Displaying reports 75141-75160 of 76953.Go to page Start 3754 3755 3756 3757 3758 3759 3760 3761 3762 End
Reports until 18:53, Thursday 08 December 2011
H2 FMP
jodi.fauver@LIGO.ORG - posted 18:53, Thursday 08 December 2011 (1877)
FMP/ICC Prep for BSC8 Cartridge Install
The Y arm cavity bottom was lightly vacuumed, using the same procedure that we typically use on BSC domes (HEPA vac with custom stainless steel brush attached). Mark L. was in the tube and Chris was on the outside. Vacuuming started at BSC8 and proceeded toward GV5. No significant issues were encountered and final inspection showed that the large debris (relative term) that had littered the bottom of the tube was gone. As anticipated, the very fine (mostly metal?) particulate "rain" from the top of the tube was not significantly improved by vacuuming.

Since the Apollo crew was in the neighborhood, we also installed the BSC flooring (without hardware at this point) and a 60" dust barrier to facilitate the upcoming Arm Cavity Baffle install.
H2 SEI
hugh.radkins@LIGO.ORG - posted 18:25, Thursday 08 December 2011 (1876)
BSC8 ISI Prep for Cartridge Lift to Chamber
SEI--Jim Corey & Greg
Once we got the all-clear from SUS for their tests and Vincent for our ISI tests we started preparations for transport.

Trillium cable end repairs were made.
Cabling was disconnected at the Feed thrus and tied off back on Stage0--we may need to move some of this for insertion clearance.
Dummy Feed-thrus were removed from the Test Stand to ease access clearance for future activities.
The Keel Mass was removed along with the other Stage2 balance weight on the sides.

-Hugh
H2 SEI
vincent.lhuillier@LIGO.ORG - posted 18:00, Thursday 08 December 2011 (1875)
ISI-BSC8 Tests

The ISI-BSC8 was tested on December 6 and 7. It went smoothly. I have attached a sum-up of this 2-day test. Further details will be given in E1100845.

Non-image files attached to this report
H2 SUS
betsy.weaver@LIGO.ORG - posted 17:18, Thursday 08 December 2011 - last comment - 17:35, Tuesday 13 December 2011(1874)
BSC8 SUS Cartridge Install Prep
This afternoon, after the final B&K hammer measurements were complete, and SEI locked the ISI and began their preps, I began securing the FMy and ITMy for lift-off.  Because the First COntact that was on the ITMy HR was many months old, and had been peeled down for IAS purposes numerous times over the last 2 months, I removed it and put a fresh coat on, including a new tab at the top.  I observed a lot of particulate on the optic after the peel and attempted to remove them with alpha swabs and the N2 gun (gun also used intermittently during FC removal).  This was cumbersome and while doing it I (and Corey over my shoulder) noticed some streaking pattern not from the First Contact, as well as some First Contact PEEK mesh patterning on the optic.  More pictures to come.  So, I gave up on the dabbing and blowing and reapplied the new FC coating.

Then, I secured all of the EQ stops on both the FMy and ITMy, with the exceptions of:
- 2 nuts (missing) - one on each UIM side stops, and
- the ITMy Top Mass Blade Stops, which require removing the Top Mass BOSEMs.  The masses and blades above and below are rock solid however, so this is fine.

I then added the new "finger" assembly which acts as a 20mm gap stop between the ITMy AR and the CP HR.  This assembly, however hangs down below the QUAD structure and may be a problem for the cartridge, but is easy to remove tomorrow if needed.

I also added the transport pins to the vibration absorbers on both suspensions.

I covered the FMy.
Comments related to this report
corey.gray@LIGO.ORG - 12:48, Friday 09 December 2011 (1880)

I took some over-the-shoulder photos of the H1ITMY as Betsy was working on it.  The photos are in ResourceSpace, here

It's hard to manually focus on the stuff we were looking at, but I think we have a few photos where we were able to capture some of the particles/marks on the surface of the optic.  Saw a little bit of everything as far as contaminants on the mirror surface:  dried liquid stains, dust particles, chunk of First Contact (due to a hole on the First Contact film), and some weird patterned ("pixel-ated" Matrix-esque) marks.

Gripes about ResourceSpace:

  • Why can't we have individual captions for every photo instead of the useless caption which just has a date & time.  I named each of my photos, so you can sorta get some info about each photo under the "Original File Name" field.
  • Wish we could edit the order the photos are arranged in Collections.
corey.gray@LIGO.ORG - 13:00, Friday 09 December 2011 (1881)

Grrrr.....yeah, it's not intuitive how to post Resource Space links (yet another gripe). 

Anyways, the REAL link for the photos I took are here:

https://ligoimages.mit.edu/?c=877

 

betsy.weaver@LIGO.ORG - 13:40, Friday 09 December 2011 (1884)
Further to Corey's elog regarding the contamination pictures of ITMy, following is my note to COC:
Yesterday, I removed the old FC from the ITMy HR and reapplied a new coating with a thin tab at the top which can be peeled in-chamber.  Corey managed to take some great pictures of this and they are posted at the link on ResourceSpace below.  (Note, the pictures are always uploaded in reverse order so the first picture is my new FC coating.)  Long story short, there are 4 things to note regarding the surface of this optic:

1) Overall particulate - lots still on the surface - like 10-20 per square inch - Ugh.  Performed the dabbing technique but gave up after a short stint because it seemed futile.  (Used lots of N2 filtered DI gun flow throughout, which helped some but not enough.)

2) PEEK Mesh pattern seen down front of optic (recall, we applied a long tab back in Oct when we bantered about the idea to tear down a strip for IAS purposes.  In the end we didn't do this and the full tab just pulled the whole top of the circle down for IAS).  You can see the "matrix" like pattern in the center of the optic in some of the pictures.

3) When I pulled the FC circle, a little square tab stayed on the optic when I got down to just below center.  Weird.  It's like it had a cut and the FC peeled around it.  I stopped pulling and pulled the circle in such a way to pull up the tab.  A small horizontal line roughly 3mm in length remained on the optic almost on center line and a 1-2 inches to the right of center (when looking at the face).

4) A very strange "watermark" was apparent streaking across the top of the optic - very apparent in some pictures.  It looked very reminiscent to me of the purple markings we observed on many iLIGO optics.  Not sure what this is.  Defect in the coating maybe - I have not looked up the CSIRO report.

As stated above, all of this was observed and then I reapplied a new FC coating as shown in picture 1 on the link.
betsy.weaver@LIGO.ORG - 16:30, Tuesday 13 December 2011 (1899)
Today, Cheryl and I re-inspected the ITMy HR surface, which now has the ~week old First Contact sheet on it.  My subsequent email to GariLynn:

Hi GariLynn -
So, the good news is, the blue streaking that ran horizontal in a band across the ITMy HR peeled off with the new FC.  The bad news is, Cheryl has pictures of a newly observed band of contaminant running around the surface of the HR surface within 1" from the edge (so outside of the FC ring).  She'll post pictures soon of today's observations.

I will indeed need to do a fresh application/pull after all IAS needs are complete in order to pull any more streaking likely to be induced when we do the pull-and-close technique a few times over the next few weeks with this new FC sheet.  Not sure how we can get away from doing this in the future - maybe we just leave it exposed?  Then we risk particulate accumulation which seems worse (as FCing over particulate may scratch, and the amount of particulate is likely to be too much to remove via dabbing).

Not sure what the new stuff is - I'll make a larger diameter FC sheet next time.

-Betsy
betsy.weaver@LIGO.ORG - 17:35, Tuesday 13 December 2011 (1905)
Cheryl's pictures from today:

https://ligoimages.mit.edu/?c=883
H2 PSL
michael.rodruck@LIGO.ORG - posted 16:31, Thursday 08 December 2011 (1872)
H2 PSL dust counts

On the night of the 5th, the HEPA fans were turned off for noise measurements. Dust levels still look good during this period. The attached file is a 3 day trend, with the time with no HEPAs roughly indicated by the black lines. 14 is the anteroom, 13 is the laser room.

Images attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 16:25, Thursday 08 December 2011 (1873)
CP1 and CP2 overfilling
The recent installation of permanent heat traces around the LLCV needle valve valve bodies for CP1 and CP2 solved 1/2 of the nuisance freezing problem.  Now the actuator box is freezing up (These units were installed upside down for some reason and are prone to moisture entry and subsequent freezing) -> I am using drop lights with 25 watt bulbs as general heat sources as an interim solution for now.  

Operators note that I'm am monitoring CP1 and CP2 levels periodically and additional alarms are likely overnight.  No action is required.
LHO General
patrick.thomas@LIGO.ORG - posted 16:18, Thursday 08 December 2011 (1871)
Ops Summary
I covered from ~12:45 - 4:00.

Work on upgrading the FMCS system.
Preparation for cartridge install.
Fiber from LVEA H2 electronics rack to H2 DAQ accidentally cut.
LHO General
patrick.thomas@LIGO.ORG - posted 16:07, Thursday 08 December 2011 (1870)
plots of dust counts
Attached are plots of dust counts > .5 microns.
Non-image files attached to this report
H2 FMP
cheryl.vorvick@LIGO.ORG - posted 15:15, Thursday 08 December 2011 (1869)
Y Arm Beam Tube Pictures:
This is a follow up to Jodi's alog here, showing the pictures I took of the stuff we found.  Images show the range of particulate that was found, which includes white thread, small bundles of glass fibers, metal, and some stuff we couldn't identify.  

White fuzzy / thready particulate was very prevalent.  Other particulate was rare, so for example, only one red item was found, I only took two pictures of what looked like bundled glass fiber, and there was only one area where there was brown stuff stuck to the beam tube wall.  The pictures of the o-rings show that there was a significant number of particles on and in between the o-rings.

Picture names have the description of what's in the picture.
Images attached to this report
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 13:13, Thursday 08 December 2011 (1868)
H2 ITMY Tap Tests
Today, impulse response tap tests on the ITMY QUAD were performed with the ISI floating.  The following plots are of the response for the 7 locations with each X,Y,and Z DoF plotted. Descriptions of the tap locations are below.

ITMY 

location1 - cross brace on reaction side in front of PUM - 
location2 - just between pum and uim vertical brace from clean side to beam tube
location3 - straight cross brace between uim and R0 
location4 - cross brace beside pum on clean side downwards 
location5 - cross brace beside R0 clean room side hitting upwards 
location6 - beam tube side - vertical brace beside M0 hitting towards clean room 
location7 - straight cross brace between M0 and UIM downwards. on ITM side 
Non-image files attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 09:12, Thursday 08 December 2011 (1863)
CP2 overfilling
Trace heat for liquid-level control valve valve stem is working -> actuator arm is frozen in this case.  I will use a heat gun to thaw-out then evaporate moisture, also try and seal.  
X1 SEI
corey.gray@LIGO.ORG - posted 08:34, Thursday 08 December 2011 (1851)
HAMISI#1: Balancing, Locker Shims, Locker Horizontal Position, & Actuator Alignment

Here is work from Wed....

Vertical Adjustment of Shims

Tues night, we found the tips of the Springs to be higher than the base of the Springs.  So, the 0.126" Shims under the Lockers were swapped out for thinner Shims.   This brought the tip/base Spring difference to around our tolerance of 0.015".  The ISI was then balanced.

Current Locker Shims:

Horizontal Adjustment of Shims

With the dial indicators, we were able to monitor float/locked positions of ISI.  Horizontally, we saw an overall counterclockwise twist (saw dial indicator changes on the order of 0.007-0.018".  So, we went about re-positioning the Locker Bases. 

(I'm noting procedure here mainly for my own records)The ISI was unlocked, the Dial Indicators (DI) were zeroed.  Then at ONE Locker, we loosened the Base bolts & Locked the locker.  Due to friction/sticking between the Locker Base and the Stage0 floor, you will probably see some Stage1 motion.  If you do, just tap on the Locker Base to free up your Base & to keep your DI at zero.  Once the Locker is locked, and the DI says zero, one can start tightening the Locker Base to Stage0.  Unlock the Locker (rezero DI if needed), and re-Lock, and confirm the change in state is within 1-2 thousandsths.  Repeat for remaining three Lockers.  After we did this, when we re-locked the system it did so without binding up the 4th Locker---a good thing.

For the most part we are mostly done with this ISI, EXCEPT, it was noticed the installed-Actuators aren't "aligned".  When they were removed off the ISI, they first had their Set-Up Bars installed to "lock" their alignment.  Either they weren't aligned before, or they Set Up Bars weren't installed correctly, and we've lost their alignment.  Each Actuator will need to be pulled off, re-aligned on a work bench, and then reinstalled.

H2 INS
michael.landry@LIGO.ORG - posted 04:45, Thursday 08 December 2011 (1861)
Towards cartridge insertion at BSC8
Steady progress is being made towards cartridge insertion at BSC8, likely late this week Thu/Fri.  Items underway include:

-The cleanroom at BSC8 was swapped out for the shorter, modified variant.  We had neglected to account for a known interference, that of the gate valve stem (and box works mounted there), when lowering the cleanroom to fly the cartridge and center over BSC8.  The shorter extent (as aligned along the Y beam axis) allows for the cleanroom to be lowered without interfering with the gatevalve.  Small modifications to the work platform/railing were made to limit interference there as well.

-At the y-manifold/cryo pump area, the H1/H2 optical lever piers and table, and TCS laser were removed, and plumbing under the beamtube modified (TCS chiller lines removed, purge air modified) for clear access.  De-installation here allowed for the arrival of cleanroom, cleaning of the area, and eventual spool extraction.  The driver is the vacuuming of the y-manifold, part of the in-chamber cleaning effort, intended to limit a particulate source near the recently brushed and cleaned BSC8.  Vacuuming is to take place prior to cartridge insertion.

-At the cartridge test stand #2, SEI software transfer functions completed and the ISI was locked up, and final power spectra obtained.  Both suspensions remain unlocked.  In an effort to pulse and vet the ESD cabling, we removed an iLIGO feedthru from HAM8 with the appropriate connector type; this failed as described in R. Abbott's earlier alog, and will require an in situ retrofit of the ESD cabling (a limited run from the feedthru to a connection point affixed to the ISI)
H2 SUS
jeffrey.garcia@LIGO.ORG - posted 23:25, Wednesday 07 December 2011 (1860)
FMY Impulse Response tests
Attached are plots of the 7 tap test locations on the FMY performed yesterday afternoon. Data was exported from the PULSE software to a text file and imported into Matlab. For this measurement, a metal tip on the B&K hammer was used as opposed to the rubber tip used in previous measurements.  A new template ("Simple Hammer Display 3.pls") in the PULSE software was used according to T1000697-v2.

The plots each have the 3 DoFs from the accelerometer used and are plotted according to location.  The FMY M1 Damping Loops were closed and the ISI floating.  The plots show the response trending upwards from ~100Hz and higher as in previous results.  However, previous measurements saw this upward trend in magnitude beginning from ~10Hz.  Here, the trend is a decrease in magnitude from the lowest frequencies to ~100Hz.  

For these measurements, the accelerometer was placed on the back side of the FMY (i.e. the side facing opposite the ITMY) due to accessibility. A description of the locations on the FMY are as follows:

location1 - back side of fmy beam tube side just above the accelerometer
location2 - side of M2 hitting away from beam tube
location3 - M2 cross brace downwards
location4 - M1 cross brace downwards - straight cross brace
location5 - top side from beam tube going away - above M1
location6 - straight cross brace on M2 on clean room side
location7 - cross brace on M2 clean room side

Data was also taken for the ITMY QUAD structure, however, there was a data corruption issue encountered in data from 5 of the 7 locations.  Measurements on the ITMY QUAD will be re-taken with time permitting before cartridge install.
Non-image files attached to this report
H2 FMP
jodi.fauver@LIGO.ORG - posted 21:55, Wednesday 07 December 2011 (1859)
Y-Arm Cavity Inspection and Documentation
The spool piece by GV5 was pulled to allow access to the section of the arm cavity leading toward BSC8. Once the spool section was out and the Arm Cavity Baffle removed, Cheryl V., Mark L., and I went into the cavity to conduct an assessment of particulate content and document what we found. (As you may recall, this expedition was first contemplated during ICC at BSC8 because of the quantity of "detritus" that we found at the drop-off between the chamber nozzle and the larger diameter Arm Cavity.) Our objectives were to assess both the quality and quantity of "detritus", determine whether there appeared to be a gradient in the location of "detritus", get good quality close-ups of items in-situ, and to collect samples of various items. We accomplished all of our goals and the preliminary results are listed below:
1. The quality of "detritus"-Seems to be very similar to what we've found during in-chamber cleaning (pieces of glove, thread, "fluffy" fibers, metal fragments including what looks to be Al foil, "goopies" of various kinds, and a very fine patina of metal "dust")
2. The quantity of "detritus"-Again, very similar to what has been found in chambers (Cheryl will attach some pix to this post when she gets a chance.)
3. There does not appear to be a gradient in the quantity of "stuff". We thought we might see more "detritus" close to the BSC or gate valve but that does not seem to be the case. The "crap" seems to be quite evenly spread from gate valve to BSC...
4. Cheryl got some great pix including the fine metal dust falling from the top of the tube and the gate valve on the north(?)side of BSC8 showing its amazing quantity of "detritus"
5. We were able to collect several samples for Robert S. and others to look at.



H2 SUS
rich.abbott@LIGO.ORG - posted 20:03, Wednesday 07 December 2011 - last comment - 12:35, Thursday 08 December 2011(1858)
Test of ESD Cableing Integrity
Performed a test of the ESD cabling associated with the BSC8 cartridge.  A time domain reflectometer was used to verify the integrity of the coaxial cable from the vacuum side connector down the suspension chain leading finally to the reaction mass ESD actuator.  Discovered that 3 out of the 5 coaxial paths were bad.  Cause traced to a failure of the solder joints used to attach the coaxial cable to the PEEK custom connector.  The joints were baked at 200 degrees C in the vacuum bake process.  The solder used has a melting temperature of 184 degrees C, which resulted in a complete failure of these connections.  Even the two that tested good rapidly failed when tension was applied to the connections.

After a conversation with John Worden and Mike Landry, we elected to leave the majority of the cabling intact and to re-terminate the coaxial cables in a new connector after the cartridge is installed.  The 5 coaxial cables will be drawn through the aperture of the conflat feedthrough and a new connector will be installed in situ.

All of the five cables appear intact and correct aside from the failure of the vacuum side conflat mate.
Comments related to this report
mark.barton@LIGO.ORG - 09:39, Thursday 08 December 2011 (1864)
For reference, here are some pictures of Rich's setup:

 1. The front panel of the TDR (time domain reflectometer) box used by Rich. This particular unit is very old and failing, and a modern replacement is being procured, but the new one will be similar in concept. The screen shows the output for a 15' test cable with an open circuit termination. The horizontal scale is set to 2" per major division, and a fairly clean reflection from the end of the cable can be seen. (A short circuit would have given a reflection of opposite sign, and a impedance-matched termination would have given little or no reflection.)

2. The output for channel 1 of the ESD (viewing the connector as a boat shape and counting left-right, top-bottom). The horizontal scale is now 5' per division and the horizontal position has been set to put the section of the trace representing the 15' of test cable on the outside of the vacuum flange offscreen to the left, so that the visible portion represents only the in-vacuum cable. There is a more complicated shape reflecting the different impedances of the conductors in the chain and the capacitance of the electrodes at the end.

3. The output for channel 3 of the ESD. It is quite similar to ESD 1. These traces can serve as a provisional reference for what a working channel should look like. (There may be slight differences when the connector is repaired, and/or the TDR is replaced.)

4. The connector falling apart in Hugh's hands. There is supposed to be a gold pin on the end of each inner conductor, but the solder has melted and several of the pins have come off.

Mark B.
Images attached to this comment
mark.barton@LIGO.ORG - 12:35, Thursday 08 December 2011 (1867)
Rich spotted a typo in my earlier comment: the horizontal scale in the first picture is 2' (feet) not 2" (inches) per division.
H2 SUS
jeffrey.kissel@LIGO.ORG - posted 18:42, Wednesday 07 December 2011 - last comment - 14:32, Thursday 08 December 2011(1852)
H2 SUS ITMY M0, Long to Yaw Coupling Investigation
In order to investigate whether the Length modes coupling into H2 SUS ITMY M0 Top2Top Yaw transfer functions are real or noise, I've taken a high resolution (2 mHz) measurement of the same transfer function (same amplitude, BSC-ISI unlocked but undamped, ITMY M0 damping OFF, ITMY R0 damping ON).

I attach three plots for discussion. 
(1) A full-frequency-range plot measurement itself, 
(2) A zoom in on the resonance that we've been concerned with, and
(3) A plot of what cross-coupling we expect from the model (i.e. zip, nadda, zilch).

Note that neither of the first two plots are calibrated properly, but the relative amplitude should be accurate

One can see from the full-range plot that not only is the lowest Longitudinal mode present (at 0.43 Hz), but the second L mode (at 0.98 Hz) also creeps in. Regrettably, I'm now convinced that this (these) resonances are actually a measurement of physical motion, not just unlucky in coherent noise.

Now, is it a show stopper? No (yet).

A useful tip from the good Dr. Lantz: physically cross-coupled modes typically show up as pole-zero pairs, as opposed to what we see here -- just a sharp pole.

Other pertinent information: the excitation for this drive is a continuous, broad-band, white noise excitation across the measurement band, for the duration of the measurement. You'll note in the second plot attached (upper right panel), that the coherence (i.e. the measure of the *linear* coupling) between the Y drive and this particular L resonance is ~0.25, which is roughly consistent with what we know to be noise in the rest of the band. 

However, the lower right panel shows the OSEM basis response of F2 and F3 to Y (in PHASE); the sensors that compose this DOFs Euler basis signal. Here, (though it's tough to see with the black cursor overlayed -- sorry) the sensors are identically in phase, implying real longitudinal motion.

Why don't I think this is a show stopper (yet)? We have found from experience that moving around these suspensions, after locking and unlocking, that these sharp cross couplings come and go. Case and point -- we don't have a smoking gun of what might have happened between the 2011-11-19, 2011-11-29, and 2011-12-02 measurements that might have caused such a gradual increase in coupling, except for *better* aligning the chains. Further, I expect that the coupling will be significantly reduced once we take a similar measurement with damping loops ON (we'll be sure to confirm this of course) -- which is the default "plant" upon which we'll apply ISC control loops (if there are any at this stage). 

But most importantly, let's just see what we get after we install the cartridge. We'll have to lock and unlock the suspension, and will have to do another round of BOSEM centering (in and out, not necessarily laterally). We may get lucky and the coupling may be reduced, or we could get unlucky and have much worse coupling. Further, we have yet to use what's in our digital back-pocket: diagonalizing the drive using sensors. This may help as well. From what I've seen of the remaining degrees of freedom, I'm confident that the suspension's mechanical system is behaving well.

--------------------

Data for this measurement can be found here:
{SusSVN}/sus/trunk/QUAD/H2/ITMY/SAGM0/Data/20111207_1700_H2SUSITMY_M0_Mono_Y_0p002to50Hz_TF.xml

Non-image files attached to this report
Comments related to this report
jeffrey.kissel@LIGO.ORG - 14:32, Thursday 08 December 2011 (1866)
B. Lantz, J. Kissel, B. Shapiro

Brian guesses that this excess cross-coupling maybe be from air currents in, on, and around the suspension.

The notes leading up to the hypothesis:
- The amplitude at this frequency (0.43 Hz) in both the Yaw2Yaw and Yaw2Long transfer function is incoherent (~0.2 coherence, consistent with what we know is noise, or non-linear coupling at other frequencies).
- One difference between the 2011-11-29 measurement and 2011-12-02 measurement is that the BSC ISI is unlocked (and undamped), and we know the BSC-ISI "is a big sail" when it comes to air currents**.
- The clean room forces air current to move in, on, and around the QUAD, as well as the BSC-ISI.
- Remember F2 and F3 are the Long (in common) and Yaw (in differential) sensors; they're in line with the vertical center of mass at the top stage.
- OSEM response to linear drive goes incoherent on *expected* resonances, because the SUS is swinging with large amplitude outside the (linear) range of motion of the Flag/LED/PD system (think -- at the edge of the range, the signal flat-lines at open or closed light and is no longer proportional to the drive). Non-linear response to drive = still get amplitude, but no coherence. 
- "The OSEMs are linear to "+/- 0.7 mm" peak to peak." I put in quotes, because though this is the number we always quote as a spec, this number is eye-balled from the curves measured of a few OSEMs, on an independent jig, ideally aligned. Mark has shown the linearity to vary with alignment (see T1100455) and we know OSEMs can have ~50% variability in sensitivity). 
- Suspension Q's are "a billion," so we often cannot resolve their actual absolute motion.
- Another plot is attached -- the calibrated amplitude spectra of the motion during the transfer function excitation, and after late at night during a quiet time (thank you data stored in frames!).

The hypothesis:
- Air currents are exciting the longitudinal mode by lots, but in an incoherent manner (such that it might be misconstrued as yaw). Because there is so much incoherent motion, it bleeds into the yaw sensors, and therefore into the amplitude of the transfer function.

Devil's Advocate questions:
- Why would there be so much more motion at longitudinal, vs. other degrees of freedom?
     (Not sure. BSC-ISI Y [not yaw but cartesian Y, aligned with IFO arms, and therefore ITMY's L direction] resonances are at )
- Wouldn't the air current excitation be broad-band? 
     (Well -- so is the intentional excitation. We insert uniform white noise across the measurement band as our excitation)
- Is there really a mechanism where longitudinal motion can be sensed as yaw? 
     (If, for example F2 goes non-linear before F3 as the pendulum swings through the edge of OSEM range in L, then you'll get more amplitude in F2 than in F3; a differential signal, which appears as yaw.)
- Why don't we see the same coupling on the reaction chain? 
     (We did -- in the 2011-11-29 measurement (see page 6, magenta curve of allquads_111202_H2SUSITMY_ALLR0_TFs.pdf), arguably just as strongly, but it went away in the 2011-12-02 measurement)
- Why don't we see anything on FMY?
     (Maybe because FMY is not aligned with any of the fundamental modes of the BSC-ISI?)

**Auxiliary/Curiosity Questions: 
- What're the BSC-ISI Modes in the L degree of freedom?
     (See second attachement -- for this QUAD and ISI, the L and Y/RX modes are roughly aligned. for the BSC-ISI, those are at [1.0, 1.75, 5.15, 6.95 ] Hz)
Non-image files attached to this comment
H2 PSL
benno.willke@LIGO.ORG - posted 23:03, Friday 11 November 2011 - last comment - 06:15, Thursday 08 December 2011(1718)
PSL instalation status
Yesterday evening the laser was shut down due to a lid violation error. During the attempt to install the rf-summation box inside the 35W front-end box, we had made a mistake in the activation of the lid-overwrite, which is required to safely open the FE box. As we did not completely understood what happened we decided to leave the laser in the off state overnight.
Today the laser was restarted and run the full day without any problems. The currents of the HPL diode boxes were adjusted to the following values:
DB1: 50.5A
DB2: 49.1A
DB3: 48.9A
DB4: 49.2A

We installed and tested the water flow sensors for the water cooled power meters. All three flow sensors were set to switch at 1.5 l/min. If the flow is too low , the shutter of the high power lasers is automatically closed. With this system in place we can now operate the PMC overnight.

We continued to work on the beam path from the PMC pickoff port to the reference cavity. With the PMC transmitting 142W at the IO interface we get 387mW in the FSS beam path (measured directly infront of the FSS-AOM). The AOM is aligned to a double path efficiency of 59% such that 225mW are measured directly after the PBS downstream of the double passed AOM. (VCO_MOD_LEVEL 32000 in FSS MEDM screen, all power levels measure with an OPHIR 10A-V2-SH power head). A WinCam scan of the single path pattern is attached. The modematching was adjusted to give a 75% dip in the reflected light while scanning over the TEM00 mode of the cavity. The transmitted peak of the largest higher order mode has about 10% of the peak heigth of the TEM00. 
Images attached to this report
Comments related to this report
oliver.puncken@LIGO.ORG - 06:15, Thursday 08 December 2011 (1862)
The pump currents we used before were:
DB1: 50.3 A
DB2: 48.3 A
DB3: 49.0 A
DB4: 49.3 A
Displaying reports 75141-75160 of 76953.Go to page Start 3754 3755 3756 3757 3758 3759 3760 3761 3762 End