Displaying reports 75961-75980 of 83069.Go to page Start 3795 3796 3797 3798 3799 3800 3801 3802 3803 End
Reports until 17:27, Friday 02 August 2013
H1 SEI
sebastien.biscans@LIGO.ORG - posted 17:27, Friday 02 August 2013 (7338)
Sum up of the Guardian work this week for Seismic

Good progress has been done this week at LHO. Jaimee installed a first version of the guardian main code ( /opt/rtcds/userapps/release/guardian/python), and I was able to use this code via the command line.

So far, 4 states are defined for the HAM-ISI:

- SAFE -> masterswitch off, watchdogs on

- READY -> all the filters and matrices are installed properly

- DAMPED -> Damping loops are on

- ISOLATED -> For now, the HIGHEST level of control is on

 

Work done this week:

- the folder infrastructure is defined

- ALL the transit scripts are working and seem robust (some work might need to be done on the DAMPED to ISOLATED transit to make it smarter)

- I wrote some basic recovery scripts for SAFE, READY and DAMPED (we might want to improve them later).

 

Everything is in the SVN at /opt/rtcds/userapps/release/isi/common/guardian/HAM/

H1 SEI
brett.shapiro@LIGO.ORG - posted 17:15, Friday 02 August 2013 (7337)
ETMY ISIINF Coherence Plots
Brett, Jeff, Hugo

Posting a measurement from last week. This data was collected at GPS time 1058659398 (23 July 2013, 5:03 pm PDT).

The data shows the coherence between all 6 ETMY ISIINF channels from 0.1 Hz to 10 Hz. The ISI was damped, with no isolation at this time. These are the witness channels of ISI STG2 in the SUS model that later get projected into the suspension point witness channels. The matrix of data can be read as the coherence from the channel name across the top of the figure to the channel name along the left side of the figure. Note that the data consists of a symmetric matrix, e.g. RX to Y is the same as Y to RX. 

The data shows the most off-diagonal coherence between X and RY, Y and RX. RZ also has some moderate coherence to everything except Z.
Non-image files attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 16:18, Friday 02 August 2013 (7336)
EndY SEI/HEPI Progress Update
The Apollo welders have completed the move of BSC6 piping to BSC10.  The Pump Station in the Mechanical Room was also moved to provide better access to the back side of the station as we now have some extra room given that we only need one Pump Station.  The Pump Station is running in local recirculation mode servo controlled at 10 psi.  The middle recirc valve is choked down to give it some back pressure, please don't adjust.  The VEA side of the piping is under 100psi pressure to monitor for leaks.  If she passes, we'll start refilling the lines next week.
1/2 of the Pier Electronics hve been moved to BSC10; that will get finished Monday.
H1 General
jeffrey.bartlett@LIGO.ORG - posted 15:48, Friday 02 August 2013 (7335)
Ops Summary

08:00
Laser Safe
Hugh and Apollo working on HEIP at End-Y

08:45 Cory G. to Mid-Y then going to End-X
10:07 Fire Department on site
10:10 Betsy & Travis working on ITM-X
11:35 Dale escorting a group through the LVEA
12:20 Richard M moved the dust monitor controller from under IMC tube to under H2-IMC
13:01 Thomas V End-Y to remove optical level equipment
13:19 Rick S working in the H1-PSL enclosure 
13:27 Fire Department back on site
15:32 Betsy & Travis at End-X
H1 AOS
jason.oberling@LIGO.ORG - posted 14:46, Friday 02 August 2013 (7334)
ETMx Cartridge Alignment First Look
Took a first look at the ETMx this morning, here's where it currently sits (all numbers reported as error from nominal):
H1 PEM
richard.mccarthy@LIGO.ORG - posted 13:54, Friday 02 August 2013 (7333)
Dust Monitor Comtrol
Moved the Dust Monitor Comtrol box from its position under the IMC Tube to the original location under the H2 IMC.  This is the start of the 485 loop.  The temporary position was in the middle and may have caused some transmission errors.
We will need to move the ethernet connection once more when the infrastructure is complete.
H1 ISC
jeffrey.kissel@LIGO.ORG - posted 18:38, Thursday 01 August 2013 (7331)
More IMC Gaurdian Progress, and Filter Transfer, but not there yet.
[K. Izumi, J. Kissel, J. Rollins]

We had a small victory today: the guardian interpreter (the robust guardian environment Jamie has created for python) is now functional, and we have successfully written a transit and recovery script to go from the ALIGNED to LOCKED state. In other words, we've converted the portions of the "mcup" and "mcdown" scripts (written in perl) which interact with the SUS MC2 into functional guardian transitions. Tomorrow, our goal is to get at least one of the MC suspensions managed by a guardian automaton.  The monitor/automaton is possibly working now, but we'll have to get it working and run it through its paces.

The IFO has been left in the following state (as of ~6:45 PDT): 

Suspended Cavities Locked: None.
Chamber    HEPI                                   ISI                               SUS
HAM1       Locked                                 n/a                               n/a
HAM2       Floating, Alignment Offsets Only       Level 2 Isolated                  MC1, MC3, PRM damped Level 1.5; PR3 damped Level 1.0
HAM3       Floating, Alignment Offsets Only       Level 2 Isolated (eLIGO Blends)   MC2, PR2 damped Level 1.5 
BS         Level 2 Isolated (Position Locked)     WD Tripped                        BS damped Level 2.0
ITMY       Locked                                 Level 2 Isolated                  ITMY damped Level 2.1
ETMY       Level 2 Isolated (Position Locked)     Level 2 Isolated                  ETMY damped Level 2.1, TMSY damped Level 2.0
H1 AOS
keita.kawabe@LIGO.ORG - posted 18:04, Thursday 01 August 2013 - last comment - 18:27, Thursday 01 August 2013(7329)
TMS today (Cheryl, Corey, Keita)

The part with incomplete tapped holes (D1200310) was fixed by using a clean tap. We pulled the same parts for the third IFO and they were all fine.

The combined tele/table was suspended from the alignment bridge.

Fiber coupled green laser was set up to mimic the injection angle in the chamber.

We started steering the input green beam using the fiber launcher and the first steering mirror on the ISC table. Since everything was aligned previously, the only thing we needed to do was supposed to be to center the beam on the green QPDs.

However, when the green QPDs were almost perfectly centered, we've found that the beam path towards the ETM was totally off and the beam was not even clearing the hole in the ISC table.

Apparently something happened after the ISC table was set up on the work table, maybe one of the mirrors was bumped, or maybe something was loose and it moved when the ISC table impacted the telescope top for mating (actually, the first time we tried to mate the table was kind of wedged into the telescope was stuck, we needed to lift it to unstick, and when the table was freed one side of the table hit the tele top hard).

We need to realign everything on the table, which is not a huge deal but would add another day of work. Today we only realigned the green QPD path, tomorrow we move to the telescope path and IR path. This is actually a good opportunity to move the pico mirror by the periscope away from the suspension wire.

Comments related to this report
keita.kawabe@LIGO.ORG - 18:27, Thursday 01 August 2013 (7330)

A note on Siskiyou actuators:

When you tighten the lock screw of the Siskiyou actuators, the mirror angle changes considerably. When we were doing this for the mirror holder in front of the green QPD sled, the beam fell off of the second QPD. The QPD sled is designed such that the second QPD monitor far field, which means that the beam displacement on that QPD caused by the angle change is much much larger than the angle change multiplied by the lever arm, but that doesn't make me less annoyed.

I don't understand why this happens, but this is quite repeatable and it's not only one mirror holder either, we also experienced this with telescope alignement.

This makes it extremely difficult to work with these actuators (if you want to lock them), because after you tighten the lock screw, the actuator screw becomes hard to move and you cannot get the mirror back to where it should be.

My work around was not to overly tighten, just make it such that it's not easy to move the actuator by hand but it's still possible to do it using an Allen key, and only use Allen keys to make adjustment. Yes it's against the idea of locking if I'm only sort-of-but-not-really locking.

If tightening the lock screw makes such a big change in the mirror angle, I have to wonder if it drifts with the temperature change. Actuator screw is stainless steel, the threaded thing for the actuator screw seems like bronze, thermal expansion coefficients are different depending on the composition of alloy (quick googling tells me that 304SS is about 17E-6/K, 310SS about 14E-6/K, bronze about 19E-6). Therefore when the temperature changes the actuator might become tighter or looser just like when you tension the lock screw.

H1 SEI
hugh.radkins@LIGO.ORG - posted 16:51, Thursday 01 August 2013 (7328)
EndY SEI/HEPI Progress Update
Randy Scott Tyler & Greg; Jim & Keith--Apollo Pipe Fitters

Almost everything is complete for the SEI transfer from BSC6 to BSC10:  All the Actuators are moved, all the plumbing is moved.  One pair of 4-way valves need to be secured to the hardlines.  A piping modification will be made in the mechanical room to give access to the back side of the pump station.  Once that is done, the system can be refilled with fluid for flushing & operation.  Pier electronics can be reinstalled on BSC10...that is about it.
A total of 15 liter of fluid has been removed so far, maybe a little more tomorrow with the MR mod.
H1 SUS
mark.barton@LIGO.ORG - posted 16:08, Thursday 01 August 2013 - last comment - 10:29, Friday 02 August 2013(7326)
ETMX TFs

Richard investigated the problem with the ETMX BIO reported in 7313 and got M0, R0 and L1 fixed, but not L2. I verified that actuation and damping now work for M0 and R0, but couldn't check L1 because the OSEMs there are still backed out.

To see whether it will be worth Doug and Jason's time to do alignment tomorrow or whether more mechanical adjustments are in order, I'm starting a round of undamped M0 and R0 TFs on ETMX from 4:10 pm.

Comments related to this report
mark.barton@LIGO.ORG - 10:29, Friday 02 August 2013 (7332)

The measurements had completed successfully when checked at 08:30:

M0: ^/trunk/QUAD/H1/ETMX/SAGM0/Data/2013-08-01-1059433785_H1SUSETMX_M0_0p01to50Hz_tf.mat

R0: ^/trunk/QUAD/H1/ETMX/SAGR0/Data/2013-08-01-1059452258_H1SUSETMX_R0_0p01to50Hz_tf.mat

For M0 there are a few small L/P peaks in Y in M0 and the fundamental pitch mode is a touch low, but otherwise everything is pristine.

R0 has the usual issue where the pitch mode is higher than in the model due to the stiffness of the cables but otherwise looks good.

The Y issue in M0 is similar to past cases of misaligned OSEMs rather than touching, so the suspension is OK to do alignment on.

Non-image files attached to this comment
H1 General
hernan.daveloza@LIGO.ORG - posted 16:04, Thursday 01 August 2013 (7325)
Ops Day Summary

Besides some discussions about OS, below there is a summury of activities:

- Y-arm road works (ask Ski for more details)
- End-Y works:
    Hugh
    Richard
- Rick gave to UTB students a LVEA tour
- Several DAQ restarts (ask Dave)
~ 11:30 Dale tour at the control room

 

Cheers

 

pablo

LHO VE
kyle.ryan@LIGO.ORG - posted 16:00, Thursday 01 August 2013 (7324)
Serviced X-end purge air
Noticed system pressure below min value when left drying tower regenerating -> Found fouled valve seat on left tower's 3/4" Y-pattern check valve -> Replaced "flapper" mechanism -> Reusing existing housing and "flapper" hinge pin
LHO VE
kyle.ryan@LIGO.ORG - posted 15:56, Thursday 01 August 2013 (7323)
Replaced BSC7's failing annulus ion pump (failed pump running since 2001)


			
			
H1 SUS
arnaud.pele@LIGO.ORG - posted 13:06, Thursday 01 August 2013 - last comment - 11:49, Thursday 05 September 2013(7305)
BS Phase 3b M1-M1 trasnfer functions

Phase 3b top mass (M1-M1) damped and undamped transfer functions on the beamsplitter under vaccum have been measured two days ago with the ISI floating, using the automated matlab script.

The attached pdf are showing in order the results for :

(1) Comparison between M1-M1 measured damped  (red) and modeled (blue) transfer function for the 6 DOF

(2) Comparison between M1-M1 measured undamped  (red) and modeled (blue) transfer function for the 6 DOF

(3) Comparison between M1-M1 phase 3a undamped (in air april 22nd 2013, orange curve), phase 3b undamped (in vacuum July 30th 2013, blue curve), phase 3b damped (in vacuum July 30th 2013, pink curve), and undamped modeled transfer function (in blue)

(4) Comparison between M1-M1 vertical DOF hanford beamsplitter phase 3b (in vacuum, July 30th 2013, orange curve), and livingston beamsplitter phase 3a (in air, April 16th 2013 black curve) and undamped modeled transfer function (in blue)

Most of measurements are in good agreement with the model. Although, the 1.70 Hz longitudinal mode cross coupling into the vertical degree of freedom, cf 3rd page of (1) and (2)

When looking at the comparison between phase 3a and phase 3b for the vertical DOF (3rd page of (3)), it appears that the cross coupling was not present in April when the suspension was in air.

Livingston beamsplitter seems to also have cross couplings in their vertical degree of freedom, but with roll and pitch mode instead of longitudinal (cf (4))

Non-image files attached to this report
Comments related to this report
arnaud.pele@LIGO.ORG - 15:30, Thursday 01 August 2013 (7321)

After discution with J.Kissel, the cross coupling might come from the top mass touching an earthquake stop. This would be due to the sag of the suspension after the air have been evacuated from the chamber.

arnaud.pele@LIGO.ORG - 11:49, Thursday 05 September 2013 (7625)

BS (in chamber, in vacuum, ISI damped (both stages), suspension undamped, no offsets) vertical degree of freedom transfer function has been re-measured yesterday, and isn't showing any signs of coupling anymore (blue curve of attached plot). In order to understand why an extra resonnance was present previously, a series of tests has been carried out, to try reproducing the coupling.

1) First, a vertical offset (-200000 cts) has been applied to the top mass osems, to push down the suspension by ~1mm, and a transfer function has been taken from 1.5 to 2Hz (green curve of attached plot). The cross coupling was still not present

2) The active control of the ISI has been turned off with the vertical offset still on, and an other tf has been taken from 1.5Hz to 2Hz (Red curve). This time, the cross coupling reappeared

3) To reproduce the theory, the offset has been turned off, with the ISI still undamped, and a last tf from 1.5Hz to 2Hz has been taken, still showing the cross coupling, but with a really poor coherence.

Conclusion : When the ISI is floating, and the BS is being excited in the vertical degree of freedom, stage 2 (Rx dof) of the ISI resonates @ ~1.6Hz which then excites the third longitudinal mode (~1.69Hz) of the suspension, creating the cross coupling between vertical and longitudinal we were seeing in our transfer functions

Non-image files attached to this comment
H1 SUS
mark.barton@LIGO.ORG - posted 10:59, Thursday 01 August 2013 - last comment - 14:30, Thursday 01 August 2013(7319)
Quad result file name cleanup

Due to a longstanding bug in a script (fixed on 6/28/13), there were a bunch of pdf files in ^/trunk/QUAD/Common/Data in the SUS SVN with names starting "allhstss...". I did svn mv commands on all of them to change the prefix to "allquads".

Comments related to this report
mark.barton@LIGO.ORG - 14:30, Thursday 01 August 2013 (7320)

Found a bunch more under ^/trunk/HLTS/Common/Data and fixed in the same way.

LHO VE
john.worden@LIGO.ORG - posted 16:21, Wednesday 31 July 2013 - last comment - 16:50, Thursday 01 August 2013(7311)
Plot of QDP80 Roughing the vertex

QDP80 roughing the vertex volume. For Mike Z.

Volume pumped would be the Y Beam Manifold + HAM2,3 + BSC1,2.

Images attached to this report
Comments related to this report
john.worden@LIGO.ORG - 16:50, Thursday 01 August 2013 (7327)

Volume pumped should be Y Beam Manifold + HAM2,3 + BSC 1,2,3

Displaying reports 75961-75980 of 83069.Go to page Start 3795 3796 3797 3798 3799 3800 3801 3802 3803 End