Displaying reports 70141-70160 of 83266.Go to page Start 3504 3505 3506 3507 3508 3509 3510 3511 3512 End
Reports until 22:00, Tuesday 19 August 2014
H1 DAQ (CDS)
david.barker@LIGO.ORG - posted 22:00, Tuesday 19 August 2014 (13506)
DAQ back up and running after 2 hours downtime

The DAQ is back up after it was shutdown for a reconfiguration restart at 19:32 PDT. For some reason the monit autostarter failed to restart daqd on h1dc0. This was further compounded by the maintenance changes made this morning which left duplicate slow channels in the configuration. So after a few false restarts I was able to get the system stable.

Here is the data gap on both frame writers.

-rw-r--r-- 1 controls controls 750947268 Aug 19 19:32 H-H1_R-1092537088-64.gwf

-rw-r--r-- 1 controls controls 753765993 Aug 19 21:49 H-H1_R-1092545280-64.gwf

H1 SEI
jeffrey.kissel@LIGO.ORG - posted 21:13, Tuesday 19 August 2014 (13505)
HEPI B&K Hammering -- 8 [Hz] motion: Final Answer... It's the Crossbeam Foot!
J. Kissel, T. MacDonald

We measured a final exploration of ETMY HEPI today to identify the exact mode shape of the 8 [Hz] resonance, given that there were still some ambiguities in yesterdays results. Peppering the piers, boots, housings, crossbeams, and support tubes with hit points, we've nailed it down. The bending point is the crossbeam foot (D020195, see green highlighted part in 2014-08-19_HEPIBoot.pdf attachment) -- the connection point of the suspended stage with the Euler springs. Inward of this foot, everything else is moving in concert -- the crossbeam, the support tubes, and everything else inside the chamber.

We took two sets of measurements, one involving tons of points on one pair of piers and crossbeam (that's where we identified the foot as the problem, see HitPattern.pdf), and the other with all four cross beams involved focused more on the crossbeam foot -- as many data points into which we could squeeze the hammer.

The "single_side.avi" is the first measurment with only one crossbeam system, and the four "*_both.avi" show the measurement with the whole system.

Check out all the visual aides, and be sure to loop your video, since the B&K software doesn't export more than once cycle.
Non-image files attached to this report
H1 ISC
koji.arai@LIGO.ORG - posted 20:17, Tuesday 19 August 2014 (13502)
HAM6 alignment

[Alexa Dan Koji]

- We aligned the OM1 transmission path again. The AS_C QPD alignment was reestablished. We can use this QPD as the alignment reference.

- The alignment of the fast shutter was revisited and now we can accommodate the beam without the extra legs. We removed the 20mm leg extentions and the placed the beam dump at the designated place.

- OM2 and OM3 were moved so that we can see the spots on the QPDs.

- We think the beams are on the diodes. In fact the diode SUM outputs are responding to the beam.
  However these QPD outputs do not give us linear response to the input alignment.

- We checked the electronics outside of the chamber including the cables from the feedthrough.
They don't show any misbehavior. (Basically we swapped the electronics between OMC QPDs and AS_C.

- We'll investigate the QPD functionality tomorrow.

- We'll want to shake the PZT of the OMC sometime soon.

H1 SEI (DetChar)
krishna.venkateswara@LIGO.ORG - posted 19:54, Tuesday 19 August 2014 (13501)
H1 EX BRS Installation, Day 12: Pump issue sorted and plot from Monday night
J. Kissel, K. Venkateswara, K. Ryan

We finally figured out the issue behind the increasing current in the ion pump. In the morning, the current was near 1.5 mA, so we decided to do a leak check. There was a small leak through a flange but not enough to account for the ion pump behaviour. I fixed it by tightening the flange further and found no other leaks. Kyle then pointed out that we had the wrong polarity setting on the controller. The Starcell ion pump needed negative voltage not positive. With that sorted out, we restarted the pump. The current increased to ~10 mA, but has since been going down steadily. After ~1.5 hrs of pumping, it was at 0.49 mA at 7 PM. With the reversed polarity, we were probably just observing the leakage current, which may have been proportional to the pressure.

I've also attached an ASD plot of some data from last night, when the ground was fairly quiet. The red curve shows the BRS/tiltmeter output while the blue shows the T240 (incorrectly labelled as STS) converted to angle by multiplying by (2pif)^2/g. The coherence between the sensors is also shown.
Non-image files attached to this report
H1 CDS (DAQ, DCS, SYS)
jeffrey.kissel@LIGO.ORG - posted 19:41, Tuesday 19 August 2014 (13500)
Attempted to restart frame builder, DAQ no hosed
J. Kissel

Was looking to restart the frame builder now that ISC folks no longer need it (for ~5 minutes while the h1dc0 reboots), telnet'ed in, 
]$ telnet h1cd0 8087
and restarted it,
daqd> shutdown
and unlike what happens normally, everything with the data concentrator stayed white, and all front ends DAQ lights went red, and neither came back.

This is what happens when you get greedy, and assume the CDS system will behave as you expect it to -- especially if you're me!

I've left a voicemail with Dave.
H1 IOO
kiwamu.izumi@LIGO.ORG - posted 16:50, Tuesday 19 August 2014 (13496)
IOT2R table is back in position

Keita, Kiwamu (WorkPermit 4806)

We placed the IOT2R table back in place (i.e. East side of HAM2). We have re-installed the light pipe that connects the lower left viewport of HAM2's east side to the table. The lexan guard of this particular viewport was then removed.

There was some mess on the optical table of IOT2R because of the PRC length measurement. We need to clean them up at some point. Also the GigEs on the table need the interior ethernet cables and feedthrough patch panels. They probably will be useful. The attached is a picture of the IOT2R after we placed it.

Images attached to this report
H1 AOS
david.barker@LIGO.ORG - posted 16:49, Tuesday 19 August 2014 - last comment - 17:07, Tuesday 19 August 2014(13497)
Timing errors on h1seib2 (BS) and h1seih45

Jim and Dave.

at 15:57 PDT both h1seib2 and h1seih45 suffered a timing fault. The IOP IRIG-B timing channel showed a number of 336685 and 336687 respectively. All user models on these front ends stopped running. The IOP SWWD tripped, zeroing the DAC output voltages.

we were able to ssh onto the machines, and verify the IO Chassis were visible.

After getting permission from the HAM6 commissioning teams, we rebooted the two front ends using the sequence:

  1. ssh onto the front end and remove them from the Dolphin network
  2. power down the computers using the front panel power button
  3. power up the computers using the front panel power button

Both computers rebooted and restarted all  their models with no timing errors. Commissioning time constraints due to staff at/in ham6 did not facilitate any lengthy diagnostics of the broken system.

Comments related to this report
david.barker@LIGO.ORG - 17:07, Tuesday 19 August 2014 (13498)

Arnaud, Dave

we just noticed that the safe.snap link from the target area to the userapps area for the ISI systems: ITMX, ITMY and BS were missing. This meant the settings for h1isibs were not restored after the reboot of h1seib2. We put the symbolic links back into the target directories and manually burt restored h1isibs. Why the links disappeared is a mystery.

H1 IOO
kiwamu.izumi@LIGO.ORG - posted 16:24, Tuesday 19 August 2014 - last comment - 17:38, Tuesday 19 August 2014(13495)
Revisit of power budget in IO-chain

Keita, Daniel, Kiwamu

In response to the too-low-power at HAM6 (see alog 13472), we revisited the IM4 trans power in order to make sure that there is no large loss in the input optics chain.

As a result, we confirmed that the incident power on IM4 is about 1.4 W. This corresponds to a throughput of PSL-IMC-Farday chain of 88%. This is consistent with the number that Giacomo and Paul gave us (see for exmaple, alog 9954). So we conclude that the IO chain is healthy.

 

==== (some details) ====

We measured the IM4 trans beam at the east side of HAM2. The power was measured to be 220 uW using a Ophir Vega without the filter on it.

According to the IO documents (E1300756 and E1300160), the relevant optics have the following properties:

Using these information together with the measured IM4 trans power, we estimated the power incident on IM4,

Power incident on IM4 = 220 uW / T_IM4 / T_RH4 / R_LH1 = 1.432 W

At the time of the measurement, the PSL power was at 1.620 W according to PSL_PERISCOPE_A_DC.

Therefore the throughput of the PSL-IMC-Faraday chain is

throughput = 1.432 / 1.620 = 88.4 %

Comments related to this report
daniel.hoak@LIGO.ORG - 17:38, Tuesday 19 August 2014 (13499)

In HAM6, we measured 3.6mW with the Ophir Vega power meter, with the filter off.  (With the filter on, we measured 3.8mW.)  The configuration during this measurement was ITMX aligned, ITMY misaligned, 1.620 watts into the IMC.

This is 81% of Daniel's prediction of 4.45mW in HAM6 -- note, the difference between yesterday and today is in the power meter that was used.  Kiwamu compared the Vega meter with the Ophir Nova we used yesterday, and found that the Nova, with the filter on, gave bogus measurements.  So, yesterday's measurement is not valid.

H1 General
andres.ramirez@LIGO.ORG - posted 16:00, Tuesday 19 August 2014 (13494)
OPs Shift Summary
8:15-8:30 Morning Meeting
8:33-Heading to End Y for B-K hammering work - T. MacDonald
8:35-Crystal chiller has been refilled (added 250 ml of water to bring the level up to maximum) – Operator
9:22-Checking mobility camera in HAM3 - Travis
9:24–Heading to work in the optics lab - Nathan 
9:55-LN2 delivery – Praxiar
10:09-Reset HEPI overflow counters for HAM3, HAM4, ITMX, and BS – Operator
11:16-Water delivery - Paradise 
11:35- Heading into the LVEA (HAM2 area) – Kiwamu/Keita
11:52-Working at End X – Krishna
12:55-Heading to End Y for cleaning – Karen
13:17-Back from the LVEA – Kiwamu/Keita
14:23-Returned from End Y – Karen
14:40-Working in the LVEA (craning) – Kyle
15:01-Finished working in the LVEA – Kyle
15:14-Moving Leak Detector Setup from the LVEA to End X – Gerardo/Filiberto

Note: Analog video cameras were not working today (see Alog# 13487)
H1 CDS
david.barker@LIGO.ORG - posted 15:28, Tuesday 19 August 2014 (13493)
Beckhoff ecat GDS MEDM screens created

Further to making the Beckhoff Ethercat PLC systems more visible to the control room, I have created "GDS" looking screens for the nine PLC systems and linked them to the CDS OVERVIEW screen in the "SLOW CONTROLS" section.

Images attached to this report
H1 SYS (CDS)
james.batch@LIGO.ORG - posted 14:44, Tuesday 19 August 2014 (13492)
Adjust time server sync on Ethercat computers
The NTP clients on the three Windows-based Ethercat computers has been set to use a server at 10.20.0.6, and the interval for checking shortened from one week to 1 hour after finding the clocks to be off by several seconds.
H1 SUS
arnaud.pele@LIGO.ORG - posted 14:10, Tuesday 19 August 2014 (13489)
Staging building teststand quad models resurrected

[Jim Arnaud]

This morning the quad iop and sus models of the staging building were restarted in preparation of future testing of QUAD09. The system would restart with wrong filters engaged (the 'norm' filters of the damping were on, whereas the input is not calibrated in um), so a new burt was saved with the good config.

Attached are some notes for testing QUAD09 in the staging building, as well as how to start the models

Images attached to this report
Non-image files attached to this report
H1 CDS (SUS)
david.barker@LIGO.ORG - posted 12:21, Tuesday 19 August 2014 (13490)
Testing RCG2.8.5 fix of 18bit Anti-Image chassis control

Jim, Dave

All systems (except h1psl0) were upgraded to RCG2.8.5 last week after the power outage. RCG2.8.5 has the bug fix which permits the IOP to disable the SUS DAC anti-imaging chassis via a keep-alive signal outputted from the 18bit DAC card.

Today we tested the control of the AI chassis using the ETMY/TMSY suspensions system via the IOP model h1iopsusey. Jeff K and Arnaud P gave us permission to use the EY suspension systems.

All the tests passed.

Here is what we did:

  1. used guardian to put h1susetmy and h1sustmsy into the SAFE state
  2. verified all AI chassis were active (green LED on back are ON)
  3. killed the models h1susetmy and h1sustmsy, verified that now no models were using any DAC channels, the IOP model deactivated the AI Chassis, relays were heard to close, green LEDs all went OFF.
  4. started the models, untripped the user watchdogs. Verified that now models are using the DAC channels, the IOP activated the AI Chassis, green LEDs all ON.
  5. bypassed the SWWD on h1seiey so if the SUS test exceeded 5 mins the SEI system would not trip
  6. PANIC crashed the TMSY SWWD, verified all the AI chassis were deactivated (green LED all OFF)
  7. removed the PANIC and RESET TMSY SWWD, verified all the AI chassis were activated (green LEDs all ON)
  8. PANIC crashed the ETMY SWWD, verified all the AI chassis were deactivated (green LED all OFF
  9. removed the PANIC and RESET ETMY SWWD, verified all the AI chassis were activated (green LEDs all ON)

This concluded the test. The BYPASS on h1seiey was removed. Guardian put both ETMY and TMSY into the DAMPED state.

H1 General
andres.ramirez@LIGO.ORG - posted 11:01, Tuesday 19 August 2014 (13488)
OPS: reset of HEPI L4C Accumulated WD Counters Tuesday 19th August 2014
Maintenance: Reset HEPI overflow counters for HAM3, HAM4, ITMX, and BS.
H1 CDS
cyrus.reed@LIGO.ORG - posted 10:24, Tuesday 19 August 2014 (13487)
Analog Video Matrix Switcher
Andres reported that the analog video feeds in the control room weren't working.  The matrix switcher in the MSR was plugged in, but did not appear to have power.  I unplugged it, waited a few seconds, and plugged it back in and it powered up.  There was nothing that looked amiss with the power supply module or any of the boards accessible from the front of the chassis.  It may have been a power glitch, or the power supply is getting flaky in it's old age.  It appears to be a modular type under the cover, so it may be easy to replace if needed if it is still available commercially.
H1 General
andres.ramirez@LIGO.ORG - posted 09:39, Tuesday 19 August 2014 (13486)
Diode Room Crystal Chiller (Maintenance)
Crystal chiller has been refilled (added 250 ml of water to bring the level up to maximum)
H1 SEI (CDS, DetChar, PEM)
jeffrey.kissel@LIGO.ORG - posted 09:25, Tuesday 19 August 2014 (13483)
Reference Mirror BRS Signal added to h1isietmx Frontend
J. Kissel, K. Venkateswara

Because we continue to find the reference mirror signal -- a proxy for the autocollimator noise -- to be a useful signal to judge where the Beam Rotation Sensor's noise floor lies, we've output this channel out of the laptop's DAC, and piped it into the H1 ISI EX ADC on Channel ADC_0_29, and stored it in the science frames at 256 [Hz]. We expect the reference mirror to be stable, so we've not applied the very-low-frequency 1 [mHz] high-pass, but otherwise the calibration of the signal is identical to that of the beam balance mirror (see 13448):
3.5e-6 [rad/pixel] * 1 [pixels/V_sing] * 1/2 [V_sing / V_diff] * 40/2^16 [V_diff/ct] * 1e9 [nrad/rad] =  1.0681 [nrad/ct]
This gain, called "cts2nrad" has been installed into FM1 of the H1:ISI-GND_BRS_ETMX_REF filter bank, as with the beam balance mirror.


This required a recompile, reinstall, restart, and restore of the H1ISIETMX. We have not yet reboot the frame builder, so it remains with a 0x2000 status until the next DAQ restart at a more convenient time. I've committed the changes both the top-level h1isietmx.mdl model, and the H1ISIETMX.txt filter file to the userapps repo. We haven't yet added the filter bank to the BRS screen, but we'll get there.

H1 DAQ (CDS)
james.batch@LIGO.ORG - posted 09:24, Tuesday 19 August 2014 (13485)
Default NDS server changed for new logins and shells
WP 4790 - The default NDS server has been changed back to h1nds1 for the control room workstations.  This affect new logins or new shells. Existing shells and programs should not be affected.
Displaying reports 70141-70160 of 83266.Go to page Start 3504 3505 3506 3507 3508 3509 3510 3511 3512 End