Displaying reports 57581-57600 of 83039.Go to page Start 2876 2877 2878 2879 2880 2881 2882 2883 2884 End
Reports until 11:38, Monday 21 March 2016
H1 General
jeffrey.bartlett@LIGO.ORG - posted 11:38, Monday 21 March 2016 (26160)
LVEA is Laser Hazard
Sheila & Jeff Transitioned the LVEA to laser hazard.
H1 SEI
hugh.radkins@LIGO.ORG - posted 10:43, Monday 21 March 2016 - last comment - 20:30, Tuesday 22 March 2016(26158)
HAM ISI CPS--Look before & after switch to 71MHz timing

re aLog 26140

Here are snaps of 0-120hz spectra for HAMs 2 thru 6 with the reference traces from 13 March (before the switch last week,) and the current traces from this morning at 3am.  Not even really suttle differences so I'd say at least no harm done from the switch to the common timing source.

Images attached to this report
Comments related to this report
hugh.radkins@LIGO.ORG - 12:29, Monday 21 March 2016 (26162)SYS

Here are photos of the HAM CPS Satellite racks which have been mounted onto the BoxBeam Mount.  This is why the HAM switch over was much longer than the BSCs.  The single port Power Regulator board was swapped for a dual on the primary (CPS1) rack.  All grounding was made more robust for both the primary green ground wire and the probe cable shield (woven copper jacket.)  Mounting the racks on the Box Mount and rerouting cables such that the racks could be accessed but are more out of the way or could be moved when needed for safety, such as slinging heavy wrenches around when removing a door.

The photos are in order, HAM2 Rack1, Rack2, HAM3 Rack1....HAM6 Rack2.

Images attached to this comment
jeffrey.kissel@LIGO.ORG - 20:30, Tuesday 22 March 2016 (26204)DetChar
@DetChar: Can you watch HAM3 for the next few days, and see if this has had any effect on 0.6 Hz?
H1 CDS (CDS, PSL, TCS)
patrick.thomas@LIGO.ORG - posted 10:42, Monday 21 March 2016 - last comment - 11:02, Monday 21 March 2016(26157)
rotation stage beckhoff chassis powercycled
Kiwamu, Patrick

Kiwamu said that the TCS X power was changing for the same angle requested and readback by the rotation stage. We powercycled the rotation stage chassis in the CER and did a search for home for the TCSX, TCSY and PSL rotation stages that it controls. Kiwamu says it is now workable, but from what he showed me it still appears to be giving significantly different powers for the same angle.
Comments related to this report
kiwamu.izumi@LIGO.ORG - 11:02, Monday 21 March 2016 (26159)

Here is a screenshot showing the issue. I requested the same angle several times which moved the rotation stage to different angles and also power changed by roughly +/- 50 mW.

Images attached to this comment
H1 AOS (AOS, SEI, SUS)
travis.sadecki@LIGO.ORG - posted 10:36, Monday 21 March 2016 - last comment - 15:43, Monday 21 March 2016(26156)
Optical Lever 7 Day Trends

Attached are 7 day pitch, yaw, and sum trends for all active H1 optical levers.

Images attached to this report
Comments related to this report
jenne.driggers@LIGO.ORG - 15:13, Monday 21 March 2016 (26165)

Note that the SR3 oplev sum is ~0, even though it's pretty well aligned.  No good.

jason.oberling@LIGO.ORG - 15:43, Monday 21 March 2016 (26168)

That would be because the oplev is off.  It had to be moved for the grouting last week and in the process was unplugged from its power supply.  I haven't had a chance to plug it back in yet.

Due to the grouting, none of the oplevs (except the BS, no grouting was done to it) are good alignment references right now.  Once the post-grouting optic alignment work is complete I will realign the optical levers.

H1 General
jeffrey.bartlett@LIGO.ORG - posted 10:13, Monday 21 March 2016 (26155)
08:30 Meeting Minutes
   The morning meeting days will change to 08:30 on Monday, Wednesday, and Friday. Monday's meeting will address review of weekend activities and work permits for Tuesday's maintenance. The Wednesday's will be a planning session. The Friday meeting will focus on FRS topics and weekend work.
  
   There is grouting still going on in the HAM2 area and at End-Y. Should be finished today.

   Vacuum is still pumping down in LVEA. Will be on Turbo pumps and annulus pumping for several days to weeks.
   
   Higher power operation of the PSL is planned for the week 04/04. 

   Tuesday Maintenance:
Reboot End-X vacuum computers for Beckhoff. 
POPX and WFS
BRS at End-Y
PI Boot   
H1 PSL (PSL)
peter.king@LIGO.ORG - posted 08:50, Monday 21 March 2016 - last comment - 16:41, Monday 21 March 2016(26154)
PSL Trends
Attached are 45 day trends of the various PSL power monitors.

The degradation of the power matches the decline of the front
end laser pump diodes.
Images attached to this report
Comments related to this report
edmond.merilh@LIGO.ORG - 16:41, Monday 21 March 2016 (26174)
I'm curious as to why the trend lines are showing a "tailing up" of power in 3 of the 4 graphs? Was there another adjustment made to the diode currents?
Images attached to this comment
H1 General
jeffrey.bartlett@LIGO.ORG - posted 08:11, Monday 21 March 2016 (26153)
Ops Day Shift Transition
Transition Summary:

Title:  03/21/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT)
State of H1: IFO unlocked. Planned Engineering
Commissioning: 
Outgoing Operator: N/A
 
   Environmental conditions are favorable for relocking. Will see what the plans for the day are at the 08:30 meeting.  
H1 ISC
stefan.ballmer@LIGO.ORG - posted 15:11, Sunday 20 March 2016 (26152)
Current PRC2_Y loop not stable when IFO is cold

After realigning the IFO, I lost lock a couple of times during ASC_PART1, due to PRC2_Y engaging.

Going slow the next time, it first looked like the IFO was more happy with the PRC2_Y input matrix of RF9I=0, RF45I=-1 .

But after about 15min the the input matrix from the guardian script - RF9I=0.7, RF45I=-1 , seemed to work just fine.

 

In the attached plot, notice that the RMS in all signals shrank significantly over about 15min.

Images attached to this report
LHO VE
john.worden@LIGO.ORG - posted 10:59, Sunday 20 March 2016 (26151)
Diagonal Pumpdown

So far so good. 

Images attached to this report
H1 ISC (ISC)
stefan.ballmer@LIGO.ORG - posted 22:46, Saturday 19 March 2016 (26150)
More post-grouting alignment work

Hang, Stefan

We went through the whole initial alignment today. The hickups along the way were:

- Because the green cameras are off-line, we turned off the ITM green camera centering loops: all four  H1:ALS-[X|Y]_CAM_ITM_[PIT|YAW]_ERR OUTPUT OFF

- This meant that the best reference on the ITM was the baffle-pointing from the TMS - we found arm alignments that correspond to those TMS pointing positions.

- Input alingment and PRM alignment were simple.

- Next we had trouble locking both MICH_DARK and the SRY cavity - we tracked it down to large electronic offsets on the AS 45 diode. We set the dark offsets on all LSC and ASC RF photodiodes.

- Then ALS DIFF wouldn't lock. Also took a while to track it down to an ESD that was switched off.

- Next we tried to lock DRMI, but ALS got kicked during locking transients. We first suspected the BS OPLEVs, but they were fine. Turns out the SRCL FF was left on - so SCRL kicked the ITMs. We updated the down script to turn FF off.

- After all that the alignment had drifted enought than we needed to realign the corner, which then was enough to lock DRMI.

- Next DRMI always lost lock on ASC engaging. Turns out the input matrix element for MICH_P was not properly set up (two lines of code were commented out)

- With that we reached DRMI_LOCKED, and continued all the way to DARM_OFFSET.

- Finally ENGAGE_ASC_PART1 failed, due to a run away PR3 YAW loop.

 

That's there we left it for the day.

Images attached to this report
LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 13:03, Saturday 19 March 2016 (26149)
Manually over-filled CP3 at 19:50 utc

1/2 open LLCV bypass valve, and the exhaust bypass valve fully open.

Flow was noted after 1 minute and 10 seconds, closed LLCV valve, and 3 minutes later the exhaust bypass valve was closed.

Next over-fill on Monday, March 21st before 23:00 utc.

H1 General
jeffrey.bartlett@LIGO.ORG - posted 19:17, Friday 18 March 2016 (26148)
Ops Evening Shift Summary

Activity Log: All Times in UTC (PT)

22:30 (15:30) Take over from Ed
22:51 (15:51) ITMX & ETMX ISI and SUS TMSX WDs tripped due to a mag 5.2 EQ near Vancouver Island, CA.
23:44 (16:44) Started working on initial alignment. 
01:50 (18:50) Several ITMX ISI WD trips due to 6.2 EQ off Atka Alaska. 
02:10 (19:10) Commissioners have left for the night.  

End of Shift Summary:

Title: 03/18/2016, Evening Shift 23:00 – 07:00 (16:00 – 00:00) All times in UTC (PT)
Support: N/A               
Incoming Operator: N/A

Shift Detail Summary:  Working with Stefan & Hang to relock the IFO. Had the TMS(s) realigned and the X-Arm green. While working on Y-Arm green, took a mag 6.2 EQ off Atka Alaska, which rang everything back up, tripping the ITMY ISI WD several times. Decided to call it a night and try again tomorrow.  
H1 ISC
stefan.ballmer@LIGO.ORG - posted 19:00, Friday 18 March 2016 (26147)
Green am alignment

Hang, Jeff, Stefan

After all the grouting we had to do a rough manual arm alignment to see the transmitted beam.

After that we ran the baffle alignment script:

/opt/rtcds/userapps/release/asc/h1/scripts/ditherAlign.py

We also had to adjust H1:AOS-xxxx_BAFFLEPD_x_NOMINAL for thje script to catch the baffles (for some reason they were changed after O1).

That all went fine until the next double earthquake hit - Atka, Ak, Magtnitude 5.0 & 6.2. The attached alignment should at bleast let the green arms flash.

Images attached to this report
LHO General
gerardo.moreno@LIGO.ORG - posted 16:55, Friday 18 March 2016 (26146)
Power Loss of Y-End Station Instrument Air Compressor

Richard M, Filiberto C, Peter K, Ed M, Gerardo M.

Lost power to the Y-End station Instrument air compressor.

Initial inspection revealed the circuit breaker had tripped.

Found main lead wires shorted against a stud.

Wires were replaced and power restored to Y-End station Instrument air compressor.

CP7 went into alarm due to the lack of air, but is now recuperating, it reached a low of 81.3% full, as of now is at 86.2% and green.

Images attached to this report
H1 CDS (DAQ)
david.barker@LIGO.ORG - posted 15:46, Friday 18 March 2016 (26145)
new h1ngn model installed, DAQ restarted

Late entry from Thursday, I installed the new Newtonian Noise model on h1oaf0, it is called h1ngn. At the same time Hugh and I restarted the BSC ISI models (except for itmy which had been done previously). We did a single DAQ restart to sync these changes.

The DAQ restarted with no problems, but later in the evening h1fw0 went unstable and restarted 7 times between 20:42 and 23:42 PDT and then became stable again.

LHO VE
chandra.romel@LIGO.ORG - posted 15:44, Friday 18 March 2016 (26144)
gate valves open & current vacuum status
GV 1,2,5,7 are now open. GV 5&7 opened with 40 psi air.

Gate annuli valves were opened and closed again. Values of the annulus IPs:

GV-1: 5 mA
GV-2: 7 mA
GV-5: 2 mA
GV-7: 2 mA

Turbo pumping stations' 10" valve closed on X & Y and shut down completely. IPs are open to spools.

Turbo on diagonal is backed by local scroll only. QDP80s are OFF. Kolbelco is OFF. Chilled water line is still open in mech. room for diagonal turbo pump.

Current pressures:

X: 2.6e-8 Torr
Y: 2.5e-8 Torr
Diag: 6.0e-6 Torr
H1 SEI (SUS)
hugh.radkins@LIGO.ORG - posted 15:31, Friday 18 March 2016 (26143)
SVN Commits related to the SUSPOINT Changes & STS2 Bio medm control

hugh.radkins@opsws1:models 0$ pwd
/opt/rtcds/userapps/release/isi/common/models
hugh.radkins@opsws1:models 0$ svn commit -m "Added epics fields for binary STS2 control"
Sending        models/isi2stagemaster.mdl
Transmitting file data .
Committed revision 12890.
 

hugh.radkins@opsws1:models 0$ pwd
/opt/rtcds/userapps/release/isi/h1/models
hugh.radkins@opsws1:models 0$ svn commit -m "Added SUSPOINT lib parts for SUS Euler Calc"
Sending        models/h1isibs.mdl
Sending        models/h1isietmx.mdl
Sending        models/h1isietmy.mdl
Sending        models/h1isiitmx.mdl
Sending        models/h1isiitmy.mdl
Transmitting file data .....
Committed revision 12891.
 

Edited & committed earlier the H1_isietmx_overview_macro.txt files adding the OPTIC1=ETMX, OPTIC2=TMSX elements for medm creation.  These are in:

/opt/rtcds/userapps/release/isi/h1/medm/bscisi

hugh.radkins@opsws1:bscisi 0$ pwd
/opt/rtcds/userapps/release/isi/common/medm/bscisi
hugh.radkins@opsws1:bscisi 0$ svn commit -m "Edit BIO medm for STS2 CONTROL and edited and added medms to get the SUSPOINT Euler Calcs"
Sending        bscisi/ISI_CUST_CHAMBER_BIO.adl
Adding         bscisi/ISI_CUST_CHAMBER_CAL_CART_ALL.adl
Sending        bscisi/ISI_CUST_CHAMBER_OVERVIEW.adl
Deleting       bscisi/ISI_CUST_CHAMBER_ST2_SUSMON_GS132EUL.adl
Deleting       bscisi/ISI_CUST_CHAMBER_ST2_SUSMON_SUP2EUL.adl
Adding         bscisi/ISI_CUST_CHAMBER_SUSPOINT_BS_CALC.adl
Adding         bscisi/ISI_CUST_CHAMBER_SUSPOINT_ETMX_CALC.adl
Adding         bscisi/ISI_CUST_CHAMBER_SUSPOINT_ETMY_CALC.adl
Adding         bscisi/ISI_CUST_CHAMBER_SUSPOINT_ITMX_CALC.adl
Adding         bscisi/ISI_CUST_CHAMBER_SUSPOINT_ITMY_CALC.adl
Adding         bscisi/ISI_CUST_CHAMBER_SUSPOINT_OPTIC_CART2EUL.adl
Sending        bscisi/SEI_SAT_OVERVIEW_test_button.adl
Transmitting file data ..........
Committed revision 12892.
 

hugh.radkins@opsws1:burtfiles 0$ pwd
/opt/rtcds/userapps/release/isi/h1/burtfiles
hugh.radkins@opsws1:burtfiles 0$ svn commit -m "Edit BIO medm for STS2 CONTROL and SUSPOINT for Euler Calcs"
Sending        burtfiles/h1isibs_down.snap
Sending        burtfiles/h1isibs_safe.snap
Sending        burtfiles/h1isietmx_OBSERVE.snap
Sending        burtfiles/h1isietmx_safe.snap
Sending        burtfiles/h1isietmy_OBSERVE.snap
Sending        burtfiles/h1isietmy_safe.snap
Sending        burtfiles/h1isiham4_OBSERVE.snap
Sending        burtfiles/h1isiham4_safe.snap
Sending        burtfiles/h1isiham5_OBSERVE.snap
Sending        burtfiles/h1isiham5_safe.snap
Sending        burtfiles/h1isiitmx_OBSERVE.snap
Sending        burtfiles/h1isiitmx_safe.snap
Sending        burtfiles/h1isiitmy_OBSERVE.snap
Sending        burtfiles/h1isiitmy_safe.snap
Transmitting file data ..............
Committed revision 12893.
 

hugh.radkins@opsws1:filterfiles 0$ pwd
/opt/rtcds/userapps/release/isi/h1/filterfiles
hugh.radkins@opsws1:filterfiles 0$ svn commit -m "Added to nm filters to SUSPOINT Cal"
Sending        filterfiles/H1ISIBS.txt
Sending        filterfiles/H1ISIETMX.txt
Sending        filterfiles/H1ISIETMY.txt
Sending        filterfiles/H1ISIHAM2.txt
Sending        filterfiles/H1ISIHAM4.txt
Sending        filterfiles/H1ISIHAM5.txt
Sending        filterfiles/H1ISIITMX.txt
Sending        filterfiles/H1ISIITMY.txt
Transmitting file data ........
Committed revision 12894.
 

H1 AOS
edmond.merilh@LIGO.ORG - posted 15:03, Friday 18 March 2016 - last comment - 15:22, Friday 18 March 2016(26141)
Shift Summary - Day
TITLE: 03/18 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Jeff
SHIFT SUMMARY:'
LOG:
14:27 Peter to EY to transition to LASER safe
15:15 Jim doin comparitive TFs on HAMS 4/5.
15:23 Jeff to EY
16:03 Jeff B back from end stations
16:10 Gerardo and Chandra into LVEA to leak check X and Y manifold
16:18 Fil. Peter Manny out to EX
16:30 Reibolt grouting at EY
18:57 Peter et al back from EX
19:14 Dave Barker into the LVEA
19:20 John and Chandra going into LVEA to open gate valves
19:30 Karen and Christina at EX
20:42 Karen and Christina finished at EX and calling it a day.
21:30 Richard back on site to investigate instrument air issue
21:59 All corner station gate valves are open
21:59 CP7 is yellow and reporting 83.8 John Worden informed
22:24 Richard and Fil back from EY
Comments related to this report
edmond.merilh@LIGO.ORG - 15:22, Friday 18 March 2016 (26142)
Jeff in the control room. He told me he could sail the ship if I wanted to start my weekend a little early.
Displaying reports 57581-57600 of 83039.Go to page Start 2876 2877 2878 2879 2880 2881 2882 2883 2884 End