Displaying reports 49881-49900 of 88171.Go to page Start 2491 2492 2493 2494 2495 2496 2497 2498 2499 End
Reports until 16:10, Monday 13 November 2017
LHO General
thomas.shaffer@LIGO.ORG - posted 16:10, Monday 13 November 2017 (39399)
Ops Day Shift Summary

TITLE: 11/13 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Purge air work took up the morning, and then a few crews went in. MC2 and PR2 WD have tripped, but I will wait for the SEI crew to finish the balancing before someone (not me) untrips it. Film crew is out in the LVEA with Keita.
LOG:

H1 PSL
thomas.shaffer@LIGO.ORG - posted 09:25, Monday 13 November 2017 - last comment - 09:27, Monday 13 November 2017(39403)
PSL Weekly Report

Laser Status:
SysStat is good
Front End Power is 35.82W (should be around 30 W)
HPO Output Power is 153.0W
Front End Watch is GREEN
HPO Watch is GREEN

PMC:
It has been locked 0 days, 0 hr 2 minutes (should be days/weeks)
Reflected power = 22.43Watts
Transmitted power = 45.97Watts
PowerSum = 68.4Watts.

FSS:
It has been locked for 0 days 0 hr and 2 min (should be days/weeks)
TPD[V] = 1.931V (min 0.9V)

ISS:
The diffracted power is around 4.2% (should be 3-5%)
Last saturation event was 0 days 0 hours and 1 minutes ago (should be days/weeks)

Possible Issues:
PMC reflected power is high

Comments related to this report
thomas.shaffer@LIGO.ORG - 09:27, Monday 13 November 2017 (39404)

FAMIS7464 closed.

LHO General
thomas.shaffer@LIGO.ORG - posted 09:21, Monday 13 November 2017 (39402)
Monday 9am Vent Meeting Minutes

Notice: Purge air work this morning, no in chamber work till this has completed. Should be complete this afternoon.

BSC arm removal to happen this morning during the purge air work, cover will stay on.

Squeezer Bay will still be intermittent laser hazard.

IO - IMC bypass planned to go in this afternoon/tomorrow morning. MC2 & PR3 are rubbing and they will revisit, alignment looks good.

OFI still a wip in lab.

ITMX --> PR3 Aux beam still set up.

Hugh ready to balance HAM3 when time permits. Half a day, few hours is lucky.

TCS tables are still being worked on by Greg.

GV6 is still closed, leak checking has finished.

 

Tues. Maintenance:

Make sure to continue to do FAMIS tasks, and remember to close the task from the dropdown menu.

 

H1 PSL
edmond.merilh@LIGO.ORG - posted 08:43, Monday 13 November 2017 (39401)
PSL Weekly Report - 10 Day Trends FAMIS #6174

Trends all look normal for the most part. Temperature trends show an ongoing effort to stabilize for alignment work.

Images attached to this report
LHO General
thomas.shaffer@LIGO.ORG - posted 08:01, Monday 13 November 2017 (39398)
Ops Day Shift Transition

TITLE: 11/13 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind: 10mph Gusts, 8mph 5min avg
    Primary useism: 0.04 μm/s
    Secondary useism: 0.55 μm/s
QUICK SUMMARY: Vent work continues

 

H1 PSL (IOO, PSL)
cheryl.vorvick@LIGO.ORG - posted 00:20, Monday 13 November 2017 - last comment - 09:46, Monday 13 November 2017(39396)
PSL TBLS and ACS look like they're switched

Looking into PSL temperatures, I started looking at the AC temperatures, and what I see is that the signals for TBLS and ACS appear to be switched.  Attachment shows from left to right:

Images attached to this report
Comments related to this report
jeffrey.kissel@LIGO.ORG - 09:46, Monday 13 November 2017 (39405)CDS, DetChar, IOO, OpsInfo
Opened 
FRS Ticket 9425 to address temperature sensor channel swap problem.

FRS Ticket 9426 to address suspected problem with calibration of the north and south table temperature sensors (we can't believe a ~5 [deg F] between the two sensor exposed to the same air, ~15 ft apart.)
H1 SYS (AOS)
betsy.weaver@LIGO.ORG - posted 19:26, Sunday 12 November 2017 (39394)
Rebuilt ITMX Elliptical Baffle installed and alignment started

Late alog for last Fri:

After moving the AUX IFO simulator beam to the ITMx-PR3 targets installed late Thur, we connected the ITMX Elliptical baffle box to it's down tube suspension structure.  Immediately we discovered that the box looked visibly crooked and out of alignment.  Recall that Robert has data supporting that this (and maybe the ITMY baffle) are misaligned and causing coupling into DARM, see his alog 39290.

We spent a few hours looking into the surveying history of this baffle and came up with somewhat unfinished IAS and alog records of final alignment of this baffle back in 2013.  As well, these records indicate that alignment of the baffles was only performed using the center target, which seems insufficient to align the baffle.  SO, maybe it's no wonder there has been coupling here.

Monday, we'll continue work to align baffles and more, likely with some consult with SYS...

H1 AOS (AOS, SQZ)
gerardo.moreno@LIGO.ORG - posted 18:00, Friday 10 November 2017 (39393)
OFI Table In The Optics Lab

(Betsy, Gerardo)

This morning Betsy and I removed the OFI Table from HAM5, cage, suspension assembly and damping assembly remain inside HAM5.

The table was transported to the optics lab for testing.

H1 SUS (GRD)
sheila.dwyer@LIGO.ORG - posted 17:55, Friday 10 November 2017 (39392)
SUS guardians loaded

In order to keep the suspensions damped as much as possible, I've loaded a changed suspension guardian similar to what is described in 39327 

This will not impact the way users interact with the suspension guardians.  Previously, the suspensions guardians would turn off all damping whenever any stage tripped, the new code does not do this and relies on the watchdogs to turn off any stages which have unreasonable drives.  When the user untrips the watchdog everything will be turned off so that it can be turned back on using the usual guardian procedure. 

The code that we are running here at LHO is actually userapps/sus/h1/guardian/SUS2.py  It is in the svn as revision 16426.  Tripped is still a protected state, which was necessary to keep the suspension from going to the RESET goto state. Attached is a diff between what I've just loaded and the previous version. 

Images attached to this report
Non-image files attached to this report
LHO VE
chandra.romel@LIGO.ORG - posted 17:24, Friday 10 November 2017 (39391)
leak hunting around CP1

[Arnab, Chandra, Kyle, Rakesh]

We spent a good part of today setting up for and diagnosing an unidentified known leak (e-7 Torr-L/s range) between GV 5 & 6, where cryopump #1 (CP1) and spool are (corner station, y-arm side). First we checked for inner o-ring leaks by connecting aux turbo cart to GV annuli and pumping and pressurizing (to about 1 Torr) with bottled dry N2 using a control needle valve. Then we soft closed GV6 (with GV5 hard closed) and shortly after valved in the newly installed 55 l/s ion pump (IP) connected to bottom of CP1. Then we walked over to the 10" CETEC GV on CP1 spool to start removing the ISO flange to connect 500 l/s turbo for He leak checking. Kyle checked the CETEC valve to verify it was closed and was able to tighten by a good half turn. We see two pressure bumps that correlate with these activities. We think we fixed the leak by tightening that CETEC valve (and suspect the ISO side is up to air), but won't know for sure until we open GV6 and trend the adjacent gauge (PT-124b), which rises when exposed to CP1 volume (because of leak) and falls when GV6 is closed.

After the pressure at CP1 (PT-114b) started to plateau just above 1e-8 Torr, we valved out the 55 l/s IP for about 10 minutes (without compressing Cu gasket on right angle valve) and valved back in to check response. We are leaving it in this configuration over the weekend - with GV6 soft closed and 55 l/s IP valved in. Dave Barker set a text alert for PT-114b to alarm for pressures above 2e-7 Torr in case the IP turns off.

Note that this volume has been He leak checked in the past by John & Kyle and remained inconclusive after spraying He and seeing no signal on leak checker.

 

Images attached to this report
H1 TCS (TCS)
greg.grabeel@LIGO.ORG - posted 17:22, Friday 10 November 2017 (39390)
TCS CO2 Table Reposition

The TCS CO2 Y table is approximately in its new location. Unfortunately, this new location is partially off the technical slab, one leg is mostly off as seen in the first photo. While lowering the table off of the wheels one bolt sheared off, so I removed the wheel for now and moving will have to be done with a pallet jack. The new baffle hardware has also been installed with a temporary plate. The panel has a hole too large for the new hardware and this plate will be used until a new panel comes in. The next step is to install the new BSC viewport pieces and lightpipe. 

Images attached to this report
H1 CDS (DCS)
david.barker@LIGO.ORG - posted 16:47, Friday 10 November 2017 (39389)
Continuing the install of E18 RAIDS in the MSR

I extracted the failed fiber-channel fiber FMM-10M-0018 and routed the replacement FMM-10M-0014 through the fiber tubes and cable trays. While the fiber was being replaced, the redundant routing of E18-1 to LDAS via the two Q-Logic switches resulted in no loss of connection. I also rerouted two management ethernet cables from the surplussed SATABOY to the primary controller card on both E18 RAIDS, we will activate these next week.

H1 CDS (VE)
david.barker@LIGO.ORG - posted 16:42, Friday 10 November 2017 (39388)
added vacuum gauge PT114B to cell phone text alarm system

WP7215 Chandra, Kyle, Dave:

As per request from the vacuum group, I have added the PT114B Cold Cathode vacuum gauge (and its associated ERROR channel) to the alarm system. It is configured to alarm if its value goes above 2.0e-07 Torr (it is currently at 1.3e-08 Torr and trending downwards). Alarms will be sent to the vacuum group and myself.

H1 PSL (IOO, PSL)
cheryl.vorvick@LIGO.ORG - posted 16:10, Friday 10 November 2017 - last comment - 01:49, Monday 13 November 2017(39387)
new mode for temp control in PSL

Issues with Commissioning mode and issues with Science mode led me to try a new mode, which is Commissioning mode with Makup Air turned down from 100%.

Leaving it set at 40% - JeffK is watching.

 

Images attached to this report
Comments related to this report
cheryl.vorvick@LIGO.ORG - 01:49, Monday 13 November 2017 (39397)

History of TBLN since alignment on Oct. 31st is shown in the attached plot.

Images attached to this comment
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:07, Friday 10 November 2017 (39386)
Ops Day Shift Summary
Ops Shift Log: 11/10/2017, Day Shift 16:00 – 00:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked - Vent
Intent Bit: Engineering
Support: N/A
Incoming Operator: N/A
Shift Summary: Continuing vent activities
 
Activity Log: Time - UTC (PT)
15:53 (07:53) Cheryl – Going to HAM2 & PSL enclosure
16:00 (08:00) Start of Shift
16:05 (08:05) All dust monitors are online
16:28 (08:28) Jeff K., - Going to HAM2 for IO work
17:24 (09:24) Gerardo – Going to HAM5 for OFI work
17:35 (09:35) Betsy – Going into the LVEA
17:48 (09:48) Jason – Going to Biergarten for Baffle work
17:56 (09:56) Travis – Going to Biergarten for Baffle work
18:17 (10:17) Jason – Going into LVEA to look for parts
19:28 (11:28) Terry – Going to Squeezer Bay – Laser hazard at height
11:30 (11:30) Jeff B, & Kentaro – Staging for ITMY camera install
19:49 (11:49) Betsy, Jason, & Travis – Out of the LVEA
19:57 (11:57) Jeff B, & Kentaro – Out of the LVEA
21:42 (13:42) Jason – Going to the Biergarten for baffle work
21:52 (13:52) Betsy & Travis – Going to Biergarten for baffle alignment work
21:53 (13:53) Chandra, Rakesh, Arnab, & Kyle – To GV1 area for leak checking (WP#7211)  
21:59 (13:59) Jason – Out of the LVEA
22:46 (14:46) Terry – Out of the LVEA
22:50 (14:50) Betsy & Travis – Out of the LVEA
23:15 (15:15) Cheryl – Going to HAM2 and PLS
00:04 (16:04) Terry – Going back into Squeezer Bay
00:05 (16:05) End of shift
 
H1 SEI
hugh.radkins@LIGO.ORG - posted 12:34, Thursday 09 November 2017 - last comment - 08:22, Monday 13 November 2017(39356)
WHAM5 ISI Optical Table Level check--Very Level

Gerardo stated that the Optical Table was not very level using a small T-Level and that the OFI needed adjustment to hang properly after doing all the adjustments on an optical table bench.

So I used the Optical Auto Level to look at the table.  With seven shots, above the walls at every corner and in the center of the table, the range of level was +-0.1mm--very level in our books.  I did manage to tie it into our LVEA monuments to put an actual elevation on the table: -325.8mm Lz.  Adding the -0.3mm conversion from local the global gives -325.8mm Gz (See T1100187.)  Looking at D0901129, it shows the Optical table to be 325mm below the BEAM TUBE CL.  I can't tell or remember if this is below the HAM5 BT CL or below the BSC2 BT CL where global 0 0 0 is positioned.  Either way, we are within 0.5 to 0.8mm of ideal elevation for this Optical Table and again very level.  Frankly, I'm relieved!  Attached are my field notes.

Non-image files attached to this report
Comments related to this report
hugh.radkins@LIGO.ORG - 08:22, Monday 13 November 2017 (39400)

I've got a couple typo above:

 

Gerardo stated that the Optical Table was not very level using a small T-Level and that the OFI needed adjustment to hang properly after doing all the adjustments on an optical table bench.

So I used the Optical Auto Level to look at the table.  With seven shots, above the walls at every corner and in the center of the table, the range of level was +-0.1mm--very level in our books.  I did manage to tie it into our LVEA monuments to put an actual elevation on the table: -325.8 325.5mm[see notes] Lz.  Adding the -0.3mm conversion from local the to global gives -325.8mm Gz (See T1100187.)  Looking at D0901129, it shows the Optical table to be 325mm below the BEAM TUBE CL.  I can't tell or remember if this is below the HAM5 BT CL or below the BSC2 BT CL where global 0 0 0 is positioned.  Either way, we are within 0.5 to 0.8mm of ideal elevation for this Optical Table and again very level.  Frankly, I'm relieved!  Attached are my field notes.

H1 SYS (DetChar, ISC, PEM, SYS, TCS)
jeffrey.kissel@LIGO.ORG - posted 17:41, Friday 03 November 2017 - last comment - 14:23, Wednesday 15 November 2017(39288)
HAM4 Baffle and HWS Components B&K Hammered
J. Kissel

Since HAM4's construction / installation stuff for this vent is complete as of yesterday's HWS Scraper Baffle install (LHO aLOG 39266), and the debugging of SR2's M2 OSEM today (LHO aLOG 39277), I took the afternoon to start B&K hammering all of the new / old baffle equipment and HWS mirror / lens mounts. Note, I deliberately skipped the SR2 cage, since nothing has changed on it since it was originally measured in LHO aLOG 12089, and I trust that Betsy and Travis successfully re-dogged and torqued bolts when they finished the relocation a few days ago LHO aLOG 39240.

Will post pictures and results next week.
Comments related to this report
jim.warner@LIGO.ORG - 14:23, Wednesday 15 November 2017 (39427)AOS

I'm attaching some plots of Jeff's data. Would be nice if the B&K data were easier to get into a publishable form, I can't guarantee I haven't screwed something up in here, a lot of places where it would be easy to make a mistake. Some of the TFs have almost no coherence, Jeff said it was hard to get the accelerometer close in couple cases.

One extended point about getting data from the B&K machine. It's possible to export one data set at a time (i.e. get the tf & coherence for one channel). Then to get them in a manageable format for matlab, I used sed to remove the last seven lines and the first 84 lines from the exported data txt file. This was some thing of the form:

 sed -i '6486,6492d' *100-1100*.txt

to remove the last seven lines of all of Jeff's data files that had 100-1100 in the name (for the frequency band) and:

sed -i '1,84d' *.txt

to remove the first 84 lines from all of the files in the directory. Best to backup your data before doing this, cause sed won't ask if you're sure. I had to try several times to get it right. The '1,84d' tells sed to delete lines 1-84. There's probably some clever way to tell sed to remove the last seven lines, I couldn't find it, so I just looked in the file to see how many lines there were.

Images attached to this comment
jeffrey.kissel@LIGO.ORG - 16:00, Friday 10 November 2017 (39385)
Attached are pictures of each setup for the above B&K hammering, in case they need to be reproduced.

Jim has volunteered to process the data.
Images attached to this comment
Displaying reports 49881-49900 of 88171.Go to page Start 2491 2492 2493 2494 2495 2496 2497 2498 2499 End