Displaying reports 55041-55060 of 83122.Go to page Start 2749 2750 2751 2752 2753 2754 2755 2756 2757 End
Reports until 09:01, Thursday 04 August 2016
H1 General
cheryl.vorvick@LIGO.ORG - posted 09:01, Thursday 04 August 2016 (28867)
Ops Morning Update:

State of H1: new OMC is in HAM6 - needs further work, shutter is closed - no IMC, site activities taking advantage of the down time

Activities: all times UTC

15:00 - JeffB - new dust monitor, #7, sampling same volume as #6 - test of system and low dust counts

15:45 - Richard - WP6053 - EX and EY Low voltage ESD driver modifications

H1 PEM
jeffrey.bartlett@LIGO.ORG - posted 08:27, Thursday 04 August 2016 (28865)
Add New Dust Monitor at HAM6
   Added a new dust monitor at HAM6 for huddle testing. The new monitor (#7) is strapped to the back of the support stand for the existing monitor (#6). To the crew working around the NE corner of HAM6, please be aware of the new monitor. I have not adjusted the alarm levels. This monitor will be removed shortly after the HAM6 vent is finished.     
H1 ISC (SUS)
koji.arai@LIGO.ORG - posted 00:33, Thursday 04 August 2016 - last comment - 08:33, Thursday 04 August 2016(28862)
The new OMC installed on the OMC Suspension

[Betsy, Corey, Chris, Koji]

Summary

- A panel of the OMC black glass shroud with a burned spot was removed. LHO aLOG 28861

- The new OMC is now suspended in the OMC SUS

- We still need balancing work of the suspension

- Once the OMC breadboard is nicely balanced, the beam will be aligned.

- We'll performe the electrical function check.


Details

- The new OMC container was moved from the bonding lab to LVEA

- The weight of the old and new OMC was compared. All the balance masses were moved from the old OMC to the new OMC. Then to reduce the exess mass of the new OMC, 10g mass was removed from each ballast at the DCPD side. (10g+10g was removed.) This made the new OMC 2g lighter then the old one. Betsy keeps the actual numbers.

- The first contact films were removed at the chamber side. Some residuals were seen on non-cavity mirror optics. They were removed by another trial of the FC.

- Then the new OMC was installed on the OMC Suspension.

- The cabling of the OMC was restored.

- The locks of the suspension masses and the blades were released. Now the OMC Breadboad is freely suspended.

- The balance of the OMC breadboard was reviewed. One of the corner is about 1mm too high. As we already adjusted the total weight, this should be done by moving the ballast mass on the breadboard.

Comments related to this report
corey.gray@LIGO.ORG - 08:33, Thursday 04 August 2016 (28864)

Photos From Yesterday's HAM6 Work

All photos from yesterday's work are in resourcespace in a folder for 8/3's work here:

https://ligoimages.mit.edu/?c=1698

Attached are some highlight photos:

  1. Betsy & Koji removing First Contact from OMC optics
  2. Applying First Contact to remove particulate
  3. Close Up of First Contact
  4. Koji & Betsy (& Chris Whittle) During re-hanging of new OMC Breadboard
  5. Koji in action
  6. Betsy in action
Images attached to this comment
H1 AOS
jeffrey.kissel@LIGO.ORG - posted 17:36, Wednesday 03 August 2016 - last comment - 17:57, Wednesday 03 August 2016(28858)
H1SUSETMs Modified to Have Individual Coil Driver Switching; ITMs will be done tomorrow.
J. Kissel
ECR E1500045
FRS 6014
WP 6051

I've begun the roll out of individual state switch-ability for the PUM / L2 coil drivers. This is essentially complete for the ETMs (just a few more aesthetic MEDM screen changes are needed). I've confirmed all functionality behaves as expected. I've reconciled the SDF "down" snap before hand, and made sure that all settings were restored, including initializing/accepting the new EPICs records that come with this update.

Though the model changes have been made to the simulink model for the ITMs (because the ITMs and ETMs are using a generic L2 stage library part), they have not yet been compiled or installed, and MEDM screens have not been updated (because they now have separate MEDM infrastructure [see LHO aLOG 27641], generic changes to all QUADs like this takes twice as long). Stay tuned for more details and screenshot in tomorrow's "it's complete" aLOG.

Still to Do:
- Edit EUL2OSEM MEDM screens to support the ramping matrix on ETMs
- Compile / Install / Restart ITM models (with accompanying DAQ restart)
- Edit ITM QUAD OVERVIEW and BIO screens for all the same changes as I've done to the ETM QUAD overview
- commit everything to the SVN
- Make sure that the ISC_LOCK guardian hits the "LOAD MATRIX" button on the PUMs in the DOWN state.
- Integrate new "three wheel motion" coil driver switching into the ISC_LOCK guardian in the COIL_DRIVERS state
Images attached to this report
Comments related to this report
david.barker@LIGO.ORG - 17:57, Wednesday 03 August 2016 (28860)

We had a strange issue with the h1susetmx restart. The H1SUSETMX.ini file was changed at 17:08, h1susetmx was restarted at 17:10 and the DAQ was restarted at 17:12. Yet the DAQ status for h1susetmx ended up as 0x2000 (ini file check sum mismatch). A restart of h1susetmx fixed the problem. With so much time between restarts this does not look like a slow NFS file issue.

LHO VE
filiberto.clara@LIGO.ORG - posted 17:17, Wednesday 03 August 2016 - last comment - 10:48, Friday 05 August 2016(28857)
Y2-8 HV Ion Pump Cable Repaired

The HV power cable for the Y2-8 ion pump has been repaired. The damaged section was cut off, and the cable was spliced together. Cable was tested with the HI-POT tester to 5KV.

Comments related to this report
gerardo.moreno@LIGO.ORG - 17:23, Wednesday 03 August 2016 (28859)

Connected cable to controller and turned ion pump on.  Pump is pumping now, see attached for 3 hour trend data.

Images attached to this comment
chandra.romel@LIGO.ORG - 10:45, Thursday 04 August 2016 (28868)
Thank you!!
gerardo.moreno@LIGO.ORG - 10:48, Friday 05 August 2016 (28895)

Work done under WP #6047 and FRS ticket 5992 closed

H1 ISC
stefan.ballmer@LIGO.ORG - posted 16:47, Wednesday 03 August 2016 (28856)
ITMs still in distributed design (ETMs are offloaded)

I noticed (somewhat surprised) that we run the ITMs in distributed design (the ETMs are off-loaded). Unless someone remembers a good reason for this, I would recommend switching both to offloaded design. We require a balancing of ETM and ITM transfer function for the HARD/SOFT basis change, which is a bit of a nightmare if we run ETMs and ITMs in different modes.

This also means that by AS top stage offloading implementation (alog 28763) did not work for the ITMs since I relied on the signal flowing through the L1 filter banks. We will have to redo this.

H1 DAQ
jonathan.hanks@LIGO.ORG - posted 16:45, Wednesday 03 August 2016 (28855)
More on frame writer testing (splitting the producer thread)
As a follow up to (https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28749) we have a build of the framewriter on h1fw2 that splits the producer thread into two components.

Here is a sample timing:

producer thread timings
 recv min:0.0592079 mean:0.0624186 max:0.0642519
producer crc thread timings
 full min:0.0259149 mean:0.0270363 max:0.0351679
 crc  min:0.014359 mean:0.0144825 max:0.0150859
 xfer min:0.0115559 mean:0.0125535 max:0.0200801

The producer thread does nothing but receiving data.  Here we notice the time to receive is increased to the full 1/16s.  We believe this is largely a busy wait while it waits for the data to come in.

The secondary thread (producer crc) is now doing the crc calculations and pushing the data stream into the main buffers.  We will watch this over night and see how the system is running tomorrow.
H1 CAL (CAL)
sudarshan.karki@LIGO.ORG - posted 16:43, Wednesday 03 August 2016 (28854)
Pcal Images for EX

S. Karki, M. Chen

While trying to take the ETM images at EndX today  to find the position of the Pcal beams we notice the following things:

1. Blocking the beam at receiver modules with beam dump before it enters the integrating sphere helps to reduce the scattered light (slightly).

2. The optical lever needs to be turned off to get any decent picture showing the Pcal beams on it. The optical lever light completely obscures the Pcal beams. (See attached Pic 1).

3. Take pictures with illuminator off to get the the Pcal beam spot on it. Use small f-number to get Pcal beam on focus. (see attached Pic 2).

4. Keeping all the settings from 3, turn illuminator on and increase the f-number to max to get all the features on test mass (see attached Pic 3).

Images attached to this report
H1 SEI (SEI)
patrick.thomas@LIGO.ORG - posted 16:31, Wednesday 03 August 2016 (28853)
ISI CPS Noise Spectra Check - Weekly - BSCs and HAMs
FAMIS #6857

HAM5 and HAM6 are well above the reference trace. In chamber work?
Images attached to this report
LHO General
thomas.shaffer@LIGO.ORG - posted 16:00, Wednesday 03 August 2016 (28832)
Ops Day Shift Summary

TITLE: 08/03 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Unknown
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:

H1 SEI
jim.warner@LIGO.ORG - posted 14:59, Wednesday 03 August 2016 (28852)
FAMIS # 6077 STS Centering Check

STS and T240 centering checks. FAMIS task 6077 closed.

jim.warner@opsws0:scripts 0$ pwd
/opt/rtcds/userapps/trunk/isi/common/scripts
jim.warner@opsws0:scripts 0$ ./check_sts_centering.py h1
Averaging Mass Centering channels for 10 [sec] ...


2016-08-03 14:55:35.366977
All STSs prrof masses that within healthy range (< 2.0 [V]). Great!


Here's a list of how they're doing just in case you care:
STS A DOF X/U = -0.0 [V]
STS A DOF Y/V = -0.0 [V]
STS A DOF Z/W = -0.0 [V]
STS B DOF X/U = 0.14 [V]
STS B DOF Y/V = -1.259 [V]
STS B DOF Z/W = -0.163 [V]
STS C DOF X/U = -0.0 [V]
STS C DOF Y/V = -0.0 [V]
STS C DOF Z/W = -0.0 [V]
STS EX DOF X/U = -0.249 [V]
STS EX DOF Y/V = 0.603 [V]
STS EX DOF Z/W = 0.032 [V]
STS EY DOF X/U = 0.056 [V]
STS EY DOF Y/V = 0.369 [V]
STS EY DOF Z/W = 0.242 [V]


Assessment complete.
 

%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

jim.warner@opsws0:scripts 2$ ./check_T240_centering.py h1
Averaging Mass Centering channels for 10 [sec] ...
2016-08-03 14:54:50.368892


There are 1 T240 proof masses out of range ( > 0.3 [V] )!
ETMY T240 1 DOF Y/V = 0.392 [V]


All other proof masses are within range ( < 0.3 [V] ):
ETMX T240 1 DOF X/U = 0.065 [V]
ETMX T240 1 DOF Y/V = 0.062 [V]
ETMX T240 1 DOF Z/W = 0.08 [V]
ETMX T240 2 DOF X/U = -0.222 [V]
ETMX T240 2 DOF Y/V = -0.262 [V]
ETMX T240 2 DOF Z/W = -0.095 [V]
ETMX T240 3 DOF X/U = 0.035 [V]
ETMX T240 3 DOF Y/V = -0.023 [V]
ETMX T240 3 DOF Z/W = 0.048 [V]
ETMY T240 1 DOF X/U = 0.039 [V]
ETMY T240 1 DOF Z/W = 0.053 [V]
ETMY T240 2 DOF X/U = -0.085 [V]
ETMY T240 2 DOF Y/V = 0.056 [V]
ETMY T240 2 DOF Z/W = 0.055 [V]
ETMY T240 3 DOF X/U = 0.053 [V]
ETMY T240 3 DOF Y/V = 0.036 [V]
ETMY T240 3 DOF Z/W = 0.056 [V]
ITMX T240 1 DOF X/U = -0.16 [V]
ITMX T240 1 DOF Y/V = 0.175 [V]
ITMX T240 1 DOF Z/W = 0.121 [V]
ITMX T240 2 DOF X/U = 0.158 [V]
ITMX T240 2 DOF Y/V = 0.147 [V]
ITMX T240 2 DOF Z/W = 0.142 [V]
ITMX T240 3 DOF X/U = -0.089 [V]
ITMX T240 3 DOF Y/V = 0.108 [V]
ITMX T240 3 DOF Z/W = 0.167 [V]
ITMY T240 1 DOF X/U = 0.055 [V]
ITMY T240 1 DOF Y/V = -0.015 [V]
ITMY T240 1 DOF Z/W = -0.079 [V]
ITMY T240 2 DOF X/U = 0.102 [V]
ITMY T240 2 DOF Y/V = 0.094 [V]
ITMY T240 2 DOF Z/W = 0.047 [V]
ITMY T240 3 DOF X/U = -0.152 [V]
ITMY T240 3 DOF Y/V = 0.092 [V]
ITMY T240 3 DOF Z/W = -0.231 [V]
BS T240 1 DOF X/U = -0.053 [V]
BS T240 1 DOF Y/V = 0.028 [V]
BS T240 1 DOF Z/W = 0.096 [V]
BS T240 2 DOF X/U = 0.085 [V]
BS T240 2 DOF Y/V = 0.086 [V]
BS T240 2 DOF Z/W = 0.081 [V]
BS T240 3 DOF X/U = -0.08 [V]
BS T240 3 DOF Y/V = 0.037 [V]
BS T240 3 DOF Z/W = -0.062 [V]


Assessment complete.
 

H1 General
vernon.sandberg@LIGO.ORG - posted 14:50, Wednesday 03 August 2016 (28851)
Work Permits, Maintenance Day 2016 August 02

Work Permits, Maintenance Day 2016 August 02

  Name WP Date Description alogs
1 6026 2016-07-28 Activity: Shutdown h1conlog1-master and h1conlog1-replica. Give the disks to LDAS to archive. https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28707
2 6027 2016-07-28 Activity: Start and run chilled water booster pump and Kobelco https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28713
3 6028 2016-07-28 Activity: Run signal cable for new Inficon BPG402 vacuum gauge to be installed on HAM6. Cabling will be routed from HAM6 to rack SUS-R5 (BSC3).  
4 6029 2016-07-28 Activity: Position 3 cleanrooms at the North & South doors of HAM6 for vent. https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28743
5 6030 2016-07-28 Activity: MONDAY -verify purge air dew point (testing Kobelco 7/28) -soft close GV 5 & 7 -vent HAM6 up to air -pull north and south doors (in chamber work Tues, Wed) WEDNESDAY -replace CC/pirani gauge with full range ion gauge on an all-metal valve THURSDAY -install doors -pump down HAM6 (~ 3 hrs until turbo can be turned on) FRIDAY -open GV 5 & 7 NOTE: most likely the week of Aug. 14th is when we can transition from turbo to IP only. This work will require crane and fork lift use. https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28821
6 6031 2016-07-28 Activity: Lock HEPI at HAM6 for duration of Vent unless intermittent unlocking is desired by commissioners/troubleshooters  
7 6032 2016-07-29 Activity: Tweak/calibrate servos, ISS especially. Check out the TTFSS field box functionality (or lack thereof).  
8 6033 2016-07-29 Activity: Collect video footage for LIGO article. Will have tour group and video activities on Saturday. Vern Sandberg and Rich Abbott to supervise activity for safety and compliance  
9 6034 2016-08-01 Activity: Connect output of Inficon guage (BSC7) to a safety interlock in the CER Mezzanine. Interlock enables/disables the high voltage power supplies to the ITM ESD. Will coordinate with vacuum team when connecting/disconnecting to vacuum gauge. A safety interface relay chassis D1400047 will be installed on top of rack in CER.  
10 6035 2016-08-01 Activity: investigate why epics values changed during the last two timing code upgrades. All EY computer systems will be restarted. No DAQ restart required.  
11 6036 2016-08-01 Activity: DetChar tour of LVEA  
12 6037 2016-08-01 Activity: In prep for ISS upgrades, install a binary IO card in h1psl0's IO Chassis and move one ADC card to make room.  
13 6038 2016-08-01 Activity: Move ISCT6 Take pictures of all cables connected to ISCT6 and document. Disconnect all cables from ISCT6. Insert lexan window to the viewports, remove bellows. Land ISCT6 and move it out of the way so we can remove the HAM6 door the first thing in the morning. Put yellow viewport protectors on HAM6 viewports.  
14 6039 2016-08-01 Activity: We would like to make a measurement while leaving CO2 on at high power overnight. There will be a script to turn the laser on/off automatically.  
15 6040 2016-08-01 Activity: Remove excess property from LVEA per Property Services.  
16 6041 2016-08-02 Activity: Routine (semi-annual) maintenance - measure powers, tweak alignments, calibrate, etc. Area of Activity: Yend Pca  
17 6042 2016-08-02 Activity: Installation and commissioning of the instrument in the bier garten, power and data cable pulling, Area of Activity: LVEA Newtonian Noise Array -- Compact BRS Addition https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28829
18 6043 2016-08-02 Activity: Swap out CO2Y RF driver. Area of Activity: TCS  
19 6044 2016-08-02 Activity: Conducting a brief tour of two in LVEA. This is a potential applicant for the LLO operator position, who has contacted me via a public tour. Undergrad in Physics, specializing in optics and lasers.  
20 6045 2016-08-02 Activity: Conduct a tour of visitors from the Bejing Normal University, China.  
21 6046 2016-08-02 Activity: Tour for candidate.  
22 6047 2016-08-02 Activity: Unplug and test HV cable for ion pump at the Y-End station, and remove and replace broken component(s). Area of Activity: Vacuum, Y2-8 Ion Pump Cable at Y-End and at Y2-8. https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=28847
23 6048 2016-08-02 Activity: Survey all viewport covers to confirm the lexan assemblies have all hardware in tact.  
24 6049 2016-08-02 Activity: Survey all viewport covers to confirm the lexan assemblies have all hardware in tact.  
25 6050 2016-08-03 Activity: Candidate tours of LVEA, Wed am, Wed pm, Thu pm  
26 6051 2016-08-03 Activity: Convert QUAD PUM/L2 output matrix to ramp matrix for independent channel switching of coil driver analog filtering. Approved ECR is E1500045.  
H1 SEI
thomas.shaffer@LIGO.ORG - posted 14:35, Wednesday 03 August 2016 (28850)
OPS: reset of HEPI L4C Accumulated WD Counters Wednesday 3rd August 2016

Counts are attached.

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 14:21, Wednesday 03 August 2016 (28849)
h1oaf0 models restarted for CBRS DAC shuffle

Jenne, Jeff, Robert, Nutsinee, Dave:

Jenne added the CBRS system to the h1ngn model. This system requires four DAC channels. Robert has given up four PEM channels for this temporary test system.

All models on h1oaf0 were restarted. It was necessary to restart the IOP model when DAC channels are moved between models in order to rescan the channel allocations. Because this in turn requires a restart of h1tcscs, Nutsinee tested disconnecting the temperature control cable at the mezanine chiller to see if we could avoid the chiller trips normally related to h1tcscs restarts.

The restart procedure was:

Nutsinee disconnects temp control cable at TCS chiller

All models were shutdown

h1iopoaf0 started

h1pemcs, h1oaf and h1ngn models started (these models use the 18bit DAC)

h1tcscs, h1odcmaster, h1calcs, h1susprocpi models started

Nutsinee reconnects the temp control cable

The chiller did not trip, this was a successful procedure.

The 8 channel 18bit DAC allocation is:

h1ngn (cbrs) chans 0-3

h1pemcs chans 4-6

h1oaf chan 7

H1 SEI
jim.warner@LIGO.ORG - posted 14:12, Wednesday 03 August 2016 (28848)
BRSY has been recentered, now functioning again

Krishna, Michael, JimW

Yesterday during maintenance, Krishna, Michael and I went to EY and recenterd BRSY. Finicky business, but it's done now. BRSY is running again, so we can return to using the normal "Windy" SEI_CONF state for the ISIs. Attached first trend is the last 10 days of the driftmon, noise in the middle is from when the BRS went out of range over the weekend, green on the right is the BRS re-equilibrating after we closed the enclosure.

Second attached trend is 120 days showing several of the resets of this BRS. Looks like the rate of drift is still slowing, hopefully we can go another couple of months.

Images attached to this report
H1 PSL
edmond.merilh@LIGO.ORG - posted 13:31, Wednesday 03 August 2016 - last comment - 08:48, Thursday 04 August 2016(28846)
DBB Scans FAMIS# 6584

RPN: 35W- no change

        200W- no change    

FRQ: 35W- no change from 10Hz to 1K. Control signal is better than last week from 1-10Hz. Error signal higher at HF.

        200W- no change

PNT: 35W- no change

         200W- no changes to speak of. High peaks at 100Hz, 1K and HF noise.

MSC: 35W-  no change. TEM10 looks a bit high. HOM power and cts are down marginally from last week

        200W- no significant change. Plot actually looks slightly better than last week despite no adjustments. Errors during measurement can be seen in the .pdf below.

Images attached to this report
Non-image files attached to this report
Comments related to this report
jason.oberling@LIGO.ORG - 08:48, Thursday 04 August 2016 (28866)

Ed's analysis is spot on.  No serious changes from previous scans.

H1 ISC (ISC)
corey.gray@LIGO.ORG - posted 12:52, Wednesday 03 August 2016 - last comment - 10:08, Tuesday 09 August 2016(28842)
HAM6 Photos From Yesterday (8/2): Damage, Dust, & Action Shots

(Betsy, Corey, Keita, Koji & also some photos by Richard M)

Following up on alogs from Keita & Koji, photos from yesterday's work has been uploaded to resourcespace and can be found here:

https://ligoimages.mit.edu/?c=1696

(There's 91 photos.  I did not upload blurry photos.)

I'm attaching highlight photos to this alog & they are roughly numbered in the order taken:

  1. M14 (was removed to blow particle off)
  2. Fingerprints on NW corner of shroud
  3. V-beam Dump (on/near QPD sled on northern part of table) with major damage on both pieces of glass
  4. Burn hole at entrance aperature on the shroud glass for OMC
  5. Photos of damage on V-Beam Dump after pulled out and on inspection table.
  6. Photos of damage on V-Beam Dump after pulled out and on inspection table.
  7. Photos of damage on V-Beam Dump after pulled out and on inspection table.
  8. Action shots of Betsy/Koji & OMC removal
  9. Action shots of Betsy/Koji & OMC removal
  10. Action shots of Betsy/Koji & OMC removal
  11. OMC PZT mirror with burn mark
  12. OMC PZT mirror with burn mark
  13. Particle contaminants on OMC Breadboard
  14. Delaminated epoxy on one of the "tomb stones"
Images attached to this report
Comments related to this report
koji.arai@LIGO.ORG - 20:24, Wednesday 03 August 2016 (28861)

> 4. Burn hole at entrance aperature on the shroud glass for OMC

Today, we took out the black glass panel with a burn hole from the OMC shroud.

The attached close-up photo shows the burn hole above the entrance aperture to the OMC. Also, you can observe many more craters.

As we are going to install the replacement panel, we wonder what was the cause of these misaligned craters and what was the difference between the small craters and the biggest burn hole.

Images attached to this comment
betsy.weaver@LIGO.ORG - 10:08, Tuesday 09 August 2016 (28952)

~10:00AM WED AUG 4th, 2016 - Chamber entrance Particle counts with hand held CC counter:

Particle size Outside of chamber cover, in CR In chamber above table
0.3um 70 0
0.5um 20 0
1.0um 10 0

 

~1PM WED AUG 4th, 2016 - Chamber entrance Particle counts with hand held CC counter:

Particle size Outside of chamber cover, in CR In chamber above table
0.3um   0
0.5um   0
1.0um   10
Displaying reports 55041-55060 of 83122.Go to page Start 2749 2750 2751 2752 2753 2754 2755 2756 2757 End