Displaying reports 48121-48140 of 83242.Go to page Start 2403 2404 2405 2406 2407 2408 2409 2410 2411 End
Reports until 15:59, Thursday 11 May 2017
H1 TCS (TCS)
aidan.brooks@LIGO.ORG - posted 15:59, Thursday 11 May 2017 (36140)
Recovery of Hartmann table (ISCHT4) - day one (Wednesday)

Yesterday we moved the ISCHT4 (Hartmann sensor) table back in position next to HAM4. Because of the on-going pumping on the vacuum system, the viewport covers remained in place and the light pipes remained disconnected. We spent several hours getting all the cables carefully hooked up again to the table.

We also noticed that the persicopes are severely out of position relative to the holes in enclosure (both shifted about 2" to the right). It's not immediately clear why this is the case but since the enclosure and periscopes are all bolted to the table, it is not a result of the table move. It may be that the table has been out of position for a long time and the periscopes were moved to capture the green beams that exit the vacuum system. Once we get access to the viewports, this should become clearer.

We also installed the nominal HWSY AIRLENS, PLCX-50.8-515.1-UV (per Table 2, T1000179-v20), replacing the lens installed to compensate for the incorrect vacuum lens.

Images attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 15:14, Thursday 11 May 2017 (36139)
LHO HEPI Accumulators' Gas Charge Checked and Corrected AR

There were a few needing N2 but they were only ones that had slowly been approaching action level over time, some that were just marginally okay, and a few that lost charge as we struggled to get the gauge to seal.  These had not been checked since Oct '16 and none were at action level.  Closing FAMIS 4596.

H1 PSL (PSL)
peter.king@LIGO.ORG - posted 13:01, Thursday 11 May 2017 (36136)
NPRO output power
Measured the NPRO output power using a Gentec Pronto-250 (S/N 233415) power meter.
After the conglomerate of optics after the NPRO but before the phase correcting EOM
the power was measured to be 1.36W.  Going into the power amplifier, 0.90W.  The
output of the monitoring photodiode at this time was 0.708V.  This is the number
reported by the laser MEDM screen.




Jason / Peter
LHO General
patrick.thomas@LIGO.ORG - posted 13:00, Thursday 11 May 2017 (36135)
Ops Mid Shift Summary
- Gerardo started vacuum pumps
- Fire department testing onsite
- Filiberto, Marc, Richard investigating timing error at end Y
- LVEA transitioned to laser hazard, TJ and Aidan working on TCS table
- Jeff B., Peter and Jason cleaned up cabling and piping in PSL enclosure
LHO VE
chandra.romel@LIGO.ORG - posted 20:22, Wednesday 10 May 2017 (36131)
Vertex pressure

8pm local time

Vertex pressure is 92 Torr at turbo station and 220 Torr at pirani gauge (not accurate). Valved out QDP80 roughing pump for the night as a chamber safety precaution. Will resume roughing down tomorrow morning.

Powered down Kobelco purge air skid.

Leaving site now.

LHO VE
chandra.romel@LIGO.ORG - posted 20:03, Wednesday 10 May 2017 - last comment - 06:57, Saturday 13 May 2017(36130)
Vacuum update on daily activity following vent

Stuff that needs to be replaced or fixed:

Comments related to this report
chandra.romel@LIGO.ORG - 06:57, Saturday 13 May 2017 (36173)

Correction:  pirani gauge is PT120A (not PT120B)

LHO General
patrick.thomas@LIGO.ORG - posted 15:58, Wednesday 10 May 2017 (36128)
Ops Day Shift Summary
TITLE: 05/10 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

Pump down of chambers has begun.

LOG:

15:05 UTC Amber leading tour in control room
15:20 UTC Tour leaving control room
15:20 UTC Jeff B. to LVEA and cleaning area, survey for plumbing work
15:32 UTC Gerardo to CER mezzanine to check on HV, and to LVEA
15:46 UTC Jeff B. out
15:57 UTC WP from Chandra to begin pumping
16:00 UTC Travis to beer garden to clean up equipment
16:18 UTC Apollo at end Y, shutting down HVAC for FMCS upgrade
16:18 UTC Kyle to mid X and end X looking for cable
16:30 UTC Apollo through gate
16:37 UTC Kyle back
16:45 UTC Travis done (from email)
16:46 UTC Filiberto and Richard to LVEA tables to document serial numbers of photodiodes
16:47 UTC Karen to VPW and then staging building
17:39 UTC Filiberto and Richard done. Heading to end stations.
17:46 UTC Amber leading tour through control room
17:49 UTC Mike taking guest into LVEA
18:17 UTC Mike and guest out of LVEA
18:21 UTC Hugh had me set CS HEPI pumpcontroller setpoint to 0
18:17 UTC Roughing pumps have been started
18:28 UTC Richard and Filiberto back
19:22 UTC Gerardo, Kyle and Chandra out for lunch
19:37 UTC Hugh had me set CS HEPI pumpcontroller setpoint to 70
19:45 UTC Hugh done in CS
20:24 UTC Aidan and Nutsinee to LVEA to start rebuilding TCS table
20:37 UTC Jim and Hugh to end stations for HEPI accumlators and pump station maitenance
21:05 UTC Gerardo to LVEA to pick up equipment
21:06 UTC Marc to mid Y to pick up parts
21:08 UTC Filiberto to LVEA to help TCS crew reconnect cable
21:19 UTC Hugh at end Y
22:00 UTC Site Weekly meeting
22:54 UTC Hugh to LVEA
H1 PSL
edmond.merilh@LIGO.ORG - posted 14:48, Wednesday 10 May 2017 (36126)
Weekly PSL Chiller Reservoir Top-Off - FAMIS #6522

Topped off Xtal chiller with 100ml. Diode Chiller looked fine

LHO VE
chandra.romel@LIGO.ORG - posted 13:45, Wednesday 10 May 2017 (36125)
Vertex pump down

Started roughing down vertex at 11:17 am local time. Pump curve attached. Someone from vacuum will stay late to babysit the system and then we'll valve out and resume pumping tomorrow morning.

IP1 valve leaks, so we connected a turbo cart to the IP. Pressure looks to be something lower than e-3 torr, so we'll valve that volume back in after we're on the main turbo (with IP powered OFF). Other three IPs look ok (no valve leaks). 

BSC3 & HAM4 door annuli are still on turbo carts.

Images attached to this report
H1 TCS (SEI, SUS, TCS, VE)
corey.gray@LIGO.ORG - posted 13:30, Wednesday 10 May 2017 - last comment - 08:36, Thursday 11 May 2017(36123)
Replacement of ITMy In-Vacuum Hartmann Lens on WHAM4 Optics Table

(Aidan B, Corey G, TJ S, Jim W, PLUS much assistance to by Vacuum Team, Betsy W for prep work, & Jeff B. for staging of Contamination Control supplies)  

All times in PDT

On Tues (May9th) multiple in-vacuum tasks were on the docket for work on H1, and this log covers the work at/inside HAM4:  Replacement of the H1 HWSY VAC LENS.  While performing this work, we followed Vent Plan (E1700124) & followed STEPS #32 - 39.  Also used the Chamber Entry & Exit Procedure (E1201035, sheet4).  Attached are some photo highlights from this job (all photos are on resourcespace [links below]).  

HAM4 was roughly open from 10am - 2pm with only minimal entry within the chamber (access was from the North & only arms/upper body entered the chamber for this work task).

NOTE:  During this activity there was an Alert/Site Area Emergency event on the Hanford site (first time this has happened for LHO in ~20years of being here).

Summary of HAM4 Activities:

  0.3um (particle/L) 0.5um (particle/L)
Before Door Removed 68 12
After Door Removed 5 1
In-Chamber 11 4
Images attached to this report
Comments related to this report
aidan.brooks@LIGO.ORG - 08:23, Thursday 11 May 2017 (36132)

The new lens is from the bag (and box) labeled: CVI PLCX-50.8-360.6-UV-700-900, per Table 2 of T1000179-v20

Images attached to this comment
aidan.brooks@LIGO.ORG - 08:36, Thursday 11 May 2017 (36133)

The old lens had a label penciled onto the side. This read: PLCC-50.8-772.6-UV

This confirms our educated guess back in October 2014: (T1400686, page 2).

 

Images attached to this comment
LHO VE
logbook/robot/script0.cds.ligo-wa.caltech.edu@LIGO.ORG - posted 12:10, Wednesday 10 May 2017 - last comment - 15:50, Wednesday 10 May 2017(36122)
CP3, CP4 Autofill 2017_05_10
Starting CP3 fill. LLCV enabled. LLCV set to manual control. LLCV set to 50% open. Fill completed in 90 seconds. TC B did not register fill. LLCV set back to 20.0% open.
Starting CP4 fill. LLCV enabled. LLCV set to manual control. LLCV set to 70% open. Fill completed in 3197 seconds. TC A did not register fill. LLCV set back to 43.0% open.
Images attached to this report
Comments related to this report
chandra.romel@LIGO.ORG - 15:50, Wednesday 10 May 2017 (36127)

Raised CP4 to 45% open.

H1 General
jeffrey.bartlett@LIGO.ORG - posted 07:37, Wednesday 10 May 2017 - last comment - 14:23, Thursday 11 May 2017(36116)
Install PSL Filter Mounts (WP #6621)
   Installed the filter mounts under the PSL table. Given the tangle of cables and plumbing it will be necessary to rework this area to relieve the strain and entanglement of these cables and plumbing. A separate work permit will be filled for these activities. 

   The photos below are of before and after mounting the filters.  
Images attached to this report
Comments related to this report
jeffrey.bartlett@LIGO.ORG - 14:23, Thursday 11 May 2017 (36138)
Jason, Peter, Jeff B. 

  Completed the mounting of the PSL chiller filters located under the PSL table. We also did some cable and plumbing cleanup.  
Images attached to this comment
H1 AOS
robert.schofield@LIGO.ORG - posted 19:43, Tuesday 09 May 2017 - last comment - 10:23, Monday 15 May 2017(36113)
Swiss Cheese Baffle Damping Complete

Damping completed and flanges back on. No hitches. Three viton corks are in, preliminary laser vibrometry looks good. More later.

Gerardo, Vinny, Robert

Comments related to this report
keita.kawabe@LIGO.ORG - 13:33, Thursday 11 May 2017 (36137)

First picture: Robert looking through the viewport at 9 o'clock position while inserting his hand into lower viewport hole at 8:00 position.

Second picture: A view through the lower viewport hole at 8:00 position. Black viton cork is inserted between the rib of the baffle and the chamber wall.

Images attached to this comment
stephen.appert@LIGO.ORG - 08:36, Friday 12 May 2017 (36153)
Pointer to the follow-up log entry: https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=36147
robert.schofield@LIGO.ORG - 10:23, Monday 15 May 2017 (36186)

Just to avoid any future confusion, the pictured location of the cork just above was not the final position. Based on feedback from the laser vibrometer, I moved it to 7:00, as pictured in the follow-up link given by Stephen.

H1 COC
calum.torrie@LIGO.ORG - posted 17:07, Tuesday 09 May 2017 - last comment - 09:03, Thursday 11 May 2017(36106)
ITMx (ITM03) Inspection and cleaning

GariLynn Billingsley, Travis Sadecki, Betsy Weaver, Calum Torrie, Nicki Washington (and a BIG support crew)

ITMx inspection with green light and portable microscope revealed several scattering sites. The center most sites were located high and right of center. (Camera images will be attached soon.) One of these (the brightest / closest to center) is shown in the attached picture. It measure roughly 0.5 mm across the halo.

There were many scatter sites of the same character all the way out to the edge of the optic. At the edge we attempted to clean one of these sites using the following solvents (IPA, Acetone, red FC and clear FC) without success.

Following this local cleaning and the overall inspection we then cleaned the entire HR face as per normal procedures i.e. with red first contact (FC) spray along with the cone etc ....

Subsequent inspection showed no change to these scatterering sites.

For full chamber report see alog by Betsy.

GariLynn and team.

Images attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 17:24, Tuesday 09 May 2017 (36108)

A few more pix of various "spots" we saw on the HR surface of ITMX today which did not come off with cleaning.

The first shows 2 very visible spots near the center of the optic which are the "halo" shaped nature that Calum/GariLynn show zoomed in above.

The second picture shows a small damage spot on the lower left of center on the HR surface that we believe has been on the optic since processing/coating/fabricating.  This is a surface penetrating feature visible with back-illumination, and is the only one observed of it's kind.

The third picture shows a much different "feature" far right of center, that is not anywhere else on the optic, but interesting. 

Images attached to this comment
betsy.weaver@LIGO.ORG - 09:50, Wednesday 10 May 2017 (36118)

Here's one more picture of us illuminating the section of the ITMX-HR slightly below and right of center where we DIDN'T find much during inspection.

Images attached to this comment
calum.torrie@LIGO.ORG - 10:04, Wednesday 10 May 2017 (36119)

We did see similarly described "donuts" on the BS-HR - see Kates alog and Betsy's attempt at pictures in ~2014:

https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=12876
 

Need to review to confirm related!

Calum

betsy.weaver@LIGO.ORG - 10:12, Wednesday 10 May 2017 (36120)

Now with the BS picture attempts during the time frame of Kate's alog:

https://ligoimages.mit.edu/?r=24661

https://ligoimages.mit.edu/?r=24659

 

brian.lantz@LIGO.ORG - 10:26, Wednesday 10 May 2017 (36121)

Here are the articles I mentioned in the SYS call this morning. These are not the same, as they describe a short, intense burst of light on a clean surface, rather than the suspected culprit of a CW beam on a bit of dust. Never-the-less, perhaps they will useful or interesting.

Morphology of femtosecond-laser-ablated borosilicate glass surfaces
Adela Ben-Yakar, Robert L. Byer, Anthony Harkin, Jacqueline Ashmore,  Howard A. Stone, Mengyan Shen, and Eric Mazur
Citation: Appl. Phys. Lett. 83, 3030 (2003);
doi: 10.1063/1.1619560
View online: http://dx.doi.org/10.1063/1.1619560
View Table of Contents: http://aip.scitation.org/toc/apl/83/15, Published by the American Institute of Physics


Femtosecond laser ablation properties of borosilicate glass
Adela Ben-Yakar, Robert L. Byer
Citation: Journal of Applied Physics 96, 5316 (2004);
doi: 10.1063/1.1787145
View online:  http://dx.doi.org/10.1063/1.1787145
View Table of Contents: http://aip.scitation.org/toc/jap/96/9, Published by the American Institute of Physics

I've included a picture of some of the craters from the second paper (fair use)

Non-image files attached to this comment
garilynn.billingsley@LIGO.ORG - 16:23, Wednesday 10 May 2017 (36129)
Facts:
Nothing was found where we were looking for the absorber, low and right from center on the HR surface. Aidan's plot showed ~25 mm down and ~25 mm Right.
No particulate was seen standing proud of the HR surface.
Nothing was found on the AR surface of the adjacent CP.

The features found on the ITM HR surface were of uniform size ~0.5 mm, with no more than 50% variation in size.
All of the characteristic spots were circular.
There were various dark (uncontaminated?) shapes in the center of the circles - keyhole, linear, dot or uniform (filled)
Features were found all over the optic including the very edge - Can’t say if there were any off the coating or not.
No immediately apparent distribution.

tried the following cleaning on a spot at the bottom edge of the optic to the left of the bevel damage. (in order)
Acetone - scrub with cotton swab
IPA - scrub with alpha swab
DI water - scrub with alpha swab
Windex - scrub with alpha swab
clear first contact paint
red first contact paint 

Within estimated beam waist we found
7 circular features counted
1 spot (very small) penetrating the coating (glowed when illuminated from behind) - believed to be present as polishing defect.

Silica wafer, mounted parallel to ITM03, but low of the arm cavity baffle: no similar scatterers - only small particulate.
1” optic mounted perpendicular to ITM03 on the side of the compensation plate suspension structure: no similar scatterers - only small particulate.

Speculation:  
Possible vaporization of particulate depositing on the surface. 
Possible contamination underneath the HR coating, present all along.
Further investigation at:  https://dcc.ligo.org/T1700193
betsy.weaver@LIGO.ORG - 09:03, Thursday 11 May 2017 (36134)

Particle counts during the in-chamber work were taken a few times:

 

2:30pm PT during first contact work with 1 person in the chamber, 2 people just prio

Count Size 10am PT entrance to chamber - Jim was starting ISI locking, 1 person in chamber 2:30pm PT during first contact work with 1 person in the chamber, 2 people just prior
0.3um 9 135
0.5um 2 82
1.0um 2 24

 

BSC3 DOOR WAS OFF FROM ~9am to 5pm PT.

 

H1 TCS (TCS)
corey.gray@LIGO.ORG - posted 14:46, Tuesday 09 May 2017 - last comment - 13:31, Wednesday 10 May 2017(36103)
HAM4 Task Complete

HAM4 chamber was open (door off) from roughly 10am - 2pm.  The actual job of swapping out a TCS lens, taking photos, and adding a Contamination Control wafer went smoothly and fast.  The only time-consuming issue was taking the transfer functions for SR2 & HAM4ISI (but Kiwamu, Betsy, & Jim eventually gave us a clean bill of health).  I will make a more thorough entry later.

Comments related to this report
corey.gray@LIGO.ORG - 13:31, Wednesday 10 May 2017 (36124)

Full summary posted here:  alog #36123.

Displaying reports 48121-48140 of 83242.Go to page Start 2403 2404 2405 2406 2407 2408 2409 2410 2411 End