Finished venting IP4 with bottled UHP N2 (started Friday afternoon then halted). Also vented (with bottled UHP N2) non-VE side of closed 12.8" gate valve (new VAT valve) mounted on OMC tube and having 16.5"-2.75" CFF zero-length reducer flange with 1 1/2" pump port valve. New valve doesn't leak! Chandra will be in early tomorrow to remove connected equipment and supervise installation of IP4 onto the OMC.
TITLE: 01/29 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
16:00 (8:00) Start of shift
16:15 (8:15) Hugh to End-Y -- HEPI filter change
16:22 (8:22) Ken to End-X -- Piping work
16:48 (8:48) Hugh out of End-Y
17:47 (9:47) Bartlett to termination slabs -- ITM camera work
17:57 (9:57) Phil to End-X -- Looking at cabling for HEPI
18:36 (10:36) Cheryl to IOT2L -- Align cameras
18:45 (10:45) Ed to HAM6 -- Inspect wire
18:58 (10:58) Jenne, Keita and TVo to HAM6
18:59 (10:59) Phil out of End-X
19:00 (11:00) TJ and Jim to End-Y -- PCal baffle work
19:03 (11:03) Hugh to LVEA -- Retrieve hardware
19:12 (11:12) Phil to End-X
19:15 (11:15) Hugh out of LVEA
19:45 (11:45) Cheryl out from IOT2L
20:01 (12:01) Bartlett out for lunch
20:08 (12:08) TJ and Jim out of End-Y
20:10 (12:10) Phil and Hugh out of End-X
20:20 (12:20) Jenne, TVo, Keita out of LVEA
20:59 (12:59) Bartlett to termination slabs -- ITM camera work
21:05 (13:05) TJ and Jim to End-Y -- PCal baffle work
21:10 (13:11) Kyle to HAM4 -- climb up OMC tube
21:13 (13:13) Travis and Betsy to End-Y -- Putting ETMY back together
21:29 (13:29) Ed to CER -- Terminate cables
21:35 (13:35) Kyle out from HAM4
21:53 (13:53) Peter and Gerardo to Optics Lab
22:06 (14:06) Bubba and Mark to LVEA -- Work on snorkel lift
22:27 (14:27) Elizabeth to HAM6 -- Scan components
22:36 (14:36) Patrick to End-X -- Reset power to HEPI pump control
22:40 (14:40) Nutsinee to ISC Rack
22:40 (14:40) Bubba and Mark out of LVEA
22:50 (14:50) Nutsinee out from ISC Rack
22:53 (14:53) Patrick out of End-X
23:13 (15:13) Bartlett out from termination slabs
23:26 (15:26) Jenne, Keita, and TVo to HAM6
23:30 (15:30) Peter and Gerardo out of Optics Lab
23:47 (15:47) Elizabeth out from HAM6
23:49 (15:49) Terry to SQZ bay
23:54 (15:54) Ed out of CER
0:00 (16:00) End of shift
We need to restore ALSX for peeking down the X arm.
We have OK fiber power (though RefCav trans is smaller than it used to in O2), and polarization at EX is not bad either, but there's no beat note.
Left: O2, Right: Now.
Could be that the frequency is too far off or the alignment is somehow bad.
The beam on top periscope mirror is roughly centered (this is a change from a few weeks ago), so the beam coming off of the bottom periscope mirror was too high. Adjustments made to clear iris/HWP/CW and beam dumps, and REFL, WFS1, WFS2, and camera recentered.
I'm emerging from sick leave, so this would be a good time to give a CDS computing summary:
Timing is in error. At around 3am PST Thursday 25th the MCA atomic clock time distribution system went into alarm. Trends suggest its time was varying for about an hour, and then settled to a static large offset. All three comparators in CS, EX and EY see bad times and are reporting the error.
h1oaf model is now consistently running long and reporting timing errors. This started Tue 16th Jan, presumably due to filter changes. I am investigating.
New filters need to be loaded for h1sqz, h1ascimc. If we don't get to this today, we'll cover it tomorrow during maintenance.
Surprisingly h1oaf's cpu issues are not filter related. It appears that the decommissioning of the h1ngn model on 1/16 has caused it to run long, even though there is no IPC between these models. I'll try a complete model restart on h1oaf0 tomorrow.
Commissioning:
CDS:
End-Y:
Mid-Y:
End-X:
Besides the ongoing tripping, everything else looks normal.
Laser Status: SysStat is good Front End Power is 35.24W (should be around 30 W) HPO Output Power is 140.2W Front End Watch is GREEN HPO Watch is GREEN PMC: It has been locked 0 days, 3 hr 16 minutes (should be days/weeks) Reflected power = 23.22Watts Transmitted power = 41.32Watts PowerSum = 64.54Watts. FSS: It has been locked for 0 days 3 hr and 16 min (should be days/weeks) TPD[V] = 1.968V (min 0.9V) ISS: The diffracted power is around 3.9% (should be 3-5%) Last saturation event was 0 days 3 hours and 12 minutes ago (should be days/weeks) Possible Issues: PMC reflected power is high
Came in this morning to find the oscillator off. The front end was still running. Looks like the watchdog kicked in
some ime around 5:30 pm Saturday.
The power decay from head 1 is the reason for the decay in laser output power. I upped the current of the 3 other
diode boxes by 0.5 A.
Laser restarted without any major hiccups. Other stuff came on-line pretty quickly. Witnessed a couple of
occasions where the injection locking was lost.
In an attempt to stabilize HPO DB1, I adjusted the operating temperatures of the 7 individual pump diodes in DB1. The changes are summarized below:
| Operating Temperature (°C) | ||
| Old | New | |
| D1 | 24.0 | 24.5 |
| D2 | 24.0 | 24.5 |
| D3 | 22.5 | 21.5 |
| D4 | 24.0 | 23.5 |
| D5 | 24.0 | 23.0 |
| D6 | 24.0 | 24.5 |
| D7 | 24.0 | 24.5 |
This took the output power of the HPO from 138.9 W to 140.4 W, an increase of 1.5 W simply from temperature tweaks. We will continue to monitor.
VPW, LVEA, Mechanical Room. I expect to be here less than one hour and will make comment to this entry when leaving.
1705 heading to Y-end to check on purge air
1725 hrs. local - Leaving site now
After a negative rail was added to the PZT driver and a new Beckhoff scanning tool became available (thanks Daniel!), I was able to simplify the SHG auto locker and modified it such that the positive and negative rails are taken into account. SHG guardian no longer toggles the offset slide bar to look for resonance but instead sends in a scan to look for resonance. Once the resonance is found, the PZT is offset by that X amount of voltage and the loop is engaged. The code currently looks at Trans PD output power. At some point I'd like to make it look at the reflected green power and make it dependent of the input power (which can be done with the LASER IR PD). If SHG is locked with too much or negative voltage being sent to the PZT, it will drop lock to find another sweet spot. The low limit is currently set to 0V, and high limit is set to 85V.
More warning messages and fault conditions will be added in the future. For now it is relatively robust (I think).
Terry, Nutsinee, Sheila
After looking at the fiber collimators we decided to try swapping them so that the one that has a greenish tint in the lens is used for 1064 and the one that looks very clear is used for 532, based on advice from Lisa, Lee and Maggie. After doing this we were able to align the cavity and saw that our mode matching isn't too bad although we haven't tried to optimize it by moving any lenses yet.
Terry, Nutsinee
Here I attached the waist measurement and fit of 532nm coming out of the correct green coupler. The Thorlabs beam profiler we use is not great with beam diameter < 1000um for 532 so we took that into account this time. The waist size we got was 183um (radius) located 270mm away from the coupler.
I also attached a photo of the couplers we have. Couldn't capture the reddish color very well but the left coupler was for 532 and the right coupler was for 1064.
Kyle, Chandra
IP4 is back from rebuild and shipped under vacuum (measured mid e-5 Torr range). We pumped down with an aux cart, isolated the turbo, and then turned on high volts and measured 1.8-2 micro-amps at 7 kV on each channel. The pump is now vented with dry N2. Monday we will vent the blank on IP4's new gate valve, verify there is no leak into main volume, and then install IP4.
Kyle, Chandra
We tested the leaks in GV12's gate o-rings by flooding the gate annulus with dry N2 (with active turbo connected and ready to be valved in to evacuate) and discovered the adjacent volumes' pressures rise too high too quickly. The Y2 beam tube rose to 7e-8 Torr and CP4 side rose to 1.4e-6 Torr in less than one minute. We may try to jog the gate on Monday to see if we can get a better seal, at least on inner o-ring. Will also re-evaluate the bake enclosure dimensions so see if gate annulus tubing can stay (GV11's definitely gets in the way and had to go).
We realized that we did not get any email or text alarms when we should have - pressure was well past the 5 minute and 15 minute set point thresholds on PT-245B and PT-256B. Will contact Dave B. about this.
Dave Barker rebooted alarm system this morning after a crash yesterday morning.
J. Kissel, for A. Bell, T. Sadecki, and D. Sellers While on my way to and from B&K hammering the EY PCAL periscope, I snapped a few publicity photos of Angus, Travis, and Danny who were fine-tuning the alignment and measuring violin modes of the brand new fibers of newly suspended H1 SUS ETMY. Thanks and keep up the good work, gents!
The violin modes were remeasured (with 0.25 Hz accuracy) position (Hz) fibre S/N +X/+Y 504.5 S1400157 -X/+Y 503.0 S1400159 +X/-Y 513.25 S1800486 -X/-Y 510.5 S1800491 as these will shift after in-chamber alignment, we didn't go for higher accuracy. The laser we used was quite noisy and should be replaced before using the kit again.