Displaying reports 61061-61080 of 86461.Go to page Start 3050 3051 3052 3053 3054 3055 3056 3057 3058 End
Reports until 11:48, Wednesday 16 March 2016
LHO VE
chandra.romel@LIGO.ORG - posted 11:48, Wednesday 16 March 2016 - last comment - 09:55, Thursday 17 March 2016(26101)
Pumping down diagonal
John, Gerardo, Chandra

Rough pump down on diagonal. We borrowed the control cable from Ymid turbo pump station to run QDP80 in remote mode. 

Current pressure on BCS4: 383 Torr
Comments related to this report
chandra.romel@LIGO.ORG - 09:55, Thursday 17 March 2016 (26111)
Valved off QDP80 overnight and opened back up at 15:53 UTC on 3/17.
H1 SEI
hugh.radkins@LIGO.ORG - posted 11:24, Wednesday 16 March 2016 (26100)
WHAM4 ISI CPS switched to 71MHz common sync--operating normally

No issues outside of the ridiculous cable nests in the area.

I spent time staighting up the Optical Lever cabling where grouting will happen Thursday or Friday.

H1 General
edmond.merilh@LIGO.ORG - posted 11:15, Wednesday 16 March 2016 (26099)
PSL FE Watchdog reset
15:30 UTC FAMIS 3589
H1 DetChar (DetChar, SUS)
borja.sorazu@LIGO.ORG - posted 09:55, Wednesday 16 March 2016 (26098)
Violin mode Q R&D

(Borja Sorazu, Alan Cumming, Giles Hammond)

This entry is an informative summary of some of the work we are doing/planning to do at Glasgow related to the monolithic suspensions and their violin modes R&D:

1) Identify actual fibre profiles of the installed fibres with actual masses.

2) Model aLIGO 'real' final stage suspension (with real fibre profiles) in ANSYS, to learn about the violin frequencies distribution and see how that can inform on identifying the higher order harmonics and their associated masses. Notice that only fundamental and fist harmonics are partially identified with actual test masses.

3) Use the model to estimate D factor for first 5 or 6 harmonics, and the energy distribution along the fibre length taking into account full fibre shape including necks and hopefully welds.

4) Use these energy ratios to weight the material loss factor equations. In this case, the material loss factor equations are used independently for each segment along the length of the fibre (therefore taking into account correctly the full fibre shape), and summed together and weighted by the energy ratio of each segment of the fibre, to give the full material loss of the fibre. Most probably we are talking about 500-1000 segments or so along each fibre's length.

5) The material loss factor equations we have used previously have used conservative estimates of parameters such as surface and weld loss, and subsequent measurements here in Glasgow have shown that the losses could be better than this, so we can give a range of possible losses (and hence noise spectra) using these and the FEA analysis, for the lower glass stage of the suspension, and compare these values with the measured Q's of the fundamental and higher harmonics of the violin modes. This information may help into understand if the low frequency noise has any thermal noise source.

H1 General
edmond.merilh@LIGO.ORG - posted 09:27, Wednesday 16 March 2016 (26097)
PSL Light Pipe Shuttered
16:20 Filiberto has locked and tagged the PSL Light Pipe
H1 General (PSL)
edmond.merilh@LIGO.ORG - posted 08:57, Wednesday 16 March 2016 (26096)
PSL Weekly status and trends
Laser Status:
SysStat is good
Front End power is 31.72W (should be around 30 W)
Frontend Watch is GREEN
HPO Watch is RED

PMC:
It has been locked 1.0 days, 19.0 hr 34.0 minutes (should be days/weeks)
Reflected power is 3.035Watts and PowerSum = 24.92Watts.

FSS:
It has been locked for 1.0 days 0.0 h and 4.0 min (should be days/weeks)
TPD[V] = 1.501V (min 0.9V)

ISS:
The diffracted power is around 9.648% (should be 5-9%)
Last saturation event was 0.0 days 16.0 hours and 33.0 minutes ago (should be days/weeks)

Please refer further, in depth, analysis of PSL trends to Jason, Peter or Rick.
Images attached to this report
H1 General
bubba.gateley@LIGO.ORG - posted 08:53, Wednesday 16 March 2016 (26095)
Grouting in the LVEA
Grouting of the remainder of the HEPI piers, transmitter and receiver pylons in the LVEA began on Monday morning by Reiboldt and Associates. The grouting has consumed more product than was originally expected and we have used up all that we had. I have ordered more grout and that should be onsite today, meanwhile, the grout crew will be out today. 

Progress to date includes, all of the HEPI piers on HAM 5 & 6, the large carbon fiber leaner on the south side of HAM 4, and the large stainless steel leaner pylon on X-Arm. Remaining items to grout in the LVEA include, 5 of the small transmitter pylons, and 1 each of the large carbon fiber and stainless steel leaner pylon. The plan is to finish these items in the LVEA tomorrow and move to the End stations afterwards.
H1 General
edmond.merilh@LIGO.ORG - posted 08:15, Wednesday 16 March 2016 (26094)
Shift Summary - Day Transition
TITLE: 03/16 day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind Avg: 2 mph
    Primary useism: 0.03 μm/s
    Secondary useism: 0.26 μm/s 
QUICK SUMMARY:LVEA is LASER SAFE
LHO FMCS
bubba.gateley@LIGO.ORG - posted 07:06, Wednesday 16 March 2016 (26093)
Bearing Change on Supply Fan 5
Yesterday afternoon I began the disassembly of Supply Fan 5 to investigate a very noisy bearing. I informed the control room that I was going to increase the flow on SF-6 from 
~6200 CFM to ~ 8500 CFM to compensate for the reduced air flow of one fan being down. I will continue with disassembly today and if all parts are readily available, I hope to have the fan back up and running by the end of this week. 
LHO VE
chandra.romel@LIGO.ORG - posted 18:57, Tuesday 15 March 2016 (26092)
Y beam manifold vacuum
John, Chandra

We isolated the beam manifold from QDP80 and are now backing turbo with scroll only.
Control cable switched to scroll box. 
Safety valve set point on both X and Y pump stations is 5e-2 Torr.

X: 5.94e-7 Torr
Y: 1.82e-6 Torr
LHO VE
chandra.romel@LIGO.ORG - posted 17:47, Tuesday 15 March 2016 (26091)
started turbo on Y beam manifold
John, Chandra

Started turbo on Y beam manifold with inlet pressure at 1 Torr and pump water cooling ON. 

X: 8.0e-7 Torr
Y: 4.9e-1 Torr
LHO VE
chandra.romel@LIGO.ORG - posted 16:46, Tuesday 15 March 2016 (26090)
Annulus pressures at GV-5
John, Gerardo, Chandra

Yesterday Kyle and Gerardo noticed the current on annulus IP on GV-5 was high (off scale). Today we noticed it was at 2 mA. We tapped on the vacuum piping around the pump and the current rose. Then we opened the valve to the annulus of GV-5's gate. The current rose to 6 mA and then quickly fell to 2 mA. Closed valve again to isolate GV-5 gate annulus. Now the IP is reading 1 mA.
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:41, Tuesday 15 March 2016 (26089)
Ops Evening Shift
 
Activity Log: All Times in UTC (PT)

23:00 (16:00) Take over from Ed


End of Shift Summary:

03/15/2016, Evening Shift 23:00 – 07:00 (16:00 – 00:00) All times in UTC (PT)

Support: N/A               
 
Incoming Operator: N/A

Shift Detail Summary:  Some commissioning work going on; does not need Ops support.  


LHO VE
chandra.romel@LIGO.ORG - posted 16:38, Tuesday 15 March 2016 (26088)
backing turbo with scroll Xarm
John, Chandra

Now backing turbo pump on Xarm spool with scroll pump. 
Closed QDP80 valve on Xarm spool pump station. 
Closed vent/purge valves at both X & Y spools.
Closed valves on Inficon gauges (PT-170 and PT-180).

Pressure on PT-170 reading 1.56e-6 Torr.
H1 TCS (ISC, TCS)
aidan.brooks@LIGO.ORG - posted 16:18, Tuesday 15 March 2016 (26087)
Simple arm power channel names - XARM and YARM

[Aidan, Cao]

The TCS SIM model has been updated. Further details soon, but now there are calibrated channels for the arm powers. The values are in Watts. The names are:

H1:TCS-SIM_XARM_POWER

H1:TCS-SIM_YARM_POWER

H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:11, Tuesday 15 March 2016 (26086)
Ops Everning Shift Transition
             Transition Summary:
Evening Shift 23:00 – 07:00 (16:00 – 00:00) All times in UTC (PT)
	
State of H1: IFO unlocked. Vacuum system work and grouting in the LVEA

Commissioning: 
     

Outgoing Operator: Ed
H1 General
edmond.merilh@LIGO.ORG - posted 15:54, Tuesday 15 March 2016 (26085)
Shift Summary - Day
TITLE: 03/15 day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Jeff
SHIFT SUMMARY:'Maintenance
LOG:
14:15 Chris S; X-Arm beam tube sealing; 300 yards from end station. (morning work)
15:00 Grouting in LVEA
15:48 Hugh out to LVEA work around HAM2. Jim handling ISI damping.
16:30 Fil into LVEA to do WP5778
16:27 Bubba going to MX and EX with Cintas people.
16:45 NORCO on site with LN2 load for EX
17:00 Fil called from LVEA. Key Lock is intslled on TCS Y and by Kiwamu's instruction, ENABLED. FIl heading to do the same for TCS X.
17:15 Water Delivery
17:29 Second LN2 truck on site
17:43 Fil back from LVEA. TCS Y Key Lock done. Heading back out to execute WP5735
18:19 Joe, Sheila and Hang out to LVEA
18:40 Joe out of the LVEA
19:05 Truck here to pick up rental equipment
19:00 Fil out of LVEA for lunch
20:53 Carlos to reboot all workstations at end stations
21:18 Joe back into the LVEA
21:30 Fil and Manny out of LVEA
21:40 Joe out
21:55 Jeff to both end stations
22:18 Gerardo to MY/CP3 for manual fill
22:24 Fil out to LVEA to retrieve cables
22:30 Bubba out of fan room headed to EX
22:35 Gerardo is back from MY/CP3

H1 SEI
hugh.radkins@LIGO.ORG - posted 15:50, Tuesday 15 March 2016 (26084)
WHAMs 2 & 3 SEI ISI CPS switched 71 MHz 'House' Sync

Other than knuckle bustin head bangin pain, not too bad a job.  Did find the data connector for the '3rd' corner satellite box seemed extra loose on HAM3.  It has a gender changer as well so there was a lot of strain & wobble present.  Fil saw that there was no fasteners tying the header to the board so it was just held with the pins and solder.  He managed to get some screws in without too much disassembly--certainly better now.  Say a hail-mary against 0.6hz.

LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 15:33, Tuesday 15 March 2016 (26083)
Manually over-filled CP3 at 22:24 utc

1/2 open LLCV bypass valve, and the exhaust bypass valve fully open.

Flow was noted after 2 minutes, closed LLCV valve, and 3 minutes later the exhaust bypass valve was closed.

Next over-fill on Thursday, March 17th before 23:00 utc.

LHO VE
john.worden@LIGO.ORG - posted 15:30, Tuesday 15 March 2016 (26082)
X Beam Manifold pumpdown

Chandra, John

We transitioned to Turbo pump on the X Beam Manifold at 15:00 local time.Pressure is currently 3 e-1 torr.

The Y Beam Manifold is currently at ~5 torr.

Displaying reports 61061-61080 of 86461.Go to page Start 3050 3051 3052 3053 3054 3055 3056 3057 3058 End