Displaying reports 73061-73080 of 85913.Go to page Start 3650 3651 3652 3653 3654 3655 3656 3657 3658 End
Reports until 18:49, Tuesday 05 August 2014
H1 SEI (DetChar, PEM, VE)
jeffrey.kissel@LIGO.ORG - posted 18:49, Tuesday 05 August 2014 (13228)
UWash Tiltmeter (BRS) installation continues!
Jeff K., Krishna V., Erik S.

Today we started with the assembly of the left arm of the vacuum can. The older flexures on the balance were damaged during transport so we replaced them with another pair Krishna had brought. We then inserted the balance into the 6-way cross and suspended it successfully. We were then adjusting masses on the balance to lower the resonance frequency close to 10 mHz. By the end of the day we got the frequency close to 20 mHz. 

Pictures of the assembly process attached in assembly order!
Non-image files attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 18:35, Tuesday 05 August 2014 (13227)
Leaving site now -> Closed XBM and YBM turbo header valves, safety valves and 10" gate valves
Will resume attended rough pumping of Vertex, XBM and YBM combined volumes tomorrow 
H1 IOO (PSL)
sheila.dwyer@LIGO.ORG - posted 18:33, Tuesday 05 August 2014 (13222)
PSL periscope PD

Alexa, Sheila

We saw that there was no signal on the PSL periscope PD, so we entered the PSL to investigate.  There is currently 170mW of light entering the periscope, and 0.7uW incident on the PD.  We measured the voltage from the PD using an osciliscope, it has a 13 mV offset and 4 mV of signal.  (both negative) This gives 0.38A/W, (we did not change the gain switch, so the gain setting should still be 15kOhms), and the pick off ratio (power on PD/power into HAM1) is 0.004.  These are not so different from the measurement Paul reported in alog 9865  We will stick with the old calibration which was made with more light on the diode.

We did not finish checking the calibration of this PD because there is also a problem with beckhoff.  Everything on corner chassis 3, 4, 5, and 6 is NO_COMM.  The problem with beckhoff was fixed by unplugging and reconnecting the cable between Corner Chassis 2+3, which could be a bad cable that needs to be replaced.

 

LHO VE
kyle.ryan@LIGO.ORG - posted 18:32, Tuesday 05 August 2014 (13226)
Running rotating pumps at Y-end during Rai's testing this week


			
			
H1 ISC
koji.arai@LIGO.ORG - posted 17:58, Tuesday 05 August 2014 (13224)
HAM6 Fast shutter installation

[Dan Koji]

A first fast shutter was placed at the approximate location on the HAM6 table. The cable has been connected to the shutter.
The feedthru end of the cable is waiting for replacement of a 2.75" feedthru flange. This flange is D3-3 according to D1002877.

The table space is really tight. The space for the shutter was just barely OK to place it behind OM3. It yet needs precise aligment.
The path for the (expected) reflected beam from the shutter was cleared by moving the beam dump for ASAIR beam diverter

The golden beam dump was installed at the edge of the table. This was realized by moving the cable post for the beam diverter.

Images attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 17:33, Tuesday 05 August 2014 (13221)
Maybe the 8hz problem at endY ETMY BSC10 HEPI Solved

Discussions with MIT (RichM) and looking closer at the very controllers & filters I plotted showed the problem.

While the developed controller I showed in the SEI Log, looked like it should not have been terrible at dealing with the potential instability at 8hz, the filter I posted in the LHO alog, was in fact a design unable to deal with this problem with strong peaking and marginal phase room at 8hz.  Once I realized these two views of the ETMY controller could not be the same, I knew somewhere the problem was twisted.  So I painstakingly went through all the filter design steps and sure enough, the design was there but was not saved correctly or prepared properly.  The Blue traces are the new X controller in the attached for ETMY while the Red traces are from the ITMX which is how ETMY appeared before.

There is of course no free lunch and if I understand and can explain (mostly for my own benefit).  The large phase bump in the 8ish Hz area pulls the controller away from instability and the design inherently has less gain peaking (maybe that is the same thing.)  On the other hand, if the zero in the plant (which can move around) moves away from this design point and/or the designer is too aggressive at matching the plant, the controller will develop something... (gain peaking?)

At the moment, ETMY is running under full Guardian Management in FULLY_ISOLATED.  Don't want to get ahead of myself but it has been almost 15 minutes now and Rai & Gerardo are still down there working on the chamber.  I have had one previous trip of the ISI for L4Cs but HEPI did not trip.  So, at least we are in a new epoch for BSC10 HEPI.

Images attached to this report
H1 COC (COC, INS)
michael.landry@LIGO.ORG - posted 16:27, Tuesday 05 August 2014 (13104)
Electrometer tests with pilot ITMY

Summary : We tested charging/deionizing of the unsuspended, isolated ITMY (Corning ETM02) with a new electrometer, the Alphalab Ultrastable Surface DC Voltmeter. We first measured the field at the HR surface of the optic interleaving a series of timed deionization runs with the TopGun Deionizer.  Next we applied and ripped FirstContact, and repeated measurements/TopGun nitrogen deionization. The deionization process appeared to take several minutes, having some effect out to nine minutes - however we have to repeat the measurement to assess charge on the barrel and AR optic surface (G. Moreno, N. Robertson, M. Landry, with C. Torrie and R. Abbott).

Details :

We set ETM02 (recently employed in BSC8/1 as the pilot ITMY for single-arm/HIFO experiments) upright on a teflon V-block in a cleanroom of the west bay of the LVEA ("fiber welding cleanroom"). We made measurements of the electric field 1" from the center of HR surface of the optic, and four measurements halfway between the center and the limb of the optic (right, top, left, bottom). Initially we simply applied the TopGun nitrogen in a series of 3 minute applications.  Later we applied FirstContact, let it dry overnight, and the pulled (with concurrent TopGun dionization), and made more field measurements interleaved with de-charging.  The data are below.

All values in negative kiloVolts (-kV) as read from the hand-held meter, unless otherwise signed positive. Field values in kV/m can be obtained by scaling by ~30X.

Trial Vc Vr Vt Vl Vb
1 2.4 2.7 3.2 2.7 2.6
2 2.2 2.2 2.4 2.3 1.8
3 0.11 0.14 0.10 0.15 0.10
4 0.02 0.05 0.035 0.03 0.03
5 0.02 0.035 0.01 0.03 0.035
6 0.005 0.005 +0.020 0.025 0.015
7 0.150 0.70 0.03 0.160 0.11
8 0.108 0.130 0.045 0.23 0.05
9 0.01 +0.01 0.035 0.08 0.01

where

Vc = raw voltage (kV) 1" above center of HR surface
Vr = raw voltage (kV) 1" above center-right (i.e. at a radius of +34cm/2, 0 degrees rotation angle) of HR surface
Vt = raw voltage (kV) 1" above center-top (i.e. at a radius of +34cm/2, 90 degrees rotation angle) of HR surface
Vl = raw voltage (kV) 1" above center-left (i.e. at a radius of +34cm/2, 180 degrees rotation angle) of HR surface
Vb = raw voltage (kV) 1" above center-bottom (i.e. at a radius of +34cm/2, 270 degrees rotation angle) of HR surface

and trial data were taken under the following conditions:

Trial 1 - Initial measure of electric field, HR side of optic, prior to application of FirstContact (FC), or TopGun deionizer (TG)
Trial 2 - same as trial 1, but 24 hours later, to see if there is some discharge in air (there is, ~25% lower than trial 1)
Trial 3 - After 3 min of TG deionization
Trial 4 - After 3 min of additional TG (6 min total)
Trial 5 - After 3 min of additional TG (9 min total)
Trial 6 - No additional TG, but after 3h delay
Trial 7 - FirstContact applied, then removed in a 2 min pull, with concurrent TG (2 min), plus additional 2 min TG thereafter
Trial 8 - After 2 min of additional TG (6 min total)
Trial 9 - After 3 min of additional TG (9 min total)

Individual measurements of the field could take 3-4 minutes to stabilize in the Voltmeter, i.e. values read out on the hand-held unit may have initially read hundreds of volts, falling and stabilizing to a seemingly stable number over the 3-4 minute time frame.

We wil repeat these measurements and include barrel and AR surface tests.  However, in consultation with C. Torrie and R. Abbott, and in order to be conservative in closing BSCs 1, 3 and 9, we opted to extend nominal few-minute TopGun blowing times for test masses and reaction masses to nine minutes total, i.e. 4.5 min for a given test mass HR face, 4.5 min for the AR gap, 4.5 min for the reaction mass upstream face, 4.5 min for the gap. We cycled between surfaces and gap in 1 minute intervals, summing to 9 min per optic.

H1 ISC
filiberto.clara@LIGO.ORG - posted 15:22, Tuesday 05 August 2014 - last comment - 14:02, Wednesday 06 August 2014(13218)
Corrected cabling for ISCT1 DC PD's and Auxiliary Channels
While doing cabling for HAM6 in the CER, noticed that the following cables for ISCT1 in ISC-C2 were plugged in backwards. Swapped the following at the EtherCAT Corner 5 Chassis. Cables are connected as listed below and match the pull list E12000408.

Cable_ISC_328 connected to Port 9 (DC PD's ISCT1)
Cable_ISC_326 connected to Port 10 (Auxiliary ISCT1)

Filiberto Clara
Comments related to this report
alexan.staley@LIGO.ORG - 14:02, Wednesday 06 August 2014 (13239)

(Sheila, Alexa)

After fixing the corner beckhoff, we noticed that the PSL persicope PD was still not reading the correct voltage based on yesterday's measurement alog 13222. It turns out that swapping back cable ISC_326 and ISC_328 fixes this problem.

As desgined from D1100583, E1200077:

The Auxiliary ISCT1 cable ISC_326 from Concentrator 1 --> EtherCat Corner Chassis slot 10

DCPDs ISCT1 cable ISC_328  from Concentrator 2 --> EtherCat Corner Chassis slot 9 --> System Manager L9-10 EL3104 Adapter 9

 

The System manager is linked according to the specification above. However, with the proper configuration the readback was not connected. Maybe it's an internal swap in the EtherCat Chassis? We have flipped the cables at the concentrator.

Current Configuration:

The Auxiliary ISCT1 cable ISC_328 from Concentrator 1 --> EtherCat Corner Chassis slot 9

DCPDs ISCT1 cable ISC_326  from Concentrator 2 --> EtherCat Corner Chassis slot 10 --> System Manager L9-10 EL3104 Adapter 9

H1 CDS
david.barker@LIGO.ORG - posted 14:35, Tuesday 05 August 2014 (13217)
Web page snapshots of CDS MEDM screens updated

I have updated the MEDM screens which are snapshotted and displayed on the web page:

https://lhocds.ligo-wa.caltech.edu/screens/

H1 PSL (PSL)
peter.king@LIGO.ORG - posted 14:04, Tuesday 05 August 2014 (13216)
diagnostic breadboard scans
Diagnostic breadboard scans were executed; these are to measure the frequency noise, beam pointing,
mode content and relative power noise.

Some notes in passing:
 - The higher mode content of the frontend laser looks okay.
 - Autoalignment did not go green as expected, I will have to sort this out after reading the manual.
 - The beam pointing seems higher than the requirement but this could be because the calibration is out (plus my operating error).
 - The relative power noise is higher than the requirement, assuming the calibration is correct.
 
Non-image files attached to this report
H1 PSL (PSL)
peter.king@LIGO.ORG - posted 13:04, Tuesday 05 August 2014 (13210)
reference cavity alignment tweak
Reference Cavity Re-alignment
=============================

The reference cavity transmission has steadily degraded over time from ~1.1V a month ago down to the ~0.4V when Jeff reported the problem to me.  A quick look at the alignment using only the periscope adjustments, did not make things any better and in fact I made it a little worse, leaving the transmission at ~0.22V (as displayed on the MEDM screen).  That indicated that either the alignment into the AOM was off or the RF level to the AOM was off.

Measured RF on oscilloscope, with 50 ohm input.
freq = 79.4 MHz
peak-to-peak amplitude = 21.66 V
Vrms = 7.965 V

So the RF level into the AOM is 1.27 W.  This is about the right level for maximum diffraction efficiency.  Note that the maximum RF power into the AOM is 1.3 W.

zero reading on power meter = 2.7 mW, power meter used is the Ophir thermal calorimeter
no measurements have been corrected unless otherwise noted
power incident on AOM, measured after PBS = 57 - 62 mW
power incident on 21.5 MHz EOM = 21 - 23 mW
this represents a double pass efficiency of ~ 22/59.5 = 37%
or a single pass diffraction efficiency of ~61% (Sqrt[37%])

After adjusting mostly the height of the AOM, the power before the 21.5 MHz EOM was 26 mW or 66% single pass diffraction
efficiency, further tweaks to the height resulted in 34 mW or a single pass diffraction efficiency of ~76%

Tweaked alignment into reference cavity using the periscope - mostly height adjustments; measured reference cavity transmission is ~710 mV on DMM, ~1.16V on MEDM display.  This is as good as the value from over a month ago.
Images attached to this report
H1 CDS
kiwamu.izumi@LIGO.ORG - posted 12:17, Tuesday 05 August 2014 (13215)
ASC and LSC models newly compiled, but not restarted

Since we are pumping down the volume, we decided to postpone restarting the models. So the mission is incomplete.

If one wants to change the ASC or LSC model in the meantime, please notify me.

H1 SEI
hugh.radkins@LIGO.ORG - posted 12:10, Tuesday 05 August 2014 (13214)
WHAM4 HEPI Unlocked Currently Postion Loops Closed

Completed stripping the Ameristat from the HEPIs and unlocking the platform at 1015pdt.  Closed the HEPI loops with no difficulty.

Attached at spectra from overnight (HELI Locked) compared to after unlocking; and, comparing after unlocking to having the position loops closed.

Comparing the three states, basically it depends, some frequencies better, others, not so much.

Images attached to this report
H1 PEM
james.batch@LIGO.ORG - posted 11:01, Tuesday 05 August 2014 (13213)
Restarted Mid-X weather station
The Mid-X weather station, which died Saturday evening, was restarted by power-cycling the Comtrol box and the weather station.  The EPICS IOC for the weather station was restarted and the weather is now being reported properly. No equipment needed to be replaced.
H1 SEI (CDS, SUS)
james.batch@LIGO.ORG - posted 10:58, Tuesday 05 August 2014 (13212)
Restart h1seiey computer
The h1seiey computer crashed with a kernel panic at 08:41 PDT today.  Attempts to remove it from the dolphin network were unsuccessful, so on restart, h1susey was glitched and needed to be restarted as well.  Inspection of the computer and I/O chassis showed no obvious reason for the crash.
H1 SEI (DetChar, PEM, SYS)
jeffrey.kissel@LIGO.ORG - posted 10:46, Tuesday 05 August 2014 (13211)
H1 EX BRS Installation, Day 1
J. Kissel, K. Venkateswara, E. Shaw

Krishna and Eric arrived yesterday, and we've begun installation of the Beam Rotation Sensor at H1 EX. Pictures attached!

Some quick notes -- the center of the platform is roughly 41" WEST (+Y), and 9" SOUTH (-X) of the GND T240, and aligned with the IFO's X-axis, parallel to the line formed by the GND T240 and PEM Guralp. 

I also attach a screen shot of the custom overview screen I created.
Images attached to this report
Non-image files attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 09:09, Tuesday 05 August 2014 (13207)
Installation meeting notes
BSC1 and 3 gatevalve work in progress
The extra viewport on BSC2 will be left in place

IOT2 table to be moved to west side of HAM2

The north door will be pulled on HAM6 for ISI rebalancing
wipe down and particle assessment beforehand

Pumping vertex by noon

HAM6: placing of fast shutter component today, remainder of work requires beam

Peter K. is checking alignment on PSL table

TCS:
Started bonding polarizer
Start work on X arm table after lunch, request for laser hazard in the afternoon

ITMX optical lever work in the morning

EE work in racks by HAM6

Hugh will be removing the ameristat at HAM4

Rai W. here to work on mirror charging experiment at end Y
end Y will be transitioned to laser safe

tiltmeter experiment underway at end X

Kiwamu updating and restarting the ASC realtime model

Praxair delivery to mid Y

upgrade of conlog
H1 SUS
arnaud.pele@LIGO.ORG - posted 00:46, Tuesday 05 August 2014 - last comment - 17:40, Tuesday 05 August 2014(13203)
SRM-MC2-SR2 balanced - overnight measurements starting

[Jeff Arnaud]

Tonight we balanced the coils of the lower stages of MC2 SRM and SR2. The MC2 notes attached are explaining the procedure in detail. Below is summarized the ASD ratio after/before the exercise for each suspension and each level.
For some reason M3 stage of SR2 was harder to balance than the other ones, so we gave up on it for now and will come back to it later.

SUS STAGE        ASD RATIO before/after balancing
PITCH YAW
MC2 M2 19.71 2.63
M3 21.27 13.52
SRM M2 9.95 38.53
M3 6.96 3.8
SR2 M2    
M3 107.7 5.12

And the gains which were found optimum for each coils

SUS STAGE OSEM GAIN
MC2 M2 UL 0.988
LL -0.992
UR -1.007
LR 1.012
M3 UL 1.082
LL -0.948
UR -1.051
LR 0.922
SRM M2 UL 0.935
LL -1.024
UR -0.971
LR 1.063
M3 UL 0.972
LL -1.014
UR -0.972
LR 0.964
SR2 M2 UL  
LL  
UR  
LR  
M3 UL 1.003
LL -1.050
UR -0.951
LR 0.996

 

Measurements will be running overnight to measure the cross couplings transfer functions for SR2 SRM and MC2

Images attached to this report
Non-image files attached to this report
Comments related to this report
borja.sorazu@LIGO.ORG - 17:40, Tuesday 05 August 2014 (13223)
There is a discrepancy in the text. While it says that SR2 M3 was not balanced however in the results table it is SR2 M2 the one blank. I can confirm that SR2 M2 is the one not yet balanced.
H1 SEI
hugh.radkins@LIGO.ORG - posted 09:53, Friday 01 August 2014 - last comment - 08:38, Wednesday 06 August 2014(13138)
ETMY HEPI 8ishHz Peak

This plot is interesting.  It seems the only moderately pronounced peak in the horizontal ground spectrum wanders, seen from 8 to 11hz changing quite rapidly.

The attached plot's current traces are with HEPI loops closed and the ISI Damped.  While the middle graph shows all four local IPSs have the strong 8hz peak (the dashed REFs are with the HEPI loops open), the peak only shows in the X & Y and not the RZ cartesian traces (top graph).  Also, note the bottom graph where the ground sensor pretty much has nothing at 8hz but does have a minor peak just above 9hz that is also peaking up in the local sensors.

The second plot shows just the ground Seismometer with X & Y traces from last night (Dashed) and the others from this morning. The peaks in that area come and go and wander around so it may or may not be a problem or just a red herring (are those edible?)

Images attached to this report
Comments related to this report
guillermo.valdes@LIGO.ORG - 18:46, Friday 01 August 2014 (13170)DetChar
I am attaching the spectrograms for the X, Y, and Z directions of the STS Seismometer in ETMY.
I used 19 continuing hours, starting 2014-07-22 01:00:00 UTC.

There is a feature that is present all the 19 hours:
Around 10.5 Hz  in X direction.
Around 9 Hz in Y direction.
Around 10.5 Hz in Z direction.

More features can be seen wandering along the 19 hours around 3-5 Hz and 8-10 Hz, for X, Y, and Z directions.

In the spectrograms, each count is 1 nm/s /sqrt(Hz).
Images attached to this comment
guillermo.valdes@LIGO.ORG - 08:33, Tuesday 05 August 2014 (13206)DetChar, PEM
Continuing with the investigation on the 8 Hz, I am attaching the spectrograms for the X, Y, and Z directions of the GND STS in EY.

Comments on the spectrograms: 
- Feature wanders between 7.5 to 12.5 Hz.
- Depends on the time of the day. 
- It is present every 15 to 30 minutes.
- Displacement amplitude higher than 2 nm.

6 hrs were used for each spectrogram, starting:
- August 01, 2014 00:00:00 UTC (Figure 1)
- August 01, 2014 06:00:00 UTC (Figure 2)
Non-image files attached to this comment
brian.lantz@LIGO.ORG - 16:08, Tuesday 05 August 2014 (13219)
The 8 hz motion seen here is most likely related to the "pier resonance" 
Laura Nutall has a nice set of plots in the DCC https://dcc.ligo.org//LIGO-G1400820
which show this motion. 
Likely you are seeing the floor component of this motion. Rich M. has data showing that (at MIT) the slab bending is an important component of this motion
nathaniel.strauss@LIGO.ORG - 08:38, Wednesday 06 August 2014 (13231)
I investigated the GND SDS and PEM MIC channels using the coherence tool at 100mHz bandwidth and found several peaks between 5 and 9 Hz. I've attached some slides with zoomed-in plots.
Non-image files attached to this comment
Displaying reports 73061-73080 of 85913.Go to page Start 3650 3651 3652 3653 3654 3655 3656 3657 3658 End