Hanford Fire Maintenance was out today after the 2 false alarms at the LSB and determined that the fire alarm control panel is faulty. Apparently a control board has been fried. HFD has taken the panel out of service and will remain disabled until we can correct the problem. Meanwhile, I would ask that the swing and owl shift operators do a walk through of the LSB every 2 hrs for the rest of the week and then 2 hr checks for all 3 shifts on the weekend. Training the control room camera towards the LSB may also be a good idea.
PT110 (HAM6 pressure gauge) showed some sort of "hiccup" - see attached.
Also PT 170 and PT180 glitched at same time although with a different shape curve.
Hmmm. Wonder when Fil was installing his Cable Pulling Guide...
I lowered the exposure for the IO GigE cameras on the PSL from 4000 to 100. At this new exposure the cameras are not saturated at 30W. The beams are hard to see at 2W, but the SUM is still sufficient for reasonable x/y data.
Sheila, Fil, T Vo
We got a little time at the end of PEM injections to try a different method of disconnecting the ETMX ESD cables. We had the sheildling box already installed at EX, so we went there and first disabled the HV ESD driver, then powered off the low voltage driver. Fil grounded the sheilds of the ESD cables using the grounding box, and then disconnected the LL cable from the shielding box (on the chamber side) and connected it to the grounding box he made on monday. The interferometer stayed locked and the noise didn't change, but just as we were touching the cables on the input side of the shielding box the interferometer unlocked. It seems like something is extremly touchy here, which we already knew.
IFO is locked at NLN, Intent Bit is Commissioning. Robert S. doing PEM injections from 16:00 to 20:00 (09:00 to 13:00PT). HFD responded to fire alarm at LSB. Bubba and Richard were notified. Appears to have been a false alarm.
PT343b at the X-mid went off at about 10:30 hrs. local. I re-enabled it and it came back on in a few minutes. John W. contacted Gil Hibbs who was in the X-mid VEA at the time. Gil didn't think that he was near the area of the gauge. Perhaps just coincidence. We have had gauges along the X-arm turn off a few times this year when there was human traffic in the area of the gauge(s) but no causal determination has been shown. Probably unrelated. John and I both got emails when the gauge dropped out but no texts (5 minute threshold for texts?)
TJ swept LVEA before the start of commissioning. He unplugged one unused extension cord.
TITLE: 08/09 Owl Shift: 07:00-15:00 UTC (00:00-08:00 PST), all times posted in UTC STATE of H1: Observing at 53Mpc INCOMING OPERATOR: Jeff SHIFT SUMMARY: No issues to report. LOG: 14:36 UTC Ken pulling wire in OSB.
Have remained in observing. No issues to report.
TITLE: 08/09 Owl Shift: 07:00-15:00 UTC (00:00-08:00 PST), all times posted in UTC
STATE of H1: Observing at 54Mpc
OUTGOING OPERATOR: Ed
CURRENT ENVIRONMENT:
Wind: 5mph Gusts, 2mph 5min avg
Primary useism: 0.04 μm/s
Secondary useism: 0.06 μm/s
QUICK SUMMARY:
0.03 - 0.1 Hz seismic BLRMS is coming down from after earthquakes near Alaska.
07:25 UTC Lock clock not updating. Lock timer python script not running. Started. Screenshot attached.
TITLE: 08/09 Eve Shift: 23:00-07:00 UTC (16:00-00:00 PST), all times posted in UTC
STATE of H1: Observing at 53Mpc
INCOMING OPERATOR: Patrick
LOG: N/A
SHIFT SUMMARY:
Mid_Shift Summary (never got posted)
After many failed attempts to recover lock after the EQ(s), I performed initial alignment. The furthest I've been able to get thus far is LOWNOISE_ESD_ETMY. I had to pause at DC readout to tame some ETMX violin modes.
Lockloss problems included:
ETMX Violin Mode damping:
Lots of phone time with Sheila got H1 back in business.
I'd like to suggest that next time an earthquake takes us down we wait to re-lock and assess any artifacts from the event before beginning maintenance on the IFO and then take it down on our own terms to begin making changes.
06:27 H1 back to Observing
23:50UTC whilst trying o acquire lock and 95% of the way there, a 6+mag EQ in Khazakstan‌ took us down. The Observatory mode wasn't switched to environment until 00:40. Apologies for the late action.
TITLE: 08/08 Eve Shift: 23:00-07:00 UTC (16:00-00:00 PST), all times posted in UTC
STATE of H1: Preventive Maintenance
OUTGOING OPERATOR: Travis
CURRENT ENVIRONMENT:
Wind: 11mph Gusts, 7mph 5min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.06 μm/s
QUICK SUMMARY:
Currently trying to debug ALS troubles. Sheila is on the case.
The ALS troubles described above went away on their own. I dont know what happened.
SudarshanK, RichardS
We moved the Pcal beam back to their optimal position at 111.6 mm away from the center of the optic. The actual position of the current Pcal beams (last column) along with the history of where they were are in the table below. The number quoted on the table are distance of Pcal beam (in mm) from their optimal position of [0, +/- 111.6] mm.
| Before 07/25/2017 | 07/25/2017 | 08/01/2017 | 08/08/2017 | |
| Upper Beam | [1.9, 0.3] | [2.5, -8.4] | [1.1, 14.5] | [0.8, 0.6] |
| Lower Beam | [-1.0, 0.3] | [-1.3, 8.6] | [-0.5, -14.1] | [-0.8, -0.2] |
We also re-centered the Pcal beams on the receiver side to relieve it from any clipping that was happening outside the vacuum. The spectra attached below shows no significant clipping on the Rx beams.
We will run a set of calibration lines (from 4501.3 - 1501.3 at 500 Hz interval) with this Pcal beam configuration for about a week.
After this Pcal beam configuration change, we turned on the two Pcal lines at 333.9 and 1083.3 Hz using Pcal at ENDX. We will collect about 2-3 hours worth of data after we acquire the lock and turned them off. We plan to initiate the HIGH_FREQ_LINES guardian node to acquire data at high frequency after that.
T Vo, Sheila
We measured a transfer function from PCAL X to DARM this afternoon. The attached screenshot shows a comparison of driving the ETMX ESD in the low noise state (with the settings that allowed us to transition to it from ETMY) and a drive to PCALX_DARM with the filters that Thomas copied from the ESD filter banks. The red trace (ref 14+15) were taken with a gain of -150 in the PCAL filter bank.
Based on this measurement, Thomas and I estimated this morning that we would need a gain of about -3000 in the PCAL X DARM bank to transition to PCAL X from the ESD, but that this would result in about 50 V rms on the OFS PD. (There is about -82 dB of gain between the OFS PD (in Volts) and the output of the PCALX DARM bank. This means that we would not have enough range on PCAL to simply replace the ESD with PCAL, so we have not tried the transition or locking ALS on ETMY.
If we aren't able to disconnect the ESD cables while in lock, we could look at using one of the ITM ESDs to transition from high voltage to low voltage on one ESD with the other disconnected. We also talked with Daniel, RIchard and Fil who had some ideas about different ways to try disconnecting the cables while in lock. We were about to try these when the EQ hit us.