Displaying reports 75821-75840 of 83093.Go to page Start 3788 3789 3790 3791 3792 3793 3794 3795 3796 End
Reports until 16:52, Wednesday 21 August 2013
H1 SEI
hugh.radkins@LIGO.ORG - posted 16:52, Wednesday 21 August 2013 (7507)
WHAM6 HEPI L4-C Leveling Status
After wiring up the HEPI L4-Cs to confirm they were good, I saw that two were not like the other two.  So I though they were bad and did some wiring swaps to troubleshoot the problem.  This told me it was indeed the L4-C or its local wiring.  Then I leveled them and they look fine now.  Did not realize it would be so obvious.  3 of 4 corners now level with the SE corner 3 still to do.  More visuals on the morrow.
H1 AOS
cheryl.vorvick@LIGO.ORG - posted 16:15, Wednesday 21 August 2013 (7506)
TMSX ready for new rounds of TFs
Prep for move:
- last nights TFs corrupted by "reversed"  magnets 
- cable swap fixed the situation  (LF/RT and F2/F3)
- bosch frame wrapped in foil to calm the air current effect on TMS
- genie left out to get the best isolation for TMSX TFs

Other:
- picture of one 2" optic on TMS ISC table shows some particulate
- particulate seen on all 2" optics
- level of particulate is low enough that blowing off the surface is sufficient
H1 INS
jodi.fauver@LIGO.ORG - posted 16:09, Wednesday 21 August 2013 (7505)
TMSX cleaning prep
In preparation for helping Cheryl clean the TMS assembly prior to its move out of the lab, I hauled a Tiger Vac and accoutrements down to the End Station. I wiped down various parts, assembled the vacuum,and applied a C-3 hose cover. The vacuum, a custom Class B attachment, and other items were placed in the lab, ready for use.
LHO General
corey.gray@LIGO.ORG - posted 16:02, Wednesday 21 August 2013 (7504)
Ops DAY Summary

Activities from today:

H1 PSL Shutter closed (Mike/Justin)

LLO Xarm Pcal Periscope craned/crated today (Rick, Pablo, Colin)

HAM6 HEPI work:  Elec check, L4C adjustment, Actuator work. (HUGH)

Tour around 1115-noon

Starting PSL Models

SUS reboot to reproduce matrix problem (Dave)

GV6 work with aux.pump cart noise this afternoon (Kyle)

TMS crew (Jeff, Andres, Cheryl) working at EX.  The Bosch Stand is now wrapped in foil (to limit winds).

H1 INS
jodi.fauver@LIGO.ORG - posted 15:59, Wednesday 21 August 2013 (7503)
Final iLIGO Large Optics removed from suspensions
Chris Soike and I spent the afternoon de-suspending the last three iLIGO large optics (2@MMT and 1@RM) from suspensions. The optics were placed in cake tins and verified ready for shipment to CIT for storage. 
H1 SEI
vincent.lhuillier@LIGO.ORG - posted 15:27, Wednesday 21 August 2013 (7502)
Progress at BSC1

HEPI:
I checked out the HEPI system. It looks good however the horizontal actuator in corner 3 seems to be a little bit weaker (15%) than the other horizontal actuators. It's not an issue since it will be corrected with the actuator symmetrization filters.

ISI:
Due to the HEPI rewiring, I recomputed the feedforward filters from the HEPI to the ISI.

H1 CDS
david.barker@LIGO.ORG - posted 10:51, Wednesday 21 August 2013 (7500)
h1sush56 models restarted repeatedly

To investigate the matrix settings problem I restarted all the models on h1sush56 (including the IOP) many times. I was not able to reproduce the problem. These models are now running and burt restored to their safe.snap.

H1 PSL
david.barker@LIGO.ORG - posted 10:41, Wednesday 21 August 2013 (7499)
PSL front end models restarted with new code

WP4093 Christina, Patrick and Dave.

We restarted the H1 PSL models h1psliss and h1pslpmc with new code Christina installed yesterday.

H1 PSL
christina.bogan@LIGO.ORG - posted 10:33, Wednesday 21 August 2013 (7498)
Level 3 maintainance of high power oscillator
[Patrick, Christina]

We did a level 3 maintainance of the high power oscillator, this includes an optimization of the pump diode currents as well as the temperature of each diode. Afterwards we set the the diode currents to 100% again. This increased the output power by about 15% inside the oscillator box. 

Next step is to check the calibration of the photo diode signals.
H1 SUS
arnaud.pele@LIGO.ORG - posted 20:09, Tuesday 20 August 2013 (7496)
TMSX TF

Started TMSX transfer functions from DTT. Measurement will run overnight

H1 SUS
arnaud.pele@LIGO.ORG - posted 19:28, Tuesday 20 August 2013 (7495)
OSEM2EUL matrices TMSX and IM1

[Dave Kiwamu Arnaud]

Today, we discovered that top mass OSEM2EUL matrices were set to 0 for TMSX and IM1. Also, they were frozen, and would go back to 0 right after trying to set a value in any of the slots. The recorded burt files show that values were 0 since august 30th, when rcg was updated to 2.7.

The problem was fixed by restarting the models

Stuart has been reporting a similar issue at Livingston

H1 ISC
sheila.dwyer@LIGO.ORG - posted 19:09, Tuesday 20 August 2013 (7494)
Picomotor controller 5
Picomotor controller 5 is not sending the correct readback to beckhoff, (the power on, pin 7 on the readback cable for example).  I pulled the unit and it is in the shop, I will find a tester for it in the morning.  Controller 4 is having similar problems, but I did not pull it. 

LHO General
thomas.vo@LIGO.ORG - posted 18:58, Tuesday 20 August 2013 (7493)
08/20/2013 Ops Summary
- PCAL working on LLO-Y periscope

- PSL crew work ongoing

- Sprague spraying down beam tube enclosure

- TMS crew at EX

- EY ion pump signal goes down for rerouting cables

- LN2 delivery at EX

- Kyle at GV5

- Cyrus reconfiguring and rebooting the vacuum LX VME crate

- Upgrade H1 PSL front end models
LHO VE
kyle.ryan@LIGO.ORG - posted 18:44, Tuesday 20 August 2013 (7492)
CDS control of CP2 liquid level lost
CP2 overfilled following Cyrus' reboot and BURT restore of the LX VE rack this morning -> The instrument air for CP2 indicated red or "STOP" on the MEDM screen as expected but was actually enabled as if in the "START" state -> Normally, we would be required to manually enable or "START" this via the MEDM screen following a reboot/restore and it would then indicate green -> Investigation showed a "fail" light associated with a 2210 card was on following the initial reboot -> Cyrus replaced this card, rebooted and BURT restored again -> I confirmed that the LLCV valve was now closed when the MEDM indicated "STOP" -> Later I noted that the LLCV remained closed even with 100% open PID output and with the instrument air "START" condition, i.e., the LLCV was not opening regardless of the PID output value or the enable state of the instrument air -> I confirmed that there weren't any rack fuses "lit" or open 

For now, I manually filled CP2 to 105% (boil-off rate ~2.5%/hour) and will come in early in the morning and manually fill again etc. until we find the problem.
H1 IOO
kiwamu.izumi@LIGO.ORG - posted 18:26, Tuesday 20 August 2013 - last comment - 08:36, Wednesday 21 August 2013(7490)
IMC ASC characterization

[Stefan, Kiwamu]

 As a part of the commissioning wrap up porjects we characterized the IMC ASC control.

Adjustment of UGF:

Change in servo shapes:

Adjustment of Output matrix for DOF3:

Some other changes :

Images attached to this report
Comments related to this report
kiwamu.izumi@LIGO.ORG - 08:36, Wednesday 21 August 2013 (7497)

Also we implemented a flat gain (of 1e-4) in FM7 for DOF1 and 2 such that  the displayed gains are at around 1 as they used to be too small to display.

LHO VE
kyle.ryan@LIGO.ORG - posted 18:21, Tuesday 20 August 2013 (7491)
Resumed leak testing of GV6 -> Restored nominal Corner vacuum valve pump configuration
Leaking joint that had been externally "VacSealed" a few weeks ago may still be leaking, albeit less than it had been -> 9 x 10-8 torr*L/sec helium background rose to 1.1 x 10-7 torr*L/sec after 150 seconds of helium applied to the bagged joint -> This needs to be repeated to confirm -> ideally the background should be lower in relation to the leak being measured for better confidence
H1 PSL
christina.bogan@LIGO.ORG - posted 17:31, Tuesday 20 August 2013 (7489)
Laser Maintainance
Christina, Patrick

Yesterday, we aligned the DBB for both input beams and started checking on the measurement scripts. A tiny misalignment of the PMC input was also fixed. 

In the morning the position of the photo diode inside the Front End was changed due to ECR E1300621-v1. During that the laser was shut down because of the lid-overwrite. We restarted the laser, the power of the oscillator droped a little on the MEDM screen. However we couldn't find the reason. Now that photo diode is hit properly, the status of the noise eater can be watched on the laser MEDM screen.  

We found that the reference cavity was misaligned a little, thus, we optimized that. 

The DBB scripts were fixed and we run all the measurements for both laser systems. We also run the ISS measurement script. The performance of the lasers seems to be good. The out-of-loop noise of the ISS is a little to high, but the inloop performance indicates that the loop is working correctly. (At the moment the show references in the pdf are the measurements from Livingston. We will create our own references soon.)
Non-image files attached to this report
H1 AOS
cheryl.vorvick@LIGO.ORG - posted 15:09, Tuesday 20 August 2013 (7488)
TMS update
BOSEMS:

- cabling issue found this AM

- BOSEMS installed and tested - two were replaced - TMSX now has 6 good BOSEMS

- BOSEM channel LEFT is reading a known good BOSEM (20K+ counts on any other channel) as 13K counts
--- Filiberto is at EX tracking down the issue.  Last info from him was that all cables have checked out OK, and he's looking at the electronics.


PREP FOR MOVE:

- telescope safety support beams attached to the top assembly


STILL TO DO - before transfer functions:
- LEFT BOSEM channel fix
- center BOSEMS
- remove protective wipes from the table, note some have visible particulate from installation activities
- check cables are not touching wires
- lower genie to allow TMS to hang freely
LHO VE
kyle.ryan@LIGO.ORG - posted 13:22, Tuesday 20 August 2013 (7487)
Leaving site for a few hours -> Corner vacuum equipment not in nominal state
I have to leave for a dentist appt. but expect to resume leak checking GV6 when I return (1530?) -> The Corner vacuum equipment is being pumped only via the YBM Turbo pump which is being backed by a leak detector and CP2.  IP1, IP2, IP5 and IP6 are valved-out.  This is a temporary pumping arrangement.  Also, the instrument air used to control CP2 is not enabled currently which is also a temporary state.
Displaying reports 75821-75840 of 83093.Go to page Start 3788 3789 3790 3791 3792 3793 3794 3795 3796 End