Clean room was moved from BSC 6 to BSC 10, work platform disassembled at BSC 6 and reassembled around BSC 10. Clean room then moved back over BSC 10. E module relocated to east side of test stand clean room (only 3 bolts per leg) and in position. TIGHT FIT West door installed on BSC 9 and bolts torqued. Only 4 bolts in dome and east door, remainder to be installed and torqued tomorrow.
After the ACB crew finished this morning, Travis, Jim and I finished the rest of the closeout work:
- Reapplied FC to ETMx-HR thin alignment windows
- Set and secured all 72 ETMx SUS EQ stops
- Set 4 top stage BOSEMs to counter upcoming buoyancy shift under vac (Left, Right BOSEMs on M0 and R0)
- Removed the ACB locking bracket and 4 screws
- Performed chamber inspection for tools, FC on viewports, tokk a few pix, etc.
- Wiped and wiped and wiped some SUS, ACB, TMS surfaces and the floor many times ("good" IPA + alpha 10 wipes)
- Added a witness plate to the vertical holder mounted off the bottom of the front of the QUAD lower structure (LS)
- Added a 1" witness optic + PEEK holder to side of the QUAD LS
- Pulled the FC from the ETMx-HR and blew with ~10psi Top Gun N2 and inspected
- Blew the TMS telescope mirrors - didn't look great, but lots of stuff lifted with the blowing
- Unlocked the ISI
- Damped ETMx to make sure it seemed healthy
- Placed 2 witness plates (not in holders since I didn't have any with me), one directly under the QUAD, one under the front of ACB towards the tube (these should be pulled asap at next vent!)
- Left Apollo to toss the door on
Steps taken to commission the ITMY ring heater pair: - Updated to the recently committed Beckhoff code that Joe B and Adam M worked on yesterday. - Added the calibration values that Aidan B had recommended for running the ring heaters. - Opened up a strip tool to monitor the vacuum pressure with the closest gauge (HVE-LY:Y1_120BTORR) - Turned the ring heaters on to low power (~.01 Watts) to make sure that the channels were working properly - Increased the power to 1 Watt for a 4 hour period starting at 12:00PM Pacific Time, keeping an eye on the pressure gauge previously mentioned. Upper: Requested Power = 1.00 Watts Measured Voltage = 5.94 Volts Measured Current = 0.17 Amps Calculated Power = .99 Watts Calculated Resistance = 34.94 Ohms Lower: Requested Power = 1.00 Watts Measured Voltage = 5.92 Volts Measured Current = 0.16 Amps Calculated Power = .98 Watts Calculated Resistance = 37.0 Ohms A four hour trend of the pressure gauge and ring heater settings is attached. A quick, back-of-the-envelope calculations shows that the ring heaters are working properly. The next step for measuring the thermal lensing would be to measure the beam diameter of a single reflection off of the back of ITMX independently and then changing the radius of curvature of ITMY using the ring heater to match. This requires looking at the REFL beam either in the HAM1 chamber or on the ISCT1 table, depending on how much power we are able to get out of REFL. The Thorlabs beam profile we have on site requires a minimum of ~1e-5 Watts of incident beam power to function.
NOTE: This pair of upper and lower ring heater segments is due to be replaced, per "Bug255" https://services.ligo-wa.caltech.edu/integrationissues/show_bug.cgi?id=255 See, also, T1300463
Day's Activities:
Swapping out PSL Chasis (Filiberto)
Greg craning dewar over Beam Tube in LVEA
Move ITMy Lower Structure to LVEA (Jeff/Andres)
Tumbleweed baling on X-arm
Lots of Apollo activity at EY (moving cleanrooms, platforms, E-module; installing BSC6 door, installing hard covers on Spool)
PSL work by Kiwamu (investigating mysterious RF jump by unplugging EOM cable); external shutter was also closed. EOM was fixed in situ
PSL Shutter was replaced (Gerardo, Joe D.)
ACB work at EX (Gerardo/Mitch)
SUS work at EX (Betsy/Travis)
Had a couple of IOP SUS Watchdog INVALID alarms during shift; not really sure of the cause (also popped up window stating: "Channel Access Exception...")
PSL Checks:
Gerardo M, Mitchell R The ETM-x Arm Cavity Baffle has been dog clamped. All class B tools and hardware has been removed from chamber. The ACB is still locked.
Bubba, Randy, Scott, Tyler, Ed, Mark, Corey, Jim
Yesterday, we completed the removal of the BSC6 cartridge. The assembly is now resting comfortably on the test-stand, 180 degrees to it's final in-chamber position (necessary for cleanroom clearances). Both suspensions are covered, and the ISI has 3 separate covers. No unusual difficulties beyond some misplaced hardware, but Apollo took an early lunch so I could scramble and find it.
Kiwamu, Stefan Attached is a new RF return loss measurement for the EOM cable taken at the PSL rack end. This was taken after the latest RF phase jump. As before, the marker labeled 24.08MHz is at the actual IMC modulation frequency of 24.078360MHz. Compare this to alog 7959 (before RF jump).
Kiwamu repeated the measurement directly at the EOM, and he was able to jump between the two setting by pushing at the EOM's Sam connector. Conclusion: a bad connector at the EOM is responsible for our phase jumps.
The resonant frequency of the notch appears to have changed such that one could reasonably account for the phase shift. The million dollar question is how? Either the tuning has bistable states (such that a mechanical tuning screw clicks between two states) or the external loading changes due to a bad connection to the EOM. It seems the latter has just been identified by Stefan...
Sheila and Kiwamu
We improved the clipping of the IM1 trans beam by moving the uncontrolled degree of freedom in the IMC alignment control.
As a result, the amount of the light detected at the trans PD went up from about 240 counts to more than 800 counts. Also the beam shape on the camera became more round-looking.
The clipping was mainly in yaw. The shift we introduced was visible in the IM4 trans QPD. The spot moved in yaw from -0.3 to 0.
The screen shots below are the current alignment settings that gives a less clipping on the IM1 trans beam. Note that we didn't touch IM1-4 suspensions.
Stefan and Kiwamu
We continued working on the alignment of IMC today. We managed to get the alignment back i.e. the beam hits the center of the IM4_TRANS QPD with all WFSs in action. It is now happiy locking.
However, we found that the IM1 trans path, which is used for a camera and trigger PD, seemed clipped. By moving the mirrors on IOT2L, we concluded that the clipping happened in chamber, namely in HAM2. This is not a critical issue as this light is used only for triggering purpose and it still gives a reasonable amount of the light. We will keep studying what is happening in the chamber. Perhaps this could be due to the uncontrolled degrees of freedom in the IMC alignment control.
What we did:
Comments on the 5th or 6th phase rotation of the IMC: We are now using the I demod output for IMC locking. The delay line settings are: 1/16:Up 1/8:Dn 1/4:Up 1/2:Up 1:Up 2:Up 4:Up 8:Dn 16:Dn The WFS phase settings are: H1:IMC-WFS_A_SEG1_PHASE_R = -90 H1:IMC-WFS_A_SEG2_PHASE_R = -17 H1:IMC-WFS_A_SEG3_PHASE_R = -27 H1:IMC-WFS_A_SEG4_PHASE_R = -22 H1:IMC-WFS_B_SEG1_PHASE_R = +15 H1:IMC-WFS_B_SEG2_PHASE_R = -34 H1:IMC-WFS_B_SEG3_PHASE_R = +28.5 H1:IMC-WFS_B_SEG4_PHASE_R = -81 For previous rotations, see Oct 1st alog 7941.
There is a similar report from the last May (alog 6265). I wonder if an optic is loose somewhere in this path.
Sysadmin tasks: Patched internal machines accessible from outside of CDS. Performed nmap network scans on 10.20.0.0/24 and 10.101.0.0/24 subnets. Updated network drawings
h1asc0: Replaced the h1asctt model with the new h1sushtts model.
updated the H1EDCU_DAQ.ini file to trend status of all models. Updated autoBurt.req for DAQ frame writers to archive all EPICS channels associated with these systems.
Updated overvew MEDMs (for ASC TT change)
Multiple DAQ restarts were required to support these changes.
- FM-200 Systems (OSB and LSB), annual inspection took place today.
- Apollo at Y-End, working on extraction of cartridge out of BSC06.
- Baling crew @ Y-arm, baling tumbleweeds, now at X-Arm, opening a path.
- Kiwamu and Stefan, working on IMC recovery.
- Dave, some DAQ reboots.
- Thomas, to LVEA, connected TCS ring heater for ITMY.
Kyle, Gerardo Repair of the drying towers is done but the purge-air supply isn't available to the LVEA yet -> We still need to devise a method to demonstrate the effectiveness of the removal of the alumina dust before routing the dry air through the final filtration stages and on to the LVEA
HEPI common parts were updated yesterday per WP #4315
HEPI-HAM2 and HEPI-HAM3 were turned ON using the new Command scrips (Command2 Button from the overview screen).
They are running on their respective position loops, with the generic position blend filters (L4C=0, IPS=1).
Both HEPIs are aligned to the initial alignment position (aLog 7180)
HAM2 alignment TARGET (nm or nrad):
| X | -34219.8 |
| Y | -28697.6 |
| Z | -49473.8 |
| RX | 8810.3 |
| RY | -67894.6 |
| RZ | -20905.3 |
| HP | 30465.4 |
| VP | 16344.5 |
HAM3 alignment TARGET (nm or nrad):
| X | -3129.6 |
| Y | 106783 |
| Z | -104514 |
| RX | -23729.6 |
| RY | -25190.7 |
| RZ | 123598 |
| HP | 87442.4 |
| VP | 200991 |
I worked on putting together a Contamination Control cart (CCC) as Calum requested while he was visiting. It is at Y End. The cart contains most of the components for a clean Top Gun Ionizer set-up (Top Gun, regulator, wrench, and hoses but no N2), a Tiger Vac with hose and attachments, a power strip, Alpha 10 wipes, a flashlight array with extra batteries, and Class B glass bottles for IPA. The cart and contents are covered in C-3. Please see pix below. Feel free to use the cart for Clean as You Go activities and then let me know how the cart can be improved.
J. Kissel, D. Barker
There was a significant amount of extra work installing the new HAUX and HTTS models on their respective front ends, so I detail below.
${userapps}/sus/${ifo}/models/${ifo}sushtts.mdl
------------------------------------
- Make sure to remove ${ifo}asctt and replace with ${ifo}sushtts (or capitalized version, when appropriate) in the following files:
- /diskless/root/etc/rtsystab (on boot machine, i.e. ${ifo}boot0)
- ${userapps}/release/cds/${ifo}/daqfiles/${ifo}dc0/master
(which hopefully is the source of the softlink in /opt/rtcds/${site}/${ifo}/target/${ifo}dc0/)
- the framebuilder's .ini file,
- the test point manager's .par file, and
- the EPICs database's EDCU .ini file
- ${userapps}/release/cds/${ifo}/daqfiles/${IFO}EDCU_DAQ.ini
- Log onto ${ifo}build front-end
- make ${ifo}sushtts
- make install-${ifo}sushtts
- Log onto ${ifo}asc0 front-end
- kill${ifo}asctt (Needs to be removed from front-end kernel, since it'll no longer be used)
- start${ifo}sushtts
${userapps}/sus/${ifo}/models/${ifo}susim.mdl (much more simple, more typical since the model already exists)
------------------------------------
- Log onto ${ifo}build
- make ${ifo}susim
- make install-h1susim
- Log onto ${ifo}sushh2b
- start${ifo}susim
Since there are a ton of new channels, one will need to restart the data-concentrator,
- telnet h1dc0 8087
> shutdown
And for good measure (because it seemed to be running slowly), we restarted the EPICs gateway, but this isn't necessary.
Stay tuned -- a plethora of MEDM screen modifications are next!
I think the second section should actually be
${userapps}/sus/${ifo}/models/${ifo}susim.mdl (much more simple, more typical since the model already exists)
Fixed. Thanks Keith!