Displaying reports 70421-70440 of 77065.Go to page Start 3518 3519 3520 3521 3522 3523 3524 3525 3526 End
Reports until 21:46, Friday 21 June 2013
LHO General
patrick.thomas@LIGO.ORG - posted 21:46, Friday 21 June 2013 (6856)
plots of dust counts
Attached are plots of dust counts requested from 5 PM June 20 to 5 PM June 21.
Non-image files attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 21:38, Friday 21 June 2013 (6855)
plots of dust counts
Attached are plots of dust counts requested from 5 PM June 19 to 5 PM June 20.
Non-image files attached to this report
H1 ISC
daniel.sigg@LIGO.ORG - posted 18:36, Friday 21 June 2013 (6852)
Green ALS PD in transmission recalibrated
The calibration of the green ALS PD in transmission of the arm cavity and located on ISCT1 have been remeasured. The responsitivity of the PD was changed to 0.22 A/W (from 0.755 A/W); a factor of 3.4 decrease. The beamsplitter ratio was measured to be 19% (from a theoretical 20%). The datasheet of the SM1PD1A indicated around 0.23 A/W at 532 nm.
H1 SUS
douglas.cook@LIGO.ORG - posted 16:45, Friday 21 June 2013 (6851)
Fiber Pulling Machine Spinning Mirror Motor Bearings Failing
Bosch 0130002090 - discontinued and out of stock so I am researching a similar product
Motor Specs:
Permanent Magnet
Torque - 1.85 Ncm
Unloaded 2850 RPM at 12vdc stock, 5.5W
 (current config Loaded: 1760 RPM - 8.55 vdc at 3.55 A)
Mounting - 2x 4mm on 46.5BC
2 bolt oval plate
shaft dia 5mm x 22.5mm
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:00, Friday 21 June 2013 (6849)
Opt Shift Summary
08:00
Laser Safe
Alarms: CDS and Dust DR #1

Pablo in H2-PSL working on PCAL
Filiberto pulling cables at End-X
Western States delivered new scissor lift
John W working at End-Y
Pablo out of H2-PSL
Jim and Cyrus at Mid-X working on fiber
Pablo in H2-PSL working on PCAL
Richard working in LVEA around dust monitor 4
Virginio taking equipment to End-X 
LHO VE
kyle.ryan@LIGO.ORG - posted 15:39, Friday 21 June 2013 (6848)
Helium removal
YBM turbo valved in for 6 hours today -> Started @ 9 x 10-7 torr*L/sec, ended @ 6.5 x 10-7 torr*L/sec
H1 ISC
corey.gray@LIGO.ORG - posted 15:33, Friday 21 June 2013 - last comment - 08:28, Monday 24 June 2013(6847)
EX TMS Work

(Corey, Keita, Lisa, Matt, Virginio)

ISC Table Layout Has Begun

I roughly laid out the QPD Sleds, High Power Beam Dump, & Beam Diverter.  Matt & Lisa started laying out all the rest of the optics (which required brining all the hardware from the Corner Station and then building each component, and then laying it out.)  Most of the optics are now on the Table.  Matt & Lisa will finish off laying them out and then begin aligning everything next week.

Telescope:  Staging & Tooling

Virginio & I unwrapped Tooling for suspending the Telescope.  Virginio is staging to start using our alignment laser.

Continuing To ICS

Continue to start making Assy Loads and accounting for all parts used for this installation.

EX TMS Weather

Relative Humidity started at 30% in the morning and went to 35% in the afternoon.  We will receive desicant packs and hygrometers on Mon/Tues.

Comments related to this report
corey.gray@LIGO.ORG - 08:28, Monday 24 June 2013 (6860)

TMS Mock Feedthru

Helped Filiberto connect the "roof-side" (vs. lab-side) cables to this Feedthru on Fri as well.  We only installed 4 (of 5) cables (5th cable had a bad connector).

Images attached to this comment
H1 CDS
david.barker@LIGO.ORG - posted 14:43, Friday 21 June 2013 - last comment - 20:02, Friday 21 June 2013(6844)
started first EX front end computer, caused DAQ problems, stopped running computer

Following the installation of timing, networking and ipc in EX, we booted the h1susauxex front end computer and started the IOP model. This caused mx-stream DAQ errors from many other front ends, including all at EY and on the LVEA test stand. Restarting the mx streamers on these front ends did not clear the problem. When h1susauxex was powered down (thereby killing the mx streaming) all the other front ends became good again with intervention needed.

We will keep EX powered down for this weekend and revisit this problem Monday or Tuesday next week.

Comments related to this report
keith.thorne@LIGO.ORG - 14:54, Friday 21 June 2013 (6845)
You may be encountering problems when manually starting models
 See this wiki page https://awiki.ligo-wa.caltech.edu/aLIGO/FrontEndStart

You will see that the old scripts start_streamers.sh and start_iop_mx_stream.sh still use a single port MX stream. 
As described, modifying start_streamers.sh is easy (merely stop/start /etc/init.d/mx_stream). Discard start_iop_mx_stream.sh.

* I have tested the new startup scheme described there on the LLO DAQ test stand, but have not attempted in on L1.
The RCG 2.7 roll-out would be a good chance to do that.
keith.thorne@LIGO.ORG - 19:32, Friday 21 June 2013 (6853)
Also make sure that the /diskless/root/etc/rtsystab file has been updated with a line for the new computer and IOP model.  Several startup scripts depend on it.  In particular /etc/init.d/mx_stream uses it to figure out the MX stream card and slot.
cyrus.reed@LIGO.ORG - 20:02, Friday 21 June 2013 (6854)
There was a configuration error on the EX DAQ switch on two ports, including the one for h1susauxex (h1seiex being the other).  It was missing the mtu setting to allow transmission of jumbo frames (the dainbramaged CLI pagination code in these switches makes this hard to see, even when expressly looking for it...).  This has been corrected, and I suspect it will work now barring any other problems, but this is yet to be tested.
H1 PEM
richard.mccarthy@LIGO.ORG - posted 14:23, Friday 21 June 2013 (6843)
Dust Monitor Y Beam Manifold Seismic Test Stand
Changed out the 9 pin cable that connects this dust monitor to the 485 loop in the hopes of reducing data problems.  The cable that was connected was twice as long and may have had too much voltage drop to properly power the dust monitor when the motor was running.
H1 CDS
james.batch@LIGO.ORG - posted 13:40, Friday 21 June 2013 (6842)
End X CDS networking has been installed.
The End-X network switches for front-end and daq traffic have been connected, allowing the front end computers for the end-x to be started when needed.  The RFM switch has also been connected between the corner and end-x.
H1 PEM
james.batch@LIGO.ORG - posted 13:36, Friday 21 June 2013 (6841)
h1pemmx has been restarted
Network reconfiguration is complete, h1pemmx has been restarted.  As a bonus, the timing master to timing slave issue has been solved, so the timing is no longer out of sync.
H1 SEI
greg.grabeel@LIGO.ORG - posted 08:57, Friday 21 June 2013 - last comment - 11:20, Monday 24 June 2013(6838)
HEPI status

HAM HEPIs 4 and 5 were brought into run mode yesterday, June 20th. 

current HEPI Status: 

Bleed Mode Run Mode
HAM 2 BSC 1
HAM 3 BSC 2
BSC 9 BSC 3
  BSC 6
  HAM 1
  HAM 4
  HAM 5
  HAM 6
Comments related to this report
greg.grabeel@LIGO.ORG - 15:24, Friday 21 June 2013 (6846)

HAM 2 is now on the run list.

greg.grabeel@LIGO.ORG - 11:20, Monday 24 June 2013 (6863)

HAM 3 is now in run mode as well.

H1 ISC
kiwamu.izumi@LIGO.ORG - posted 07:15, Friday 21 June 2013 - last comment - 10:57, Friday 21 June 2013(6835)
HIFO activity

[Alexa, Chris, Matt, Kiwamu]

Currently our focus is on two main tasks : refinement of Alexa's control model and the CARM control with the PFD (Phase Frequency Discriminator).

Yesterday we did the following items :

Comments related to this report
kiwamu.izumi@LIGO.ORG - 07:34, Friday 21 June 2013 (6836)

As a result the UGF of the end PDH loop became 9.7 kHz with a phase margin of 50 deg. Probably we could go higher but we can't go higher than 17 kHz where the phase margin turns in zero.

alexan.staley@LIGO.ORG - 10:57, Friday 21 June 2013 (6839)

[Kiwamu, Alexa, Matt]

Attached are the transfer functions Kiwamu refered to. The attachment are in the following order:

1) Current picture of the ALS model used for comparison of the transfer functions taken

2) Image of measure transfer function of End Y PLL Loop

3) Transfer function of End Y PLL Loop from ALS model

4) Image of measured transfer function of End Y PDH Loop

5) Transfer function of End Y PDH Loop from ALS model

Images attached to this comment
H1 ISC
corey.gray@LIGO.ORG - posted 08:28, Thursday 20 June 2013 - last comment - 08:35, Friday 21 June 2013(6820)
EX TMS Work Yesterday

(Corey, Virginio)

Continue to build up the Telescope and In-Vac ISC Table assemblies.

Spent time contemplating how to make TMS Assy Loads in ICS.

Topic of humidity came up in the Weekly TMS Meeting came up yesterday---namely the negative effects of humidity on Optic coatings.  We have a Dust Monitor in the Lab, but it isn't "online".  (For a "first Humidity data point", had a humidity of 21% mid-afternoon time yesterday)  In the future, we'll be receiving desicant packs from CIT and will make "Ameristat bags/covers" for our assys with optics and place desicant within these "bags".

Lisa has completed cleaning of all 2" optics which go on the In-Vac Table.  We will gather opto-mechanical hardware for these optics & then transport this to EX.

Continue to add photos of progress here.

Comments related to this report
corey.gray@LIGO.ORG - 08:35, Friday 21 June 2013 (6837)

Actually, want to nullify that "first data point".  I assumed the Dust Monitor was constantly running, but it wasn't.  Once Virginio Started it, this is when we saw humidity levels around ~40%.  Now it's worth noting we have had some rare summer rainstorms for the last few days.

Displaying reports 70421-70440 of 77065.Go to page Start 3518 3519 3520 3521 3522 3523 3524 3525 3526 End