Y -- PCal baffle work
21:10 (13:11) Kyle to HAM4 -- climb up OMC tube
21:13 (13:13) Travis and Betsy to End-Y -- Putting ETMY back together
21:29 (13:29) Ed to CER -- Terminate cables
21:35 (13:35) Kyle out from HAM4
21:53 (13:53) Peter and Gerardo to Optics Lab
22:06 (14:06) Bubba and Mark to LVEA -- Work on snorkel lift
22:27 (14:27) Elizabeth to HAM6 -- Scan components
22:36 (14:36) Patrick to End-X -- Reset power to HEPI pump control
22:40 (14:40) Nutsinee to ISC Rack
22:40 (14:40) Bubba and Mark out of LVEA
22:50 (14:50) Nutsinee out from ISC Rack
22:53 (14:53) Patrick out of End-X
23:13 (15:13) Bartlett out from termination slabs
23:26 (15:26) Jenne, Keita, and TVo to HAM6
23:30 (15:30) Peter and Gerardo out of Optics Lab
23:47 (15:47) Elizabeth out from HAM6
23:49 (15:49) Terry to SQZ bay
23:54 (15:54) Ed out of CER
0:00 (16:00) End of shift
We need to restore ALSX for peeking down the X arm.
We have OK fiber power (though RefCav trans is smaller than it used to in O2), and polarization at EX is not bad either, but there's no beat note.
Left: O2, Right: Now.
Could be that the frequency is too far off or the alignment is somehow bad.
The beam on top periscope mirror is roughly centered (this is a change from a few weeks ago), so the beam coming off of the bottom periscope mirror was too high. Adjustments made to clear iris/HWP/CW and beam dumps, and REFL, WFS1, WFS2, and camera recentered.
I'm emerging from sick leave, so this would be a good time to give a CDS computing summary:
Timing is in error. At around 3am PST Thursday 25th the MCA atomic clock time distribution system went into alarm. Trends suggest its time was varying for about an hour, and then settled to a static large offset. All three comparators in CS, EX and EY see bad times and are reporting the error.
h1oaf model is now consistently running long and reporting timing errors. This started Tue 16th Jan, presumably due to filter changes. I am investigating.
New filters need to be loaded for h1sqz, h1ascimc. If we don't get to this today, we'll cover it tomorrow during maintenance.
Surprisingly h1oaf's cpu issues are not filter related. It appears that the decommissioning of the h1ngn model on 1/16 has caused it to run long, even though there is no IPC between these models. I'll try a complete model restart on h1oaf0 tomorrow.
Commissioning:
CDS:
End-Y:
Mid-Y:
End-X: