Displaying reports 46801-46820 of 87739.Go to page Start 2337 2338 2339 2340 2341 2342 2343 2344 2345 End
Reports until 10:07, Wednesday 23 May 2018
H1 SUS
betsy.weaver@LIGO.ORG - posted 10:07, Wednesday 23 May 2018 - last comment - 11:15, Tuesday 03 July 2018(42145)
ETMX In-chamber work status

Yesterday, Travis and I worked on finishing the reaction chain cabling now that the ESD connection is back to working.  We also fixed the noisy signal on the L2 UL OSEM by swapping the short quadrapus cable D1002524 that connects to all 4 L2 (PenRe) AOSEMs.

D1002524 s/n 904 was removed and 905 was installed.  Note, there are no more spares at LHO of this type of cable.  Will look into getting spares. 

While at it, we swapped 2 AOSEMs which had open light voltages which decayed down to 15k (from 30k).

We then aligned the L2 AOSEMs to the flags on the PUM, in a few iterations.

We made a few more alignment tweaks to both chains and then ran a series of transfer functions to make sure all 8 masses were fully suspended and free from mechanical interference.  

Details of this were posted by Travis on the original alog associated with the L2 UL signal, below.

Comments related to this report
betsy.weaver@LIGO.ORG - 10:19, Wednesday 23 May 2018 (42146)
Integration issue generated, see Bug #929.

travis.sadecki@LIGO.ORG - 16:23, Tuesday 22 May 2018 (42127)

Betsy and I swapped the quadrapuss cable to the L2 (PUM) AOSEMS.  This seems to have fixed the noise issue that had been plaguing the UL OSEM for several years.  See attached spectra for comparison.

After swapping the cable, we noticed that the 2 lower AOSEMs at the L2 stage (LL and LR) had low OLV values, so we decided to swap these as well.   We also took OLV values for UL and UR that were not replaced, but are dying of natural causes.

  Old S/N New S/N Old OLV New OLV Old Gain New Gain
LL 270 332 18726 18050 1.602 1.662
LR 483 473 25518 18150 1.176 1.653
UL N/A N/A 17934 21300 1.673 1.408
UR N/A N/A 25124 20600

1.194

1.456

 

betsy.weaver@LIGO.ORG - 10:20, Wednesday 23 May 2018 (42147)
jeffrey.kissel@LIGO.ORG - 11:15, Tuesday 03 July 2018 (42747)
These new open light current compensation values have been accepted into the SDF system.

H1:SUS-ETMY_L2_OSEMINF_UL_OFFSET -9000
H1:SUS-ETMY_L2_OSEMINF_LL_OFFSET -12291
H1:SUS-ETMY_L2_OSEMINF_UR_OFFSET -10612
H1:SUS-ETMY_L2_OSEMINF_LR_OFFSET -10163

H1:SUS-ETMX_L2_OSEMINF_UL_GAIN 1.408
H1:SUS-ETMX_L2_OSEMINF_LL_GAIN 1.662
H1:SUS-ETMX_L2_OSEMINF_UR_GAIN 1.456
H1:SUS-ETMX_L2_OSEMINF_LR_GAIN 1.653
LHO VE
chandra.romel@LIGO.ORG - posted 09:44, Wednesday 23 May 2018 (42144)
HAM 6 pressure is safe for high volts

HAM 6 pressure is at 4.9e-6 Torr, well below the 1e-5 Torr HV interlock set point. I gave Jenne and Sheila permission to turn HV ON.

We will continue to pump HAM 6 with turbo. If for some reason the turbo trips, the pressure gauge on HAM 6 is interlocked with HV.

H1 TCS
jason.oberling@LIGO.ORG - posted 09:30, Wednesday 23 May 2018 - last comment - 11:03, Wednesday 23 May 2018(42142)
TCSy CO2 Water Leak

This morning, a leak sprung on the TCSy CO2 table.  One of the dry break fittings on the supply manifold lost its seal and dumped just about the entire contents of the chiller onto the table.  With a quick initial assessment, I don't see any optics that were contaminated (the water manifolds are in the SE corner of the table, away from the optics).  Jeff Bartlett is currently cleaning up the water and repairing the broken fitting; if he can find a spare it will be replaced, if not it will simply be capped as it was an unused port on the manifold.

Edited to add: I took a couple quick pictures of the broken fitting, see attached.

Images attached to this report
Comments related to this report
jason.oberling@LIGO.ORG - 09:31, Wednesday 23 May 2018 (42143)

Filed FRS 10736.

jeffrey.bartlett@LIGO.ORG - 11:03, Wednesday 23 May 2018 (42148)
    Installed plug as replacement for leaking dry break fitting. Refilled the chiller with lab water and restarted the system. Observed no leaks on the table. Could not find a replacement dry break fitting. If TCS does not have spares, will order several pairs.  
H1 AOS
aidan.brooks@LIGO.ORG - posted 09:16, Wednesday 23 May 2018 (42139)
ETM HWS source replacement - status update day 2 - return beam from ETM detected. Poor beam quality

[Aidan, Marie, Dan B, Alexei, Keita]

Yesterday morning we realigned the ALS beam into the vacuum system, confirmed it was centered on the TMS QPDs, confirmed it was coming out again and was centered on the in-air WFS and confirmed that it was getting back to the ALS length PD. The two irises installed after the PBS were centered on this ALS beam.

We then aligned the LED beam through the PBS and through the two irises. By carefully fine-tuning this alignment as best we could by eye, we found that there was a return beam coming back to the Hartmann sensor.

The return beam is quite sensitive to alignment. There is a narrow window of adjustment of the pitch and yaw on the final two HWS mirrors. Small changes (fractions of a turn) can make the beam disappear entirely. We don't have picomotors on these actuators so we can't easily quantify what "small" means here.

We were able to get images of the return beam on the Hartmann sensor camera. We started with the Hartmann plate in place but eventually took it off and saw the intensity distribution of the return beam. It looks quite mottled and smaller than expected. 

We spent the remainder of the day trying to improve the spatial quality of the return beam. It looks like it might be clipped in multiple places or is experiencing some diffraction off particulates on optics - we're still investigating. We experimented with trying to change the divergence of the beam coming from the fiber launcher as well as removing the iris that was in front to get more of the beam through.

Due to concerns about clipping, we temporarily removed the PBS so that the HWS beam didn't have to contend with that small aperture.

The goals today are to:

 

Images attached to this report
H1 General
edmond.merilh@LIGO.ORG - posted 08:16, Wednesday 23 May 2018 (42141)
Shift Transition - Day

TITLE: 05/23 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind: 11mph Gusts, 8mph 5min avg
    Primary useism: 0.03 μm/s
    Secondary useism: 0.13 μm/s
QUICK SUMMARY:

 

LHO VE
kyle.ryan@LIGO.ORG - posted 18:07, Tuesday 22 May 2018 (42135)
Leak tested CP4 CFF joints / Reassembling GV11 and GV12 external hardware

Chandra R., Gerardo M., Kyle R.. Ken D.

Today we helium leak tested the CFF joints on CP4.  With the 55 L/s ion pump valved-out and the leak detector backing the 450 L/s turbo pump (which was valved-in for this exercise), each CFF joint was sprayed with an audible flow of helium for 10s of seconds each.  The nominal helium background signal was < 2 x 10-9 Torr*L/sec during testing.  Additionally, Chandra partially filled the (now empty) inner LN2 vessel with helium via applying helium to the bottom level sensing line and allowing the displaced air to exit the upper sensing line.  This test was incomplete in that the exhaust exiting the upper level sensing line was not monitored for O2 concentration and thus the helium concentration within the inner LN2 vessel could not be determined. 

A pressure accumulation test was also done.  For this test, all pumps were valved-out and the pressure within CP4 was allowed to rise (see attached graph). 

By all indications, CP4 seems to have survived the months-long bake exercise unscathed.  Of note too was that, while being pumped by only the turbo during leak testing today, that the pressure achieved nearly the same value as had been observed just prior to the unexpected turbo shut down last Thursday. 

Ken D. is well on the way to restoring the electrical connections that had been removed to accommodate the heated enclosure.  He also reminded us to consult with him later in the week prior to operating GV11 so as to review the details pertaining to the limit switches and motor rotation etc...

Gerardo M. and I have started to re-hang the annulus ion pump plumbing on GV11.  Chandra R. intends to be ready to open GV11 as soon as EOB Friday - stay tuned.  GV12 won't be opened until later.

Non-image files attached to this report
LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 18:04, Tuesday 22 May 2018 (42136)
Y-End Station NEG Pump

This morning ~16:45 utc the NEG pump attached to the south door on BSC6 was valved in to the chamber, see attachment for pressure change.

Images attached to this report
H1 IOO (IOO, PSL)
cheryl.vorvick@LIGO.ORG - posted 17:12, Tuesday 22 May 2018 (42134)
IMC input power PD not reading the same power as the measured beam - status of PDs in the IO path

Yesterday I measured the IMC input beam (measurement location: in front of the bottom periscope mirror), and compared that to the reading on the IMC IN PD.

IO path PD Status:

LHO VE
chandra.romel@LIGO.ORG - posted 17:02, Tuesday 22 May 2018 - last comment - 10:22, Friday 25 May 2018(42131)
corner pump down status

The pressure in corner station is 6.5e-7 Torr. Attached is a projection of *rough* dates at lower pressures. Ideally, we want to wait to open to the arms until the corner pressure is 1e-7 Torr on the turbos alone, and then valve in IPs and CPs. Last May when we vented corner for one day, we opened back up to arms at 2e-7 Torr in 16 days. Will consult Vacuum Review Board on how to proceed with opening up GV5 for y-arm commissioning.

Images attached to this report
Comments related to this report
chandra.romel@LIGO.ORG - 10:22, Friday 25 May 2018 (42187)
Images attached to this comment
H1 PSL
jason.oberling@LIGO.ORG - posted 16:55, Tuesday 22 May 2018 - last comment - 14:44, Wednesday 23 May 2018(42130)
PSL ISS Recovery

J. Oberling, P. King

Today we worked on recovering the PSL ISS, and began by re-installing the ISS AOM.  The AOM mount was moved to a place where the beam was ~1mm in diameter (unfortunately I forgot to take pictures, will take some tomorrow and upload as a comment) and installed the AOM.  The mirror that sits downstream of the AOM and reflects the 1st order diffracted beam into a beam dump was also re-installed and aligned.  A power meter was placed in this beam path and the alignment of the AOM tweaked to maximize the power in the 1st order beam.  We then adjusted the ISS offset to find the point where the AOM was diffracting ~2W; this was found at an offset of 8.0.  The offset was then set to 0, and increased to 20 in steps of 1; a power reading for the 1st order beam was taken at each step.  This allows for calibration of the diffracted power graph on the ISS MEDM screen.  Peter has the data and is analyzing it.

The beam from the PMC to the ISS box had to be re-aligned, as we had not re-aligned this path since moving the ISS box to accommodate the damping bars for the new PMC.  This complete, we then roughly aligned ISS PDB.  The PD assembly was then removed from the ISS box so we could re-install ISS PDA (recall that PDA had been removed from the ISS box and installed in place of IO_AB_PD3 prior to O2).  With PDA back on the PD assembly, this was installed back in the ISS box, and both PDs aligned.  They both now read ~10.0 V.  Next step on the ISS (for tomorrow) is to get the loop to close and measure TFs to optimize its operation.

Comments related to this report
peter.king@LIGO.ORG - 05:38, Wednesday 23 May 2018 (42137)
Attached is the calculated fit to the percent diffracted power versus offset slider setting.
Ihe fit is close to a parabola p(x) = 113.18 x^2 - 82.3309 x + 15.0625.

    The power measured in front of the AOM was 67.8 W, and after the neoVAN amplifier was
69.8 W.  The power in front of the AOM was used in calculating the percentage diffraction.
Images attached to this comment
peter.king@LIGO.ORG - 06:22, Wednesday 23 May 2018 (42138)
I went ahead and changed the coefficients in the ISS MEDM screen that calculates the percentage diffraction.
Set the reference level to be -1.89 and closed the loop without any problems.

    The offset slider is currently set to 8.00.  Please do not mess with this value.  Only the reference level
(labelled REFSIGNAL) and the gain slider should be adjusted.  At the time of making this log entry the gain
setting has not been determined as that will require a few transfer function and noise measurements.
jason.oberling@LIGO.ORG - 14:44, Wednesday 23 May 2018 (42158)

The promised pictures.  The 1st is the ISS AOM installed in its new location.  The 2nd is the mirror that directs the 1st order diffracted beam from the AOM into a beam dump (bottom-left of picture); the power meter shown was used for alignment of the AOM.

Images attached to this comment
H1 General
jim.warner@LIGO.ORG - posted 16:00, Tuesday 22 May 2018 - last comment - 17:12, Tuesday 22 May 2018(42118)
Shift Summary

15:00 JeffB to LVEA

15:45 Fil to MSR 

16:15 Betsy, Travis to EX

16:15 Gerardo to EY

17:00 Jason to PSL

18:00 Marc to HAM6

20:15 Jason Peter to PSL

20:45 JeffB to ITMX camera

21:15 Betsy, Travis to EX

21:30 Aidan, Marie, Dan, Alexei to EY

 

 

Comments related to this report
aidan.brooks@LIGO.ORG - 17:12, Tuesday 22 May 2018 (42133)

Aidan, Dan, Marie and Alexei are back from ETMY.

We have disabled the ETMY ALS laser for the moment but VEAY remains laser hazard.

H1 SUS (SUS)
cheryl.vorvick@LIGO.ORG - posted 15:51, Tuesday 22 May 2018 - last comment - 16:13, Friday 01 June 2018(42129)
ITMX and ITMY TFs taken today, under vacuum

files saved in:

Comments related to this report
jeffrey.kissel@LIGO.ORG - 16:13, Friday 01 June 2018 (42293)
J. Kissel

I've processed Cheryl's data for the Main Chains of the ITMs, 
/ligo/svncommon/SusSVN/sus/trunk/QUAD/H1/ITMX/SAGM0/Data/
    2018-05-22_2102_H1SUSITMX_M0_WhiteNoise_L_0p01to50Hz.xml
    2018-05-22_2102_H1SUSITMX_M0_WhiteNoise_P_0p01to50Hz.xml
    2018-05-22_2102_H1SUSITMX_M0_WhiteNoise_R_0p01to50Hz.xml
    2018-05-22_2102_H1SUSITMX_M0_WhiteNoise_T_0p01to50Hz.xml
    2018-05-22_2102_H1SUSITMX_M0_WhiteNoise_V_0p01to50Hz.xml
    2018-05-22_2102_H1SUSITMX_M0_WhiteNoise_Y_0p01to50Hz.xml

/ligo/svncommon/SusSVN/sus/trunk/QUAD/H1/ITMY/SAGM0/Data/
    2018-05-22_2119_H1SUSITMY_M0_Mono_WhiteNoise_L_0p01to50Hz.xml
    2018-05-22_2119_H1SUSITMY_M0_Mono_WhiteNoise_P_0p01to50Hz.xml
    2018-05-22_2119_H1SUSITMY_M0_Mono_WhiteNoise_R_0p01to50Hz.xml
    2018-05-22_2119_H1SUSITMY_M0_Mono_WhiteNoise_T_0p01to50Hz.xml
    2018-05-22_2119_H1SUSITMY_M0_Mono_WhiteNoise_V_0p01to50Hz.xml
    2018-05-22_2119_H1SUSITMY_M0_Mono_WhiteNoise_Y_0p01to50Hz.xml

and attach the results. I also whole-heartedly agree with her assessment -- everything looks great.
Non-image files attached to this comment
H1 AOS
jeffrey.bartlett@LIGO.ORG - posted 15:42, Tuesday 22 May 2018 (42128)
Add 100ml to Crystal Chiller
   I added 100ml water to crystal chiller and no water to the diode chiller. Both filters are clean and clear. 
LHO VE
kyle.ryan@LIGO.ORG - posted 14:52, Tuesday 22 May 2018 (42125)
HAM6 on turbo pump now

Rough pump down was faster than normal.  Implies that the majority of the gas load comes from the O-ring sealed QF flex lines that connect the scroll pump assembly to the HAM6 connection as these were pumped overnight.  Typically, these get pumped simultaneous with HAM6.  In other words, it seems that the time needed to rough pump HAM6 down to the point of switching over to the turbo pump is significantly determined by how wet the connecting flex lines are.  We have always suspected this but never realized to what degree. 

LHO VE
kyle.ryan@LIGO.ORG - posted 14:35, Tuesday 22 May 2018 - last comment - 15:20, Tuesday 22 May 2018(42124)
~1420 hrs. local -> Shut down Corner Station cleanrooms

Large units over HAM3, HAM4, HAM5, HAM6 and the Beer Garden, as well as, the small change rooms etc. on north side of OMC tube.

Comments related to this report
kyle.ryan@LIGO.ORG - 15:20, Tuesday 22 May 2018 (42126)

Re-energized HAM3 and HAM4 clean rooms as there still is a possibility of installing new large ion pumps

H1 SUS
stuart.aston@LIGO.ORG - posted 12:59, Friday 01 August 2014 - last comment - 16:23, Tuesday 22 May 2018(13065)
ETMX (QUAD) L2 (PUM) UL channel excess sensor noise appears due to in-vacuum cabling
[Gary T, Danny S, Matt H, Stuart A, Norna R]

During the close-out work of the BSC9 chamber (see LHO aLOG entry 13085) we were able to further investigate the source of the excess noise that had previously been observed on the ETMX (QUAD) L2 (PUM) UL channel (see LHO aLOG entry 13047).

Previously, I had swapped field cables at the Satellite Box between ETMX L1 and L2 stages running to the chamber. This indicated that the noise was downstream, i.e. with the field cables themselves or in-chamber. We repeated this test, but this time swapping field cables at the air side of the vacuum flange. Further measurements then eliminated the field cables and confirmed the issue resided in-chamber.

Gary inspected and re-seated the in-chamber connectors from the vacuum flange to the OSEM, but this offered no improvement. Finally, the L2 UL AOSEM (s/n #270) was removed and a spare unit connected up in it's place, but again, unfortunately this offered no improvement.

This indicates that the excess noise is most likely a in-vacuum harness problem, which would be invasive to attempt to replace. Therefore, it was decided to generate an integration issue and proceed with the close-out of the chamber, with the excess sensor noise on this channel.
Images attached to this report
Comments related to this report
stuart.aston@LIGO.ORG - 13:00, Friday 01 August 2014 (13147)
Integration issue generated, see Bug #929.
travis.sadecki@LIGO.ORG - 16:23, Tuesday 22 May 2018 (42127)

Betsy and I swapped the quadrapuss cable to the L2 (PUM) AOSEMS.  This seems to have fixed the noise issue that had been plaguing the UL OSEM for several years.  See attached spectra for comparison.

After swapping the cable, we noticed that the 2 lower AOSEMs at the L2 stage (LL and LR) had low OLV values, so we decided to swap these as well.   We also took OLV values for UL and UR that were not replaced, but are dying of natural causes.

  Old S/N New S/N Old OLV New OLV Old Gain New Gain
LL 270 332 18726 18050 1.602 1.662
LR 483 473 25518 18150 1.176 1.653
UL N/A N/A 17934 21300 1.673 1.408
UR N/A N/A 25124 20600

1.194

1.456
Images attached to this comment
Displaying reports 46801-46820 of 87739.Go to page Start 2337 2338 2339 2340 2341 2342 2343 2344 2345 End