Displaying reports 75081-75100 of 76953.Go to page Start 3751 3752 3753 3754 3755 3756 3757 3758 3759 End
Reports until 17:26, Monday 19 December 2011
LHO General
greg.grabeel@LIGO.ORG - posted 17:26, Monday 19 December 2011 - last comment - 17:27, Wednesday 21 December 2011(1937)
Optics Air-Bake Oven

The air-bake oven in the LSB optics lab has had a new controller installed. The controller is capable of handling ramp and soak functions. Large changes to the oven (opening or closing the flue, etc.) will now need the autotune process after the change has been made if an accurate temperature ramping is desired. More info can be found here: Omega Manual. The controller can run a program with 30 setpoints to ramp and soak at different rates and hold times.

Attached is a graph of a ramp up from 40 to 70 degrees in 30 minutes that was run as a test. I will attach a more detailed report to this when it is finished, but if anyone would like to use that oven I will be more than happy to give a run down on how to set it up. This controller really suffers from a Blinking 12 problem.

Also attached is the modified wiring schematic that represents what is now in use for the oven. As you can see the controller will stay on even with the power switch off. This is how I intended it to be, the fan and heater will be de-energized by the switch still.

Images attached to this report
Comments related to this report
greg.grabeel@LIGO.ORG - 17:27, Wednesday 21 December 2011 (1951)
H2 SEI
hugh.radkins@LIGO.ORG - posted 17:25, Monday 19 December 2011 (1938)
BSC8 HEPI is Suspended
With most of the cabling completed we got the Dial Indicators in place and followed that with suspending the HEPI from the double start counter wound Springs.  Of course that means everything is floating--SEI Crossbeams (external blue), Support Tubes (in-vacuum), SEI-ISI & Suspensions.

***  Do not disturb the Blue Crossbeams  ***  Ah heck--DON"T TOUCH ANYTHING, please!


EricA, MitchellR, RichM & Hugh
LHO VE
cyrus.reed@LIGO.ORG - posted 16:31, Monday 19 December 2011 (1936)
Network Switch Moves
The first phase of network switch changes is complete for the coming migration of the iLIGO legacy systems to aLIGO.  Note that there will be short data gaps (1-2 min) from this afternoon in the VE and FMCS data when the connections between switches were moved.
Logbook Admin Feature Requests
jonathan.berliner@LIGO.ORG - posted 16:15, Monday 19 December 2011 (1935)
Add Option for Subsystem Slassification for Tasks Involving Both Interferometers

A soluation may be either checkboxes for relevant interferometers (as was done in the iLog), or list all the subsystems under the "Task" menu when the LHO "Section" is chosen.

This would be useful for classifying tasks such as:

- A subsystem purchases a tool, e.g. romer arm pr camera, for use throughout a site.

- Pcal calibrates a power meter that will be used for all interferometers.

- A seismic event happens that affects all interferometers.

LHO General
jonathan.berliner@LIGO.ORG - posted 16:11, Monday 19 December 2011 (1934)
Monday Ops Log

- IAS working in BSC8, installing corner cube
- Richard and SEI pulling cables
- SLC hoping for Wednesday installation
- Kyle looking for missing ConFlat flanges
- H1 PSL contractor coming Tuesday to lay down linoleum
- HAM1,2,3 - removing optics from HAM3
- Hanford Fire Department on site for testing

H2 SUS
jeffrey.kissel@LIGO.ORG - posted 20:12, Saturday 17 December 2011 (1933)
BSFM Model Updated
See LLO aLOG 2140 for details, but please svn up any local copies of the SusSVN, specifically the ${SusSVN}/sus/trunk/BSFM/ corner of the tree.
H1 AOS
cheryl.vorvick@LIGO.ORG - posted 18:20, Friday 16 December 2011 (1932)
TCS Ring Heater in BSC6 passes the in-vacuum cable continuity check.
The RH installed on the quad for BSC6 had an encounter with the fiber pulling laser, and has a couple burn spots.  I checked the resistance of the RH cabling at connector J9 today, and all wires check out OK, except the RTDs which we knew were broken.

Table of resistances is attached.
Non-image files attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 17:17, Friday 16 December 2011 (1928)
dust monitor moved, loss of communication to dust monitors
The communication to the dust monitors was lost for an extended period yesterday (Thursday Dec. 15, 2011) due to an accidental cutting of a network fiber to the LVEA.

The dust monitor at location 3 in the LVEA was moved into the clean room over BSC8 last night to replace the one previously there. It now has location 15 in the LVEA.
LHO General
patrick.thomas@LIGO.ORG - posted 16:59, Friday 16 December 2011 (1931)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 16:21, Friday 16 December 2011 (1930)
Deenergized IP1,2,3 and 4 in preparation for removal on Monday


			
			
H1 SEI
corey.gray@LIGO.ORG - posted 15:49, Friday 16 December 2011 (1929)
HAM1 SEI Stack & MMT3 Removed From HAM1

(Corey, Mark, Randy, Zach)

With yesterday being devoted to clearing out an already-congested LVEA South Bay (& releasing load on Scissors Table Spring Cups), we started bright and early today on extracting iLIGO hardware from HAM1 [this was all done with only the West door off].

The MMT3 was slid out via the teflon highway, and we slid it onto a mini-surfboard mounted on the forklift.  (This SUS Assembly is now in the Optics Lab)

After this, we removed everything above the Support Table for this Seismic Isolation Stack (i.e. Optics Table, Masses, Springs, etc.).  Minus the Springs, we were asked to wrap & bag all the hardware (this generally doubles the time of the work).  The Optics Tables and Masses are currently wrapped and bagged and in the area near the racks. 

Notes:

Images attached to this report
H2 SEI
hugh.radkins@LIGO.ORG - posted 17:25, Thursday 15 December 2011 (1925)
BSC8 Feed Through Protection in Place
Attached is a photo of the feed thru protection on a flange of BSC8.  We mainly wanted to protect the Triax connectors for the CPS (capacitive position sensor) but of course added them to all the conflats with actual conductors.

Ready for Cable Tray and Cabling.
Images attached to this report
H2 SEI
hugh.radkins@LIGO.ORG - posted 17:20, Thursday 15 December 2011 (1924)
BSC8 HEPI Actuators in Bleed Mode
After setting the Actuators to bleed mode we (Eric & I) powered down the Pump Stations, took fluid samples to look for gross things, restarted just a single pump and set the servo to low pressure (80psi down to 15PSI).  Then one by one, opened the valves to the actuators while watching the pressure changes.  Servo worked as expected throttling back the pump as the pressure increased going to the Actuators.  We monitored for leaks real time and found nothing.  After half the valves were opened, we upped the pressure to 30psi and checked for leaks again.  Still all good.  We final opened up the remaining four valves checking for leaks as we went.

So far all's well--no leaks, servo functioning.
H1 INS
hugh.radkins@LIGO.ORG - posted 17:12, Thursday 15 December 2011 (1923)
HAM2 SEI On Transport Blocks
We (Greg, Scott, Mark) cranked up the HAM2 Scissors Tables and got the Support Tubes on the Support Blocks in the Chamber Nozzles.  The Crossbeam is loose at the top of the external support stack (CAS) so in theory, all the external stuff could be removed.

We also pulled the glass baffle between HAMs 2 & 3 out as well as the metal baffle South of HAM2 at the Mode Cleaner Tube port.
Logbook Admin General
jonathan.hanks@LIGO.ORG - posted 15:56, Thursday 15 December 2011 - last comment - 08:16, Friday 16 December 2011(1921)
Last notice before the logbook goes down for maintenance
The logbook is going down in 4 minutes for maintenance.
Comments related to this report
jonathan.hanks@LIGO.ORG - 16:15, Thursday 15 December 2011 (1922)
The maintenance is complete.

Updates include:
* comments are searchable
* comments can be linked to
* comments may be edited for up to 24hrs by their author
* comments inherit the section/task of their parent
jeffrey.kissel@LIGO.ORG - 08:16, Friday 16 December 2011 (1927)
Thanks for these updates Jonathan! I've tested the editing of comments, and task inheritance with this entry; works well.
LHO VE
kyle.ryan@LIGO.ORG - posted 14:16, Thursday 15 December 2011 (1920)
Vented Y-end
No Tee for purge line -> purging BSC10 volume, BSC6 in cleanroom
H2 SUS
betsy.weaver@LIGO.ORG - posted 13:03, Thursday 15 December 2011 (1919)
H2 ETMy HR FirstContact
Removed FirstContact from EMTy HR, as it was too thin and tore when pulled down for IAS purposes.  Also, there were 6 splatters of FC towards the edge of the optic which needed to be "picked up" with the new sheet that I applied.  Particulate was observed on the surface of the ETMy, but no discoloring.  Attached are pix of the as-received thin FC sheet.
Images attached to this report
H2 INS
michael.landry@LIGO.ORG - posted 12:23, Monday 12 December 2011 - last comment - 05:39, Friday 16 December 2011(1890)
A few images of the BSC8 cartridge insertion
More images to follow (we'll get an entry at ResourceSpace), but for now, some images from Betsy and myself of the Friday cartridge work.
Images attached to this report
Comments related to this report
michael.landry@LIGO.ORG - 05:39, Friday 16 December 2011 (1926)
Four more photos, these ones proofs.
Images attached to this comment
Displaying reports 75081-75100 of 76953.Go to page Start 3751 3752 3753 3754 3755 3756 3757 3758 3759 End