Rotation stage is disabled at 2W input power to the IMC.
Of course, the shutter is closed, so there is no beam from the PSL into the vacuum system.
We closed the shutter for two laser beam pipes between PSL and HAM1.
Lexan plates were installed on all HAM6 viewports. Yellow covers were installed on these viewports except one. For the remaining one, Gerardo will find and install one later).
Cable connections were documented and photographed, and all cables were disconnected from the table.
The accelerometer cable on HAM6 North door was disconnected fron the accelerometer and was taped on HAM5 North door. But the accelerometer itself is still on HAM6 North door.
ISCT6 was moved out of the way.
Took 12 sec. to overfill CP3 until LN2 poured out exhaust, with 1/2 turn open on LLCV bypass valve. Lowered CP3 LLCV from 18% to 17%.
Chandra, Gerardo, Kyle Added ~ 2 Qts Turbine oil. Routing output to LVEA
~1330 hrs. local Measured dew point in LVEA < -35C
In order to move ISCT6, the lightpipe from the PSL needed to be closed.
Jenne closed it and locked it closed - it should remain until after the HAM6 vent.
Not quite...
Hugh did a lot of work over the last few weeks diagnosing the ITMX ISI, with respect to it tripping earlier than the other platforms during an earthquake. His fix last week seems to have worked, at least for the earthquake Friday. First 2 attached plots are the ST1 WD Triggers (the ISI has tripped when the trigger /= 0, first plot shows the triggers separately, second is all on the same plot) , and ITMX, ITMY and ETMX all trip at roughly the same time. ETMY and the BS trip several minutes later, but they were in different configurations (BS is always Isolated_Damped, ETMY had it's sensor correction turned off). This was a large earthquake that came up quickly (third plot shows ETMY Z STS 30-100 mhz BLRMS and ITMX WD trigger) , but for now it looks like ITMX is behaving like the other platforms.
The following is a short calculation of the ITM lensing estimates for O1 for the recycling cavities based on the measurements from the HWS.
WP 6022
I have updated the PI models (28462) in order to accommodate four excitation paths for test mass' drum head modes. The h1omcpi and h1susprocpi models will be restarted tomorrow. The modification will be used
This update actually involves not only h1omcpi and h1susprocpi models but also h1omc. However, in light of the upcoming in-vac activity with the OMC, we will hold off the update on h1omc so that we can recover the interferometer with least confusion. The update on h1omc will go in some time later once we recover the interferometer.
[eLIGO amplitude locked loop]
Here is a screenshot of the digital amplitude locked loop of a drum head mode that had been used in eLIGO.
This algorithm is imported to the current PI models. One update we might additionally implement in some future is a clock recovery with iWave instead of the clipping-based clock recovery.
[Modification on h1omcpi]
h1omcpi has one update i.e., normalization of the OMC DC signals.
I modified one of the down conversion channels, chan 8, to have a normalization using the OMC DCPD SUM. It is show in the orange-shaded region. This signal is sent to the susprocpi model and processed to generate feedback signals for the test masses.
[Modification on h1susprocpi]
Here is a screenshot of the top level of h1susprocpi in which a parallel excitation block for the drum head modes (a pruple block at the bottom) are shown.
This block contains four identical amplitude locked loop for generating excitation signals. The feedback outputs (shown as yellow tags) are summed on the right hand side of the output matrix so that they are sent to the test mases to excite the drum head modes. Also the rms information of a selected mode will be sent back to h1omc through an PCIe communication so that it can be used as a beacon alignment error signal. The contents of the purple block look like this:
As seen in the upper right, one can select which mode to use for the OMC alignment. The red blocks on the left hand side contain the function blocks as seen in the following screenshot.
The amplitude error signal is generated by a combination of an Abs block and lowpass filter. Then it is fed back to the output of the clock generator (which is based on the clipping technique as was done in eLIGO). The bandpass filter on the left allows one for selecting a mode out of the four modes. In addition, we placed an iWave block so that we can read out the frequency directly. A future expasion would be to use the output of the iWave block to generate the clock or sinusoidal excitation signal instead of the clipping-based one.
This change has been implemented yesterday (28826).
The Problem: The SEI configuration nodes have been in error since Friday at 2:58 local due to a bug in the WD decorators, and a bit of oversight by the one who coded that part (me). The regular SEI guardian nodes were tripped and then someone requested the config nodes to change, but these config nodes were not designed to be changed when everything was tripped. The decorator that caused the isse is just copied code and so it tried to jump to a state that didn't exist. Glad this was found before O2.
The Fix: removed all of the decorators that check on WD's, isolation, and damping of the regular nodes. Jim W and I talked and decided that it wasn't really necessary for the config nodes to even have to watch that, so lets lose them. Changing the config states while it is tripped or isolating was thought to maybe be an issue before, but doesnt seem to pose a problem anymore.
Status: Discussed smoke from nearby fires. DetChar F2F starts this morning. HAM6 vent plan for the week--most likely crack bolts on HAM6 on Tues, BUT we will only start this work when we confirm no dust/smoke issues in the LVEA.
Due to upcoming vent work, we did not go through status of the SEI & ISI.
Bake RGA at end station might start today (Kyle)
HAM6 ISI: should be isolated or atleast damped (see Hugh)
For Tuesday Maintenance: Timing work and PI model work were mentioned as primary tasks. PSL work will cover Mon/Tues per work permit.
For any tours, please remember to fill out a work permit & check with the operator as to whether it is OK (if there is active work in an open chamber we may want to limit tours at that time.)
Visitors This Week: DetChar people, visitors from China (Fred), KAGRA visitors for PCal (Kiwamu), Krishna/Micahel from UofWA (Hugh)
Attached are trends of the LVEA Dust Monitors.
On the 24hr trend, there was a little bit of dust in the LVEA between 8am-1pm, but in the cleanroom, were have been near zero for the last 24 hrs.
On the 4-day trend, the only dust in the HAM6 cleanroom was from technical cleaning on Friday.
Jeff is going to take some more readings outside.
Checked particle counts from outside and inside the OSB and in the LVEA. Summary: Outside air is currently around 330,000 for 0.3um particles. As one moves through the OSB towards the LVEA the counts drop as the building air filtration system does its job. Counts in the LVEA range from 1290 to 270 03.um particles. The attached spreadsheet has the complete readings for all sampled locations. Will continue to monitor as the fire continues to burn.
Second Mid-day check of air around the site shows air quality is not improving. Fires continue to burn or smolder and light wind is not helping clear the air. Posted are the 13:00 hours data. Outside and inside counts are up considerable. Particle counts inside the cleanrooms remain well within acceptable levels for in chamber work.
Terra, Evan, Stefan
With the spot move script from last alog we could reliably maximize the recycling gain. We reached 30 (as measured by LSC-PR_GAIN - Evan claims this is more like 35).
The instability in AS90 could be removed by manually aligning the SRM - but POP18 got worse when doing so.
Interestingly - the same move that fixes the recycling gain at 50W, has almost no impact on the recycling gain at 2W.
For reference, the last lock loss was at about 6:15 UTC on Aug 1st.
We had to adjust the soft loop gains to
ezca['ASC-DSOFT_P_GAIN'] = 0.5 # 3 killed it
ezca['ASC-DSOFT_Y_GAIN'] = 3 # oscillates at lower UGF when much lower
ezca['ASC-CSOFT_P_GAIN'] = 0.5 # designed differently
ezca['ASC-CSOFT_Y_GAIN'] = 3 # oscillates at lower UGF when much lower
Estimating the spot mosition move required to regain the recycling gain.
====================================================
Conclusion: The corner spot moved by about 8mm in pitch and yaw.
The move direction (to improve the recycling gain) in each arm is a soft translation of the beam axis towards the other arm (yaw), as well as up (pit).
====================================================
We used two methods to estimate the spot move on the ITM/BS/PR3.
A) using IM4 angle readback:
Since PR2 doesn't move, looking at how much IM4 moved allows us top simply project the move on PR3. The effecive lever arm (incl. the PRM and PR2 lens effects) is 151.4m.
To regain the best recycling gain we moved IM4 26.2urad in pit and 25.5urad in yaw. This corresponds to (note the factor of 2 for beam steering vs optic angle)
IM4 PIT projection on PR3: 7.9337mm
IM4 YAW projection on PR3: 7.7217mm
B) using the test mass oplevs:
The move recorded by the test mass oplevs (in urad) are (EX,EY,IX,IY) are:
PIT:
1.8700
1.6500
2.5000
2.0600
YAW:
2.7000
2.8200
3.3200
3.2600
Since it is always hard to get a clean soft that is not masked by residual hard, we project out any spurios hard move.
i) Without removing the hard:
ITM:-1.9858mm, ETM:12.091mm
ITM:0.91049mm, ETM:7.2637mm
ITM:2.4191mm, ETM:10.6978mm
ITM:6.315mm, ETM:6.329mm
ii) removing the hard by forcing the ETM and ITM spot move to be the same:
i.e. we force the spot move to be the same on ETM and ITM:
ITM:4.5198mm, ETM:4.5198mm
ITM:3.8466mm, ETM:3.8466mm
ITM:6.2452mm, ETM:6.2452mm
ITM:6.3215mm, ETM:6.3215mm
iii) forcing the spot to be zero on the ETM (that's how we think we tuned the SOFT loop sensors):
ITM:8.4743mm, ETM:0mm
ITM:7.1944mm, ETM:0mm
ITM:11.674mm, ETM:0mm
ITM:11.7903mm, ETM:0mm
The reality probably lies between ii) and iii)
FInally, note that the control signal recorded in alog 28764 can't be used because of all the radiation pressure torque effects.
Attached is a snapshot of the arm oplev motion.
State of H1: earthquake, unlocked, ISC_LOCK set to Down, IMC_LOCK set to Offline
Activities:
Since EQ:
SEI_CONF guardian is set to EARTH_QUAKE
Hugh and I opened the Blends MEDM and changed the SEI_CONF.
Should be returned to WINDY_NO_BRSY when locking resumes.
MEDM attached
Be very careful here! Even though the SEI_CONF says that it is in the correct state, it also has 10 notifications saying that 10 of its suborrdinate nodes are in ERROR. So it actually never got to its EARTHQUAKE state fully. If Guardian nodes are ever in error, someone who knows how, needs to fix them. In this particular case it is a bug that I will post an alog about soon.
The OMC alignment servos keep turning on, even though the OMC guardian is paused. I found that it gets turned on in engage_wfs_centering whenever we do any ASC since it's in a generate states function. So, I have commented out that line, but we must uncomment it when we have the OMC back and are ready to use it again. It is currently line 113 in ISC_GEN_STATES.
Maybe this should have a work permit to make sure this isn't forgotten; or at least some mechanism to undo the change in a timely manner.
Not sure when it happened, but looks like this has been restored to normal & uncommented (probably some time after the HAM6 work last week).
Making a note in Operator Sticky Notes wiki.
Cabling documentation of ISCT6.