Displaying reports 74961-74980 of 76953.Go to page Start 3745 3746 3747 3748 3749 3750 3751 3752 3753 End
Reports until 12:54, Wednesday 18 January 2012
H2 SEI
hugh.radkins@LIGO.ORG - posted 12:54, Wednesday 18 January 2012 (2064)
BSC8 HEPI State for Initial Alignment
As IAS told us last night we were 0.4mm South, we disconnected the Vertical Actuators and then based on the Dial Indicators moved a total of ~1/2mm North.  After this, IAS told us we were 0.9mm too far North...What gives?

Jason checked his numbers and confirmed.  We moved the HEPI back South ~1mm and now IAS says we are 0.03mm South.

So now the ACB is being aligned--when they are done, SEI will change/add Viton to vibration absorbers.
H2 SUS
betsy.weaver@LIGO.ORG - posted 12:00, Wednesday 18 January 2012 (2063)
BSC6 ETMy STatus
Bland, Sadecki
Yesterday, we worked towards attaching the lower reaction chain to the full QUAD.  We:

- Moved it to the 5-axis scissor lift
- Rerouted and secured the cables on this portion of the chain
- Maneuvered it under the ISI next to the main chain
- Pulled the FirstContact on the ERM HR surface (blew with filtered N2 and drag wiped residual ring around the edge near the ID of the gold coating)
- Pulled the FirstContact from the ETMy AR - found that there was sever streaking on the mass under the FC at the top 3 inches of the sheeting, as well as a smear of FC on centerline, right 3". <- Awww, game over.
- Repainted on new FC sheet with PEEK tab.
- Left it overnight to dry since it was so late in the day.

So, unfortunately we could not get the chain attached due to the FC process.
LHO General
david.barker@LIGO.ORG - posted 10:58, Wednesday 18 January 2012 (2062)
Control room and msr upgrade status

Photo shows that all racks other than the fibre opitcs patch rack have been removed from the MSR and the UPS rack is disconnected from the power circuits at the moment. Underfloor power upgrades are complete. We are still pulling out the old underfloor CDS cabling, carefully while maintaining active systems. A new cable tray has been installed under the floor which cuts across the centre of the main loop. Underfloor drawing is available on DCC 

<A HREF="https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=78581"> Link to D1200078</A>

Images attached to this report
H2 SUS
anamaria.effler@LIGO.ORG - posted 18:44, Tuesday 17 January 2012 - last comment - 09:18, Wednesday 18 January 2012(2060)
H2 ETMY Software
Betsy, Richard, JeffG, Anamaria

ETMY now has an iMac work station near the clean room.

The electronics chain will hopefully be closed tomorrow, once the feedthrough has been cleaned (to my knowledge the last piece missing).

The models are running on the front end, h2susetmy. We've loaded the filters and epics values necessary (using the load_medm_values and prepare scripts in SusSVN), so it *should* all be ok. In order to fix previously mentioned issues of sign flip and dc gain, we've entered dumb OSEM input filters by hand as a simple zero at 10 Hz and pole at 4 Hz. When the scripts are fixed, we will rerun them to get in whatever filters we decide on. We also copied over the damping filters from ITMY, by hand. Had to change some filter bank gains to match production electronics.

Saved a burt file with today's date in /opt/rtcds/lho/h2/userapps/release/sus/h2/burtfiles/etmy/ and committed it to svn. Just in case. 
Comments related to this report
anamaria.effler@LIGO.ORG - 09:18, Wednesday 18 January 2012 (2061)
Typo: pole at 0.4 Hz not 4 Hz.
LHO General
patrick.thomas@LIGO.ORG - posted 18:11, Tuesday 17 January 2012 (2059)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
H2 SEI
hugh.radkins@LIGO.ORG - posted 18:03, Tuesday 17 January 2012 (2058)
BSC8 HEPI State for Initial Alignment
IAS told us we were 1.1mm too South.  I decided this was too far and too unpredictable to move with the Horizontal Actuators attached.  So, we detached them.  The Vertical Actuators are still connected although I want to disconnect/reconnect to relieve stress.

We then cranked the HEPI North ~1mm based on the Dial Indicators.  IAS checked again and said we were now in spec and just 0.4mm South.  I asked Jason about this discrepancy and he corrected his early number to being 1.4mm South.

For the life of me I didn't think I had moved things that far since our alignment back on Dec 21.

Early, Jim & I checked the elevation and level of the ISI Optical Table.  It is just 0.2mm low and shows <0.3mm variation in level.
H2 SUS
betsy.weaver@LIGO.ORG - posted 15:37, Tuesday 17 January 2012 (2057)
ETMy AOSEM s/ns
We swapped the AOSEM with the broken PD.  The S/Ns of the 4 AOSEMs are now:

UL 473
UR 332
LL 428
LR 321
H1 SEI
corey.gray@LIGO.ORG - posted 15:34, Tuesday 17 January 2012 (2055)
iLIGO Hardware Removal: HAM4, HAM5, BSC2

(Corey, Mark, Slim, Zach)

With the Payload extraction from last week, and starting first thing this morning, we were able to empty HAM4 & HAM5, and remove a few more items from BSC2. Today's work occurred roughly from 8:15-11:30 (with a 20min break at 10am after the SEI stack was removed).  All photos for this work is located in Resource Space, hereThis signifies the last removal of an iLIGO HAM SEI from a chamber.  A breakdown of today's activity is below:

HAM4

Removed SEI system (kept Support Table in Chamber).  The Optics Table and Leg Elements were wrapped & bagged.

Note:  Zach found a loose 1/4-20 bolt inside the Optics Table.  This either dropped down there during Payload extract on Fri, or it has been along for a ride for the last few years (and Science Runs).

HAM5

Removed HAM5 Baffle (this will be scrapped for recycling)

BSC2 (& BSC1, BSC3)

Removed (4) Cornucopia Beam Dumps (black glass should be removed off of these guys, and rest tossed for recycling)

Removed (18) Side bolts from the Support Tubes (this is to prevent the need to have someone go into the chamber for BSC SEI extract later).

Removed forgotten allen wrench

Put H1 ITMx & ITMy Suspensions on their stops.

Images attached to this report
H2 SEI
greg.grabeel@LIGO.ORG - posted 09:39, Tuesday 17 January 2012 (2052)
HAM2 HEPI Install

aLIGO HAM 2 has had the old iLIGO stacks removed and replaced with fancy new HEPI piers, frames, and crossbeams. The support tube positions will be checked and fine tuned within the week. Hopefully work can begin on removing the iLIGO HAM 3 stacks and installing the new HEPI structures soon.

Images attached to this report
H2 CDS
james.batch@LIGO.ORG - posted 09:03, Tuesday 17 January 2012 (2051)
New Version of Awgstream installed for Linux Workstations
A new version of awgstream has been installed for Ubuntu workstations which corrects a bug in which not all channel names are read from the nds.  New version is 2.15.5. 
H2 SUS
betsy.weaver@LIGO.ORG - posted 17:42, Monday 16 January 2012 (2050)
ETMy QUAD misc failures
While working on the ETMy today, we also found that one of the 4 PUM flags had a failed glue joint, and one of the PenRe AOSEMs has a broken PD filter.  We reglued the flag and set the heat lamp for overnight.  We'll need to get a replacement AOSEM to swap with the one with the broken filter.
Images attached to this report
H2 SUS
jason.oberling@LIGO.ORG - posted 16:00, Monday 16 January 2012 - last comment - 17:23, Monday 16 January 2012(2048)
ERM Pitch and ETM Vertical Position Measurements

J. Oberling, B. Bland, T. Sadecki

Betsy noted that a cable was rubbing on the side of the LSAT and that this cable was influencing pitch.  She corrected this and I measured the ERM pitch in the single, double and triple hang configurations:

Betsy then put the reaction chain in the double hang configuration and adjusted the pitch to 1.21 mrad down.  I then measured the ERM triple hang pitch again:

This was deemed acceptable for ERM pitch adjustments on the LSAT.

Travis made adjustments to the main chain to lower the ETMy in the quad assembly, then I measured the ETMy roll and vertical position.  Roll is reported as the vertical distance from the ETMy horizontal centerline (measured with an optical level and a scale attached to a carbon fiber rod hanging from the ISI optics table) and vertical position was measured as done on 1-13-2012.

Comments related to this report
betsy.weaver@LIGO.ORG - 17:23, Monday 16 January 2012 (2049)
Pictures attached: The cable interference in the Lower Structure Tooling (LSAT) and then after I unlaced the cable and stuffed it up on the UIM.  I'm not sure how it was envisioned that we use this tooling with cables - this is the first time it has been tried and it's proving to be more work that anticipated.  Likely the cable bundling (the fix) in the tooling still affects the pitch, which will change when we restore the cabling back to it's nominal routing.  So, while we gave up at 2mRad, we know we can get the pitch error smaller in the full hang on the ISI.
Images attached to this comment
H2 SEI
hugh.radkins@LIGO.ORG - posted 17:49, Friday 13 January 2012 - last comment - 13:17, Tuesday 17 January 2012(2044)
BSC8 SEI Stage0 Modified to SUpport ACB Install
JimW, ScottS, Hugh

See the attached which is a zoom in of D0900894 sht2.  The upper right cloud area is the SW corner of the SEI ISI Stage0(+Y,-X) looking up.

We tapped and helicoiled the three holes in the right cloud and one of the 'A' holes in the left (not exactly sure which) to accommodate the planned mounting of the ACB dog clamp and alignment pushers.  These holes were vent holes and were never planned to be tapped.  We were lucky in that they were close enough in size to only lose maybe 25% of the thread holding in the aluminum--plenty fine for the 200lb ACB.
The story is this clamp and these pushers can be removed as there is another clamp on the mounting plate.  And we could swap out the hardware later with vented bolts.
Non-image files attached to this report
Comments related to this report
hugh.radkins@LIGO.ORG - 13:17, Tuesday 17 January 2012 (2056)
Below is Actual entry before system logged me off and I thought all was lost.  Jonathan showed me the drafts and it was saved there.  Thanks!


The Arm Cavity Baffle crew this morning reported holes that were not tapped/helicoiled for the dog clamp & pusher attachment.  These were in the bottom of Stage0.  See D0900894 if you want to follow along or see the attached.

On the attached drawing, I've zoomed in and highlighted the areas of interest.  The cloud circled area to the right is the SW corner(+Y,-X) of the SEI Stage0 looking up.  This is grid area H6 of Sheet 2 of D0900894.  The three holes in vertical alignment on the left with the center one labeled A and the other two unlabeled are the three holes that were planned to connect a custom dog clamp to Stage0.  Problem is only holes marked C are actually tapped and helicoiled for use.  The 'A' hole is the bottom thru vent for the 1/2-13 Stage0 Bottom/Top clamping bolts.  The unmarked holes are the '2' holes called out on sheet 3.  These are fully thru Stage0 Bottom venting the 5/8-11 bolts clamping the Stage0 Spring Post to the Stage0 Top along with a few other things.  The right most 'A' hole in the cloud area was planned to be used with the lower 'C' hole to clamp on an ACB alignment pusher.
On the left side of my zoom-in drawing in the ellipse highlight area, one of the outboard 'A' holes (not sure which) was planned to mount the other pusher in combination with a 'C' hole.

We got very lucky.  Both the A & 2 holes were drilled 0.41" and are plenty deep (inches).  The drill diameter for a 3/8-16 helicoil tap is 0.397".  So we started with a hole 13mils oversized.  The helicoil OD is 0.450".  So we lost 13 of 53mils (assuming the helicoil diameter is the tap OD, which it likely isn't.)  Still we assumed this and figured we lost some 25% of the nominal thread holding in the Stage0 Aluminum.  Since the ACB weighs less than 200 lbs, any one of these even weakened holes can likely hold the entire ACB and it will actually be held by at least four.  So we went to John Worden with this info and he gave us approval to use these thru/vent holes.

So we tapped the 4 holes on the right and 1 on the left for 3/8-16 2D helicoils.  We did this in-situ holding a chip catch under the tap.  I can't lie, I'm sure there are some tap chips that made it under the flooring of the BSC but we did the best we could to catch all the chips.  We swapped out our chip catch for each hole and had no spills.  As the hole was oversized, the tapping wasn't too bad and we flushed the hole with IPA again catching the effluent.  We then ran the cleaned tap into the hole again, flushed the hole again, and then inserted the helicoil.  We tested the holes and then mounted the Pushers.  The right middle 'A' hole must have gotten a little chip under the helicoil but the bolt wasn't too bad going in--it starts fine and threads a few turns before tightening up for just a little bit, then it is fine.

Finally--These vent holes are now not vented and there is a fairly large trapped volume--~20"x.41dia.  Fortunately, the pushers AND the right clamp can come off as there is another clamp in the middle.  And we have a chance to get vented bolts and replace them if needed.
LHO General
patrick.thomas@LIGO.ORG - posted 17:13, Friday 13 January 2012 (2042)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
H1 AOS
keita.kawabe@LIGO.ORG - posted 16:24, Friday 13 January 2012 - last comment - 18:33, Sunday 15 January 2012(2037)
H1 HAM4 optics deinstall (DavidJ, JohnM, Corey, Sheila, Keita)

We uninstalled everything on HAM4.

The followings were bagged and labeled for later reuse for aLIGO itself as well as aLIGO related researches at here and elsewhere:

These are all stored in plastic bins and are temporarily put in the ALS/SQZ work area.

There was a mirror-like thing mounted on one of the side viewports from inside. What is this? It was bagged, but if there's no taker I'll throw it away.

The beam reducing telescopes were roughly wrapped with foils and left in the clean room. Store them wherever you want.

All counter balance masses will go to the recycle bin.

HAM5 baffles was not removed this time.

Corey will post pictures, Sheila will notify Carolyn which iLIGO parts are kept.

Comments related to this report
corey.gray@LIGO.ORG - 18:33, Sunday 15 January 2012 (2047)

Attached are some photos from the work Keita mentions above.

Link to all full-sized photos from the HAM4 Extract are located here:

https://ligoimages.mit.edu/?c=919

Images attached to this comment
H2 SUS
betsy.weaver@LIGO.ORG - posted 16:15, Thursday 12 January 2012 - last comment - 23:08, Friday 13 January 2012(2028)
H2 ETMy ERM soldered pins
Today, when we stuffed the ERM mass into the ETMy lower suspension, we noticed that one of the 5 pins had been somewhat dislodged from it's soldering pool on the gold tab.  Gerardo and Margot believe that this is from the "flipping fixture" which is used to handle the mass.  The fixture apparently sits across some or all of these solder joints.  In the picture attached, the pin is the one towards the 4th one from the right.  
Long story short, Margot thinks we need to revisit the soldering of this pin. 
...to be continued.
Images attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 23:08, Friday 13 January 2012 (2045)
This morning, Margot and Gerardo reheated the soldering joints of the ETMy ERM ESD pins to reseat them.  I used the cleanroom vacuum to help pull away any vapors, etc, but it was a pretty straight-forward procedure.  Gerardo held the pins with tweezers.  No additional soldering material was added.
Images attached to this comment
H1 COC
betsy.weaver@LIGO.ORG - posted 15:32, Wednesday 11 January 2012 - last comment - 14:51, Friday 08 May 2015(2018)
QUAD Glass Mass measured weights
For the record, following are the measured weights of the QUAD glass penultimate masses (PUM) and test masses that are currently here at LHO.  Most of this data can also be found on the CIT optics Nebula we page.  Note the labels of the masses are slightly confusing as the optics have been coated specifically for the one-arm.

MASS     LABEL              INSTALL LOCATION
39,653g ETM02 (TM)    BSC8 ITMy
Didn't measure ITMy PUM because it was the first mass bonded and we were not wise to the need for weights.
39,626g ETM04 (PUM) BSC6 ITMy PUM
39,689g D050421-001 BSC6 ETMy PUM (was lasti mass)
39,613g ETM04 (PUM) 
39,641g ETM05 (PUM)
39,633g ITM01 (PUM)
39,621g ETM03 (PUM)

Comments related to this report
betsy.weaver@LIGO.ORG - 23:30, Friday 13 January 2012 (2046)
We found more weight numbers and I made a typo in my original alog.  The correct table is this:

MASS     LABEL        INSTALL LOCATION
39,653g  ETM02 (TM)   BSC8 ITMy
39,583g  ITM04 (PUM)  BSC8 ITMy PUM
39,626g* ETM04        BSC6 ETMy
39,689g  D050421-001  BSC6 ETMy PUM (was lasti mass)
39,613g  ETM04 (PUM)
39,641g  ETM05 (PUM)
39,633g  ITM01 (PUM)
39,621g  ETM03 (PUM "holy mass" has extra ground recesses) 
39,650g  ITM08 (PUM)
39,616g  ITM05 (PUM)

* Mass weighed with ears/prisms after binding/curing.

- Bland, Barton, Moreno
betsy.weaver@LIGO.ORG - 14:51, Friday 08 May 2015 (18330)

I have reason to doubt the weight listed for ETM02 "TM" - I do not know where this number came from.

Displaying reports 74961-74980 of 76953.Go to page Start 3745 3746 3747 3748 3749 3750 3751 3752 3753 End