Displaying reports 71061-71080 of 77037.Go to page Start 3550 3551 3552 3553 3554 3555 3556 3557 3558 End
Reports until 15:53, Monday 22 April 2013
H1 SEI
vincent.lhuillier@LIGO.ORG - posted 15:53, Monday 22 April 2013 (6161)
Model updates - BSCs 1 2 3 6

BSC-ISI common model was updated. I modifided the master model and a couple of MEDM screens. Changes were commited (rev 4230 for model and re 4231 for MEDM screen). 

A correction was made on the T240 calibration gain and binary outputs block was modified to control STS-2s centering proccess. Overview and BIO screens were modified as well.

New codes were installed on BSCs 1 2 3 6.

H1 SUS
betsy.weaver@LIGO.ORG - posted 15:53, Monday 22 April 2013 (6160)
BSC2 chamber closeout

Since further work continued in the chamber last week, the final chamber closeout had not been completed.  After checking for task completions for the final, final time, I went in and

1) checked for tools (none found, good)

2) removed the in-chamber stool

3) took a few more pix

4) re-inspected the naked BS optic (yep, dirty @ ~1-3 particles per square inch in many regions of both HR and AR face - some there prior to last week)

5) wiped my way out of chamber

6) placed verticle 1" witness optic under the BS suspension.

H1 PSL
michael.rodruck@LIGO.ORG - posted 15:15, Monday 22 April 2013 (6159)
PSL plots

For the 35W beam.

Images attached to this report
Non-image files attached to this report
H1 SEI
vincent.lhuillier@LIGO.ORG - posted 13:26, Monday 22 April 2013 (6157)
ISI-BSC2

The ISI-BSC2 (tested at the end of last week) is functional. The testing report can be found at LIGO-E1300292-v1.

LHO General
patrick.thomas@LIGO.ORG - posted 10:11, Monday 22 April 2013 (6156)
dust monitors in LVEA
I had to restart the IOC for the dust monitors in the LVEA due to communication errors. Cause is unknown.
H1 CDS
james.batch@LIGO.ORG - posted 09:06, Monday 22 April 2013 (6155)
Restart cdsfs1
Found cdsfs1 completely unresponsive, no display on console, no ability to log in remotely.  Powered off computer, removed and reinserted power cords, then powered back up.  After usual reboot, system came back, disk verify shows parity mismatches which are being repaired.
H1 IOO
keita.kawabe@LIGO.ORG - posted 01:19, Monday 22 April 2013 (6152)
IO work on Friday

Belated alog for Friday activity after Cheryl was gone.

A good news is that Cheryl told me that the IM alignment was not good when we (Kiwamu, Sheila and me) found in HAM1 that the IFO refl beam was clipping on Thursday. On Friday Cheryl restored IMs and Sheila couldn't see any clipping of the beam going to HAM1.

But the bad news is that PRM still has a huge offset.

I think  it is essential to establish that the beam is actually at a good ballpark position on PR2. If the beam going from the last IM to PR2 has a reasonable angle and yet PRM is using up more than 90% of DAC range for PIT offset, one can conclude that PRM has a big natural tilt (though we don't know why). OTOH if the beam is not hitting PR2 or something, we have a bigger problem.

Cheryl told us that it should be possible to see the beam in front of PR2 if we have 00 mode flash. Since she also told that the straight shot beam (through MC1bouncing on MC2 and coming through MC3) looked good, I and Sheila tried to align MC using only MC1 and MC3 without touching MC2. We didn't do a thorough job, in the end we were still off in PIT (looked as if 10, 01 and 11 were dominant, but PIT had larger order modes flashing) but got 00 once in a while, but we couldn't see anything in HAM3.

Before giving PRM to SUS, the following should be done:

  1. Align MC better. Note that the alignment offset of MC1 and MC3 are already kind of big-ish.
  2. Use CCD camera and IR viewer card to see if the beam is on PR2.
  3. Use CCD camera to see if the beam is hitting the baffle.
  4. Use laser safety glasses for 1064nm. Our "official" glasses are totally utterly incompatible with IR viewer.
H1 General
sheila.dwyer@LIGO.ORG - posted 14:59, Saturday 20 April 2013 (6151)
Door cover ripped on HAM2 West
While Keita Cheryl and I were trying to see 00 flashed from the mode cleaner yesterday afternoon/evening, I ripped the door cover on the west side of HAM2.  It is a small rip (about an inch long) right by the clip on the north side of the door.  Since everyone had gone home and we didn't know where to find new door covers, we just covered back up when we left.  
LHO General
patrick.thomas@LIGO.ORG - posted 22:52, Friday 19 April 2013 (6150)
plots of dust counts
Attached are plots of dust counts requested from 5 PM April 18 to 5 PM April 19.
Non-image files attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 21:12, Friday 19 April 2013 (6149)
Replaced temp (2nd) purge air connection and replaced with 10" CFF blank -> Began pumping Y-end


			
			
H1 SEI
hugo.paris@LIGO.ORG - posted 20:07, Friday 19 April 2013 (6145)
IMC HAM-ISIs - Lockers Adjustments

Both HAM2 and HAM3 ISIs were locked this morning for alignment work. It was a good occasion to take look at the time series of the ISIs' Capacitive Position Sensors, and make sure that the locked/unlocked shifts were within requirements.

Maximum shift observed < 800cts*.The locked/unlocked shifts are within requirements**. Results are attached.

*:Calibration: 32768cts/mm

**: Acceptance Criteria (E1000309-v13, p28)
 Absolute values of the difference between the unlocked and the locked table must be below 1600 cts

Images attached to this report
H1 SUS
arnaud.pele@LIGO.ORG - posted 19:43, Friday 19 April 2013 - last comment - 21:06, Friday 19 April 2013(6147)
SHIFT PRM

April 10th between midnigth and 1am (UTC) (cf dataviewer trend attached)

M1 PRM Pitch offset  = 2000
M1 PRM Yaw offset   = 50

M3 pitch = 2000
M3 Yaw  = 115

Today with the same offsets (cf medm screen attached)

M3 Pitch = 1164
M3 Yaw   = -199

Images attached to this report
Comments related to this report
cheryl.vorvick@LIGO.ORG - 21:06, Friday 19 April 2013 (6148)
Keita and I looked at the PRM in both the old aligned position, p=2000 and y=50, and found that EQ stops looked good as expected based on Arnaud's spectra.  Then we drove the PRM to p=4135 and looked again for an EQ stop that was touching, and found none.  I looked at ISI trends, and the vertical sensor change from the locked for installation and rebalanced and refloated show that there was a tilt in the HAM ISI table and PRM saw something like 1800 counts change.  From this, I believe that PRM is not touching an EQ stop, and that the shift in alignment is due to the tilt of the HAM2 ISI table, when it was rebalanced and refloated after changing it's payload.

I left today with Keita and Sheila still possibly working on the IMC, the low beam in HAM3, and PRM alignment, so maybe this is all solved.  IF not, then it's time to have SUS come take a look at PRM to see how healthy it is, and to relieve the pitch bias.  Recall, it's aligned position has 2000 of pitch already, and we needed an additional 2000 to get REFL through to HAM1.
H1 SUS
arnaud.pele@LIGO.ORG - posted 19:14, Friday 19 April 2013 (6146)
PRM spectra

PRM spectra is plotted on the pdf attached for 3 different dates, with 3 different alignment offsets.

*in blue April 15th with Pitch and Yaw set to zero

*in green today (April 19th) at noon with Pitch=2000 and Yaw=50

*in red, today (April 19th) at 5pm with Pitch=3900 and Yaw=350

Except the noise floor that is higher for the last one (red), all curves match (in terms of resonnances), showing that PRM is/looks fully suspended (transfer function would be the only way to be sure, but spectra is already a very good indicator).

the conclusion is that even with large offsets in Pitch (taking more than 90% of the DAC range) PRM doesn't seem to touch any EQ.

PS : as the picture shows, when the ADC reads a DC signal greater than 10,000 counts (red number), the IOP watchdog trips (eg when a large offset is applied), meaning you'll have to bypass it if you need to keep the offsets on.

Images attached to this report
Non-image files attached to this report
H1 General
jeffrey.bartlett@LIGO.ORG - posted 15:57, Friday 19 April 2013 (6144)
Ops Summary
Alarms: Dust Monitor, IOP Watchdogs, CDS Front end
Laser Hazard

08:06 Washington Crane on site for crane inspection
Pablo and Michael working in H2 Laser enclosure for PCAL
08:36 Transition to Laser Safe
10:30 Sno Valley on site to work on chillers
Japanese National Broadcasting film crew on site being escorted by Fred Raab
Crane inspection in LVEA and at End X
Aaron & Filiberto working at End Y
11:15 and 11:40 Dale escort two high school tours of control room
13:08 Washington Crane on site for crane inspection
13:20 Kyle pumping at End Y
14:00 Cheryl transition to Laser hazard
14:25 Alarm on air handlers at Mid Y, Kyle to check out.   
H1 CDS
james.batch@LIGO.ORG - posted 14:25, Friday 19 April 2013 (6141)
H1 DMT system available
The H1 DMT computers were moved within the equipment rack in the MSR to make room for additional CDS hardware.  The DMT system has now been powered up and is available for use.
X1 DTS
james.batch@LIGO.ORG - posted 14:23, Friday 19 April 2013 (6140)
X1boot powered up
X1boot was powered down for a disk clone, which was successful.  It has been powered up again and is available for use.
H1 TCS
greg.grabeel@LIGO.ORG - posted 18:38, Wednesday 17 April 2013 - last comment - 14:37, Friday 19 April 2013(6117)
BSC2 Steering Mirror Assemblies
The two steering mirror assemblies, D1101851, are installed in BSC2. They went in fairly smoothly. One hitch is where the support bracket attaches to the chamber's lower bracket; the weld from the lower bracket to the chamber wall kept the two surfaces from mounting flush.

The two mirrors are NOT installed yet. They oxidized during their bake and I am still working on figuring out if anything should be done about that. The mirrors shed a little, but it seems as though they are not shedding anywhere near the level that the chamber itself is.
Images attached to this report
Comments related to this report
greg.grabeel@LIGO.ORG - 14:37, Friday 19 April 2013 (6143)
Went in today to get better pictures. Specifically you can see where the mating to the chamber is somewhat inhibited by the weld.
Images attached to this comment
H1 AOS
hugo.paris@LIGO.ORG - posted 16:07, Wednesday 17 April 2013 - last comment - 15:11, Friday 19 April 2013(6116)
HAM3-IS - Viton Pads Test

We set up Viton Pads under HAM3-ISI balancing masses. The size of those pads is the same as the size of LLO's. However we set those pads under 1/2 the mass LLO uses, in order to rise the corner frequency of the mass+Viton stack.

Comparison before/after is attached.

The Viton Pads improve the 310Hz peak in V efficiently, by a factor > 5 without any drawback to it. Results are satisfying enough for now. We may try other configurations next time the chamber is open.

Non-image files attached to this report
Comments related to this report
hugo.paris@LIGO.ORG - 15:11, Friday 19 April 2013 (6142)

This Viton Pads Efficiency Test was plotted in the cartesian basis. Results are attached.

Best improvements can be seen along RX and RY, in the 310Hz region. Suspension modes can be seen there and they are known to be coupling with the ISI. 

Plots show that the Viton Pads we used helped limiting the impact of SUS/SEI couplings, on the ISI's Transfer Functions.

Having those viton pads should also facilitate the design of control loops, and eventually allow pushing the performance a bit further, as more gain margin will be available.

Non-image files attached to this comment
H1 SUS
arnaud.pele@LIGO.ORG - posted 09:45, Monday 15 April 2013 - last comment - 12:42, Monday 29 April 2013(6081)
BeamSplitter phase 3a (pre)testing

Beamsplitter transfer functions have been running over the weekend in order to fix any issues during the day if needed.

The attached pdfs show :

  1. Comparison between last TF damping on and model
  2. Comparison between last TF damping off and model
  3. Comparison between LHO damping on/off and LLO phase 3a (feb 2013) TFs
  4. Zoomed version of 3.

Vertical degree of freedom is noisier than expected between 1.5 and 3Hz (3rd page of each pdf).

Non-image files attached to this report
Comments related to this report
arnaud.pele@LIGO.ORG - 15:10, Monday 15 April 2013 (6087)

Gerardo went into the chamber, checked the EQ stops, and nothing is apparently touching. When the chamber will be free tomorrow during the day, I will run quick DTT measurements for the vertical degree of freedom, between 1 and 3Hz and see if it's still noisy. There were no need of taking the night for full measurements since the other DOFs are fine. I let the night to Vincent for ISI tfs if needed.

arnaud.pele@LIGO.ORG - 13:44, Monday 22 April 2013 (6158)

I ran a DTT transfer function on the vertical degree of freedom of the beamsplitter this morning

New TF looks nicer than the old one from April 12th, meaning the beamsplitter is healthy and passed Phase 3a testing

Will run a full set of TF tonight, for our record.

Data of the DTT measurement has been saved in a matlab structure named :M1VtoM1V_20130422.mat under SusSVN/sus/trunk/BSFM/H1/BS/SAGM1/Data and has been commited to the svn

Non-image files attached to this comment
arnaud.pele@LIGO.ORG - 12:42, Monday 29 April 2013 (6219)

Last measurement on the beamsplitter has been taken monday night April 22nd with damping on and off, before pumping down BSC2 chamber.

One thing to notice :

Vertical degree of freedom remains noisy around 2Hz, as on April 12th, even though dtt transfer function from aLOG 6158 doesn't show any issues. It could be that when taking TF with matlab, the drive for that frequency band is not high enough. I will try with higher gains in the MATLAB_TFs.m script and see if it changes anything. 

Non-image files attached to this comment
Displaying reports 71061-71080 of 77037.Go to page Start 3550 3551 3552 3553 3554 3555 3556 3557 3558 End