Displaying reports 46881-46900 of 87739.Go to page Start 2341 2342 2343 2344 2345 2346 2347 2348 2349 End
Reports until 08:18, Friday 18 May 2018
LHO General
corey.gray@LIGO.ORG - posted 08:18, Friday 18 May 2018 - last comment - 11:07, Friday 18 May 2018(42060)
Morning Status

TITLE: 05/18 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind: 14mph Gusts, 10mph 5min avg
    Primary useism: 0.07 μm/s
    Secondary useism: 0.07 μm/s
QUICK SUMMARY:

Quiet morning thus far with technical cleaning team only activity in LVEA.  Ran through the morning items from Ops Checksheet (only items of note were:  OPO was tripped, so untripped watchdog.  Dust Monitor Check looks "OK".  Dust monitor alarm at HAM5 (prob due to cleaning), HEPI EX diff pressure is INVALID.  Vacuum has lots of (usual?) alarms.)

Comments related to this report
corey.gray@LIGO.ORG - 09:29, Friday 18 May 2018 (42064)

Morning Meeting Minutes

  • ETMx work continues with ESD cable, R0 alignment, and TFs Monday.
  • HAM6
    • Ground loop issue (ZM1 is the hold up).
    • Fil investigating on the floor, then TJ will run transfer functions
    • If TFs bad, this will mean time to fix
    • If TFs good, or if problem fixed fast, then we will:
      • Transition LVEA to Laser SAFE
      • HAM6 north door install (Tyler here until 2pm)
    • Once door on, can:
      • Roll ISCT6 into place
      • Install light piping on bottom/left viewport (if not pumping, and with a Work Permit!).
      • Install Camera housing (if not pumping, and with a Work Permit!)
    • Plan is to start pumping down on Monday.
  • PSL
    • Possible work today (Robert will coordinate)
    • PSL System work is good for Mon & Tues (assuming we are down for pumping HAM6).
  • EY
    • Discussion of when we'll open
    • Oplev EY work can happen Monday morning
  • Network is stable, but there is still work going on.
  • Teamspeak is down (there is workaround via "teamspeak3", supposedly)
ryan.blair@LIGO.ORG - 09:41, Friday 18 May 2018 (42065)

Instructions for accessing the backup TeamSpeak server are here: https://wiki.ligo.org/LSC/RemoteParticipation/TeamSpeak

ryan.blair@LIGO.ORG - 11:07, Friday 18 May 2018 (42068)

Regular TeamSpeak server usage should be possible again.

LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 19:29, Thursday 17 May 2018 - last comment - 08:39, Friday 18 May 2018(42057)
Turbo pump pumping CP4 tripped off

(Chandra R, Gerardo M)

The turbo pump pumping CP4 tripped off this afternoon, the turbo controller was off and the scroll pump backing the turbo was on, but isolated. 

The following was done to restart the system: The turbo was isolated via its manual valve as a precaution, then the turbo was restarted, it reached full RPMs, after reaching normal running condition the backing pump was valved in.

After 1 hour the system seems to be OK.  Pressure is now at 1.40x10-08 torr.

Something to note, we need a lower alarm setpoint for H0:VAC-MY_Y4_PT245B_PRESS_TORR, by the time I received the first text alarm (00:24 utc while I was at the site) we were at 5x10-05 torr.

It is not understood why the turbo tripped, but we'll look into it.

Comments related to this report
gerardo.moreno@LIGO.ORG - 19:40, Thursday 17 May 2018 (42058)

Screenshot of alarms.

Images attached to this comment
thomas.shaffer@LIGO.ORG - 08:39, Friday 18 May 2018 (42062)

Something to note, your screenshot is of the VerbalAlarms log, which does not necessarily share the same alarm values as the text alarms. This is something that I am working with CDS on and we will see a change sometime in the future.

LHO VE
chandra.romel@LIGO.ORG - posted 18:47, Thursday 17 May 2018 - last comment - 11:56, Friday 18 May 2018(42056)
CP4 turbo tripped

Around 4:30 pm local time the turbo pump on CP4 tripped for unknown reason. Coincidentally EY chiller pump tripped around the same time. Unfortunately a portion of the foreline (upstream of safety valve) back streamed through the turbo. Thankfully Gerardo was still on site and rushed to MY to turn it back on. But unfortunately the RGA was valved in. We will take a scan tomorrow to assess and then install the small IP at bottom of CP and reconnect the cold cathode gauge so we can leave the turbo valved out. Pressure currently at 2e-8 Torr.

Comments related to this report
chandra.romel@LIGO.ORG - 11:56, Friday 18 May 2018 (42070)

Pressure rose to 7e-5 Torr over the course of an hour. Alarm threshold was set to 5e-5 Torr. Dave just lowered it to 5e-9 Torr. Current pressure is 4.1e-9 Torr, double what it was before the incident.

Because RGA was valved in, the filament tripped. I turned it back on at 10:17 am local. After 45 min. I took an initial scan and see a new water peak. Will scan again after further warm up and post results. This is what happens when you claim victory prematurely.

The IP is being pumped by aux cart. Will valve in this afternoon.

Images attached to this comment
LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 17:28, Thursday 17 May 2018 (42055)
Corner Station Purge Air

Measured dew point for the corner station purge air this afternoon 00:15 utc, value at -37.6 oC.

H1 SUS
filiberto.clara@LIGO.ORG - posted 17:05, Thursday 17 May 2018 (42054)
HAM6 SUS Ground Checks

Ground loops for HAM6 suspensions completed. Looked at OMC, ZM1, and VOPO. Found short on ZM1 pin 2 shorted to chamber ground.

H1 AOS
betsy.weaver@LIGO.ORG - posted 16:26, Thursday 17 May 2018 (42053)
AMD #3 and #4 installed on ETMX Test Mass - Final set for H1!

Slawek, Sebastien, Travis

After the usual fussing (care) by a perfectionist team, the last AMDs were successfully glued to the flats of the ETMX test mass!  Well done guys!  

The tooling will be removed tomorrow mid-afternoon.

All 4 H1 test masses now have AMDs installed (4 each).

I'll state again that I'm impressed by how easy the tooling is for this in-situ install and how issue-free the process was.

 

LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 16:23, Thursday 17 May 2018 (42052)
Relief Valve at X-End Purge Air Skid

Replaced worn out relief valve on air compressor #4 for the purge air skid at X-End station.

LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 16:17, Thursday 17 May 2018 (42051)
X-End Purge Air Skid

Replaced burned out indicator lights on the purge air skid at the X-End station.

H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:00, Thursday 17 May 2018 (42050)
Ops Day Shift Summary
Ops Shift Log: 05/17/2018, Day Shift 15:00 – 23:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked for upgrades
Intent Bit: Engineering
Support: X
Incoming Operator: X
Shift Summary:  HAM6 table work, End-X close out, commissioning
 
Activity Log: Time - UTC (PT)
16:30 (09:30) Take over from Cheryl
16:39 (09:39) Peter – Transition the LVEA to laser hazard
16:56 (09:56) APS on site – Access control system install
17:02 (10:02) Hanford – Testing alarms in 300 area
17:07 (10:07) Daniel S. – Going to Squeezer bay – will turn on laser
17:25 (10:25) School tour of control room
17:25 (10:25) Jenni & Alexie – Going into IOTC6
17:42 (10:42) School tour of control room
17:57 (10:57) Filiberto – Going into the LVEA to move power supply into the CER (WP#7567)
18:11 (11:11) Jenni & Alexie – Out of the LVEA
18:24 (11:24) APS – On site for access controls work
18:25 (11:25) Karen – Cleaning in the H2 room
18:27 (11:27) Marc – Going to the vault
18:43 (11:43) Robert – Going into the PSL Enclosure to mount accelerometers
18:48 (11:48) Richard & Niko – Going into the LVEA
18:53 (11:53) Karen – Out of the H2 building
18:55 (11:55) Richard & Niko – Out of the LVEA
18:55 (11:55) Filiberto – Out of the LVEA
19:04 (12:04) Marc – Back from vault
19:20 (12:20) Daniel S. – Out of the LVEA
19:36 (12:36) Filiberto – Going to the vault
19:41 (12:41) Marc – Going to the vault
19:56 (12:56) Jim – Going to HAM6
20:22 (13:22) Daniel B., - Going to HAM6
20:30 (13:30) Corey – Going to HAM6/Squeezer  
20:40 (13:40) School tour of control room
20:45 (13:45) Robert – Out of the PSL enclosure
20:55 (13:55) School tour of control room
21:05 (14:05) Alexei – Going to HAM6 with beam profiler laptop
21:20 (14:20) Filiberto & Marc – Back from the vault
21:27 (14:27) APS – On site for access control work
21:32 (14:32) Travis & Sebastian – Going to End-X to install AMD
22:14 (15:14) Gerardo – Going to End-X
22:19 (15:19) Corey – Installing light pipes for Squeezer table (WP #7571)
22:25 (15:25) APS – On site for access control system
22:34 (15:34) Gerardo – Back from End-X
21:48 (15:48) Filiberto – Going to HAM6 for ground loop checks
22:48 (15:48) Marc & Peter – Going to the vault
23:00 (16:00) End of shift
H1 SQZ (ISC, SQZ)
corey.gray@LIGO.ORG - posted 15:49, Thursday 17 May 2018 (42049)
New Light Piping Installed For SQZT6

(Corey, Daniel) 3:00 - 3:40pm

Installed (qty2) light piping  for the two beam paths coming out of HAM6.  The Viewport Cover/Guillotine was in place for both and the plastic Guillotine is also in place & will need to be removed when people want to work on beams for this table.  This completes WP#7571.

Images attached to this report
LHO VE
chandra.romel@LIGO.ORG - posted 15:47, Thursday 17 May 2018 (42048)
CP4 bake results

We are declaring victory on CP4 bake at MY! Rai Weiss and Dennis Coyne gave it their blessing. :)

Attached is a spreadsheet with RGA scans showing partial pressures of residual gases. Total pressure = 2.4e-9 Torr for the post bake scan. LLO’s CP4 scan at their EX serves as a reference/baseline (coincidentally we’re both changing states of our #4 CPs). I also included a scan of our CP4 before the bake, but after the LN2 was boiled away and ice pumped away (total pressure 2e-7 Torr) in Faraday mode. Not very useful, but it’s data. We baked our newly installed RGA in situ with the CP bake so we never captured a baseline.

Comparing LLO’s reference to our post-bake, the peaks relative to each other look good, expect maybe for AMUs 50-60. Note that LLO’s scan is from an SRS unit and ours is from a Pfeiffer unit. I don’t have Torr/A conversions for these units specifically. Based on VBO scans, we know that the Pfeiffer ion current correlates closer to pressure than the SRS:

Pfeiffer = 1.3 Torr/A of Ar

SRS = 367 Torr/A of Ar

I used these values to convert to Torr and included that plot as well.

We have a new peak at AMU 7. Probably from baking the old 10” CETEC valve with o-ring gate seal.

After the annulus piping is installed and GV electrical connected, we will open GV 11 first to expose the bake volume to CP3 and IP9 and collect an RGA scan and finally open GV12.

 

Non-image files attached to this report
H1 SEI
jim.warner@LIGO.ORG - posted 15:36, Thursday 17 May 2018 - last comment - 09:12, Friday 18 May 2018(42046)
HAM6 ISI is good to go

CPS Z/RX/RY location residuals are all <15 micron/microradians indicating the table hasn't move much since they were last zero'd (around the time of the last closeout). Today's transfer functions (first image) look much like the Apr 26th measurements (second). I also replaced the 4" cc sample on the table earlier today. Think the chamber is good to close up.

Images attached to this report
Comments related to this report
jim.warner@LIGO.ORG - 09:12, Friday 18 May 2018 (42063)

I should mention, I left the ISI unlocked.

H1 SQZ
daniel.sigg@LIGO.ORG - posted 12:56, Thursday 17 May 2018 (42044)
SQZT6 Alignment

The periscopes and beams were realigned, now that SQZT6 is in its final position.All three beams travel down the periscopes and make it to the photodiodes for locking green. The CLF DC has been temporarily hooked up to a Thorlabs PD that is in the homodyne path. For reasons unknown the green transmitted beam seems even weaker than before.

Still to do:

H1 AWC
daniel.brown@LIGO.ORG - posted 20:14, Wednesday 16 May 2018 - last comment - 15:36, Thursday 17 May 2018(42028)
HAM6 IFO beam profiling

Tvo, Alexei, Dan

We took some more beam profiles of the single bounce (off of ITMX) IFO beam in HAM6 as the north door is off. We took measurements from the edge of the HAM6 table near the viewport and up to OM1. At first glance it seems the astigmatism of the IFO beam is not as bad as our previous measurements. However we still need to analyze the results. We don't have the OPO beam available at the moment so we couldn't profile that, perhaps we can before the doors go back on.

As we were there we also tried to profile the beam shape change induced by the SR3 heater. We got the heater up to ~70C and took profiles with the nanoscan in a single position near the HAM5 viewport. Along with the OMC mode scan results we took the other day we are hoping this will allow us to narrow down where in the beam parameter space we are. Results to come.

Comments related to this report
alexei.ciobanu@LIGO.ORG - 15:25, Thursday 17 May 2018 (42043)

Attached is the analysis of the beam profiles taken 50.5'' from OM1 as the SR3 heater temperature increased from 30 to 75 C at 5 W requested power on the SR3 heater.

The starting beam size was (2401.2, 2375.6) um and the final size was (2310.5, 2258.7) um.

The ellipticity (1-b/a) of the beam varied from 0.01 to 0.02.

Images attached to this comment
alexei.ciobanu@LIGO.ORG - 15:36, Thursday 17 May 2018 (42047)

Attached is the analysis of the last set of data taken during this measurement.

Here the nanoscan was positioned 21' away from OM2, and the SR3 heater was left for about 15 minutes at 75 C to come to equilibrium.
The power to the SR3 heater was then cut and the beam size was tracked as the temperature decayed.

The aim of this exercise was to observe the optical transient of the SR3 by trying to find the point where the beam size would start changing after the power to the SR3 heater was cut.
20 minutes after the power was cut the beam size had not changed significantly and we stopped taking measurements.

Images attached to this comment
Displaying reports 46881-46900 of 87739.Go to page Start 2341 2342 2343 2344 2345 2346 2347 2348 2349 End