Displaying reports 77141-77160 of 84498.Go to page Start 3854 3855 3856 3857 3858 3859 3860 3861 3862 End
Reports until 16:13, Friday 30 August 2013
H1 ISC
stefan.ballmer@LIGO.ORG - posted 16:13, Friday 30 August 2013 (7593)
6hrs of MC locking - ISS diffraction effeciency and FSS temperature control signal drift
The two attached plots show the following signals over the span of 6h (patch them next to each other):

Blue:   FSS control signal readback
Green:  FSS autolocker state
Brown:  ISS diffraction efficiency
Cyan:   IMC build-up
Yellow: FSS temperature loop control signal

Notable:
 - The ISS diffraction efficiency varied between 10% and 15%. This corresponds to an ISS loop gain variation of sqrt(0.15/0.10)~1.2, or about 20%.
 - The short lock losses were due to Ethercat reboots, resulting in IMC lock losses. The FSS never dropped below state 2, as is evident from the fact the the temperature loop did not forget its offset.
 - The IMC held lock through the magnitude 7.0 earth quake in the Aleutians this morning. The peak seismic signal at LHO was on the order of 20u/sec.
Images attached to this report
H1 SEI
hugh.radkins@LIGO.ORG - posted 16:12, Friday 30 August 2013 (7594)
WHAM6 HEPI Install Update
With the doors on and cleanroom now moved, I've installed all the sensors & electronics.  Quick look at spectra suggest things are OK.  The HEPI is still locked and the Vertical L4-Cs still need to be leveled and protected.  There remains some cable dressing as well.  Please be mindful of the sensors and cables at this location.
H1 General
jeffrey.bartlett@LIGO.ORG - posted 15:49, Friday 30 August 2013 (7592)
Ops Summary
09:00 Cory, Cheryl, and Andres at End-X to move and attach TMS OB/Telescope
09:32 Betsy & Travis working on ITM-X
09:41 Richard at ITM-X working on SUS electronics
10:15 Justin check out dust alarm in Bake Out lab
10:15 Bubba/Apollo in LVEA working on cleanroom move
13:15 Thomas Vo Recycled EtherCAT in corner station
13:26 Hugh at HAM6 working on HEPI electronics
14:11 Andres dog clamping SR suspensions to optics table
14:32 Cheryl at End-X working on TMS
LHO VE
kyle.ryan@LIGO.ORG - posted 15:08, Friday 30 August 2013 (7591)
X-end purge air still running on 4 of 5 compressors
I attempted to replace Compressor #1's "noisy" scroll but the new scroll (SLAE05E) is not a direct substitute for the legacy scroll (SLAE05) -> I'll attempt to acquire the old part number or make a custom mount if needed (next week)
H1 SUS
betsy.weaver@LIGO.ORG - posted 14:09, Friday 30 August 2013 - last comment - 16:25, Friday 30 August 2013(7590)
ITMx SUS - update

We've connected all of the cables on the ITMx QUAD and all 20 OSEMs have some sort of signal coming out to medm.  Thanks Richard for some power and rack troubleshooting on QUADTST.  There is some strangeness on the medm so Arnaud is looking into what model version is loaded on the QUADTST testbed.  The main chain does not damp so we likely have crossed signals or a sign flip somewhere...?  More from him to come.

Comments related to this report
arnaud.pele@LIGO.ORG - 16:25, Friday 30 August 2013 (7595)

Damping gains were still set to their old values. They are now set to -1, which is the convention for filter gains. Coilouput gains and signs have been checked, and are in accordance with the magnet convention (+ sign = north pole magnet, and vice versa).

H1 ISC
corey.gray@LIGO.ORG - posted 21:02, Thursday 29 August 2013 (7589)
Table/Telescope Not Installed (Ready To Go)...Continued Cabling Work

The Continued Story of CB3

On Wed, there were unresolved issues with cabling for the TMS.  The main issue was a cable bracket (CB3) which, on a drawing, is supposed to be on the east side of the table (i.e. -Y side of TMS), but having it here has limited access, and it would be even worse after we box it in when the Table/Telescope was installed.  

Now the cables (TMS OSEMs) which use CB3 eventually run to a feedthru which is quite on the other side of the TMS (i.e. the +Y side of it); on this side of the TMS there is lots of open space & getting to the feedthru is trivial.  So, after consulting with Cheryl/Mike/Calum, Jeff & I decided to move CB3 from it's "called out" location on the "edge" of the table to roughly the center of the table.  So, the "quadrapuss" OSEM cable D1000234 was run to this feedthru (and excess bundled near bracket), then D1000225 was run straight "north" on the table and out to a spot where Jim W suggested---then he'd be able to dress it on the ISI and on to the feedthru.  The beauty of this cable run is that we have elegant access to the cables & cable bracket.

This leaves us ready at the Cartridge to bring in the Table/Telescope.  

Table/Telescope Installed On Test Stand:  Promise!

Throughout the day, I also prepped the Table/Telescope for the trip form the TMS Lab to the Test Stand.  I blew off the Telescope Mirrors, installed the TMS Cover (to protect Table optics), and arranged the Genie and Table/Telescope for the move first thing tomorrow morning.

Attached are photos of how Jeff B. ran the cabling and where he positioned CB3 (the D1000225 has about 14' of cable and it is coiled on the table ready to be grabbed by SEI for final dressing to feedthru).

Images attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 18:33, Thursday 29 August 2013 (7588)
plots of dust counts
Attached are plots of dust counts requested from 4 PM August 28 to 4 PM August 29.
Non-image files attached to this report
LHO General
patrick.thomas@LIGO.ORG - posted 18:30, Thursday 29 August 2013 (7587)
plots of dust counts
Attached are plots of dust counts requested from 4 PM August 27 to 4 PM August 28.
Non-image files attached to this report
H1 AOS
stefan.ballmer@LIGO.ORG - posted 17:57, Thursday 29 August 2013 (7586)
investigation of EY drift event of 07/19/2013 00:00 UTC

To tie up some loose ends, I went back to the EY drift event of 07/19/2013 00:00 UTC (elog 7146), which was triggered by turning off the clean room.

The attached plot 1 shows 20 days around the event. Marked in dark blue is the turn-off event, marked in bright clue is the turning on of the same clean room a day after. I am not sure where exactly the two temperature sensors are located, but I amsure the actual temperature jump at the BSC was bigger (From John's elog 7149 is was >2degF).

According to the OSEMS the TMSY drifted by about 5 urad in pitch and yaw (ignore sharp steps due to realignments) - I don't think that can be responsible for us falling off the photodiode. so something else must have moved.

The ETMY is even less: ~2urad in pitch and nothing significant in yaw (plot 2).

The PZT actuators (under QPD control, slaving the beam to the TMS) show some shift, but nothing that would be very unusual.

So the bottom line is: I still don't understand why we fell of the diodes on ISCTEY that day.

 

 

 

 

'

Images attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 16:33, Thursday 29 August 2013 (7585)
Corner Station RGA
I have been trying to familiarize myself with Rai's "hydrocarbon" RGA (software and apparatus) which is mounted on the East door of HAM3 and have included some preliminary scans taken today.  These aren't intended to contribute to the eventual analysis but are interesting nonetheless.  It looks to me like the lack of distinct hydrocarbon peaks will necessitate an accumulation on the RGA's 80K "cryo finger".  We may need to compare scans with and without CP2.  

Rai has already used this same setup to quantify the hydrocarbon partial pressures at the Y-end and has commented on the expected impact on aLIGO mirrors (see T1100561, T1100642, T1200021 and T1200395). 

Note: these .pdfs contain "sticky notes" without which these scans won't have much meaning
Non-image files attached to this report
LHO General
hernan.daveloza@LIGO.ORG - posted 16:02, Thursday 29 August 2013 (7584)
Ops Summary

- Apollo crew working on the floor of End-Y.
- Apollo installed HAM door in LVEA.
- Arnaud was taking TF of the BS.
- Dust monitors location updated (I guess Patrick did it).
- Richard went to mid-X to check equipment.
- Dave installed firefox on left operator's computer for camera views.
- Dave copy firefox's folder after crash (lost bookmarks) on main operator computer.
- Rick and Christina (her last day) working on PSL.

 

pablo

H1 SEI
vincent.lhuillier@LIGO.ORG - posted 15:59, Thursday 29 August 2013 (7582)
ISI - BSC1 and BSC2 at the requirements

Last night, I left the two ISIs at the corner station with the aggressive feedback isolation filters and the feedfoward engaged. HEPIs are just controlled in position (100mHz UGF). Configurations were almost identical (cf item 5) on both ISI (low blend on translations and high blend on rotations to limit noise injection).

I have attached spectra of the stage 2 motion in the Y direction.
Note that:
1- ISIs didn't trip during a long stretch of time. The control is very robust (the ITMY feedback filters were even designed with the HEPI locked)
2- The stage 2 motion in the Y direction meet the requirements for both ISIs
3- The performance are similar for both ISIs
4- The feedforward control allows squashing the HEPI pier resonance on ITMY (feedforward filters clearly need to be reworked on BS)
5- ITMY performs slightly better than BS at low frequency. I noticed that the sensor correction was engaged on stage 2 in the Y direction. It might explain the difference

Images attached to this report
H1 PSL
justin.bergman@LIGO.ORG - posted 15:46, Thursday 29 August 2013 (7583)
ALS light pipe shutter

I have removed the lock and tag on the ALS light pipe entering HAM 1 and opened the shutter.

LHO General
bubba.gateley@LIGO.ORG - posted 15:36, Thursday 29 August 2013 (7581)
Apollo crew
Ham 6 doors are on with 4 bolts each. Flange joints on hams 4,5,&6 are taped all around, started sealing vacant bolt holes on same flanges.
Relocated clean room that was over ham 4 to area in front of hi bay.
Tyler in machine shop, talked with Betsy regarding a longer tap, still working on SUS parts.
Flooring guys at end y will finish this afternoon, with the exception of approximately 14' of trim. This trim had to be oredered and is 2 weeks out. This trim is where the seams come together and does not pose any contamination isssue.
H1 SUS
arnaud.pele@LIGO.ORG - posted 14:39, Thursday 29 August 2013 (7577)
PR2 phase 3b lower stage TF

Following previous aLog (7568) on PR2 top mass transfer functions, lower masses phase 3b transfer functions have been taken and measurements data have been processed. Plots attached are showing comparison with model and other hsts measurements

(1) H1 PR2 M2 to M2 undamped TF (July 2013 in pink) against L1 PRM M2 to M2 undamped TF (July 2013 in orange) against hsts model

(2) H1 PR2 M3 to M3 undamped TF (July 2013 in pink) against L1 PRM M3 to M3 undamped TF (July 2013 in orange) against hsts model

Looking at M2-M2 TF, the two highest resonnances of pitch (3.094 Hz and 3.641Hz) are shifted down compared with the model and LLO's measurement (3.216Hz and 3.778Hz). 

 

Those measurements have been taken with DTT and the xml templates are located on the svn under sus/trunk/HSTS/H1/PR2/{SAGM2 or SAGM3}/Data/2013-07-15_1900_H1SUSPR2_M2_WhiteNoise_{L or P or Y}_0p01to50Hz.xml

Data, plots and scripts have been commited to the svn

Non-image files attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 14:20, Thursday 29 August 2013 (7580)
legacy blue/ilog web pages down, being investigated

The legacy web pages from iligo (e.g. blue, ilog) are down at the moment. LDAS is looking into the problem.

H1 PEM
justin.bergman@LIGO.ORG - posted 13:45, Thursday 29 August 2013 (7579)
Dust monitor location change

Jeff B moved Dust monitor 15 from HAM5/6 cleanroom to small cleanroom just north of HAM 4 where suspensions are loitering. I have changed the wiki to reflect this.

H1 PSL
justin.bergman@LIGO.ORG - posted 13:23, Thursday 29 August 2013 (7578)
crystal chiller refilled

Twenty days since last fill (8/9/13)---added 375mL distilled water this morning.

H1 SUS
betsy.weaver@LIGO.ORG - posted 08:56, Thursday 29 August 2013 (7576)
ITMx SUS - pilot optic wire hang progress

Last Friday Travis and I finished hanging the metal ITMx QUAD and adjusting out coarse alignment errors.

On Monday, I disassembled the lower metal masses and dummy wire segments from the ITMx QUAD.  The RH guys attached the RH (see their alog below).

On Tuesday, Gerardo, Travis and I moved the ITMx and CP optics from the LSB bonding lab to the LVEA.  The ergo arm was transported from Ex to the LVEA and recleaned.  Using the arm, we stuffed both optics into the ITMx QUAD currently hanging from the ISI on the LVEA test stand after first peeling the CP-HR and the ITMx-AR First Contact sheets (using N2).  Note, I had to fold the FC sheet on the CP-AR in all the way around it's edge since it's diameter was too large and the ergo arm could not get good suction on it to pick it up.  The suspension also had a coarse cleaning to blow off particulate prior to installing the optics - cleaning these suspensions is very difficult however since the equipment cannot reach the trapped areas and working real estate is so limited.

Yesterday, Travis and I attached the new loop wire segments to the main and reaction chains and fully suspended them.  No gross alignment errors observed, so prism placements and loop lengths are good!  We then proceded to lace the reaction chain cables.  We need to make some height adjustments and also plumb in the 12 top BOSEMs to get damping control before we can start taking IAS measurements, but we hope that will come together today/tomorrow.

H1 SEI
hugh.radkins@LIGO.ORG - posted 14:38, Wednesday 28 August 2013 - last comment - 08:53, Thursday 29 August 2013(7565)
WHAM6 Chamber ready for doors
Before lunch I got the sign off on the Optical Table position from IAS (Jason;) I expect you'll see an entry from him shortly.  This was preceded by an elevation survey performed by myself and GregG:

Our initial level had an 11mil runout about 4mils low per target (D1100398/E1000403).  We did a couple small large Spring adjustments and finished at <8mils runout at -220.1mm average elevation Gz (0 error from spec.)

After IAS was done, I activated the CPS, recorded locked positions and then unlocked the IAS.  I repeated the lock and unlock recording the CPS all around.  The largest change observed was <1200cts or 0.04mm, comfortably under our <1600 cts max lock/unlock change.

WHAM6 has dummy payload on viton suitable for testing and is ready for doors.

One final thing--conferring with Bubba/Apollo: I will lock the HEPI this afternoon and will not install HEPI electronics.  Will keep the Dial Indicators in place to monitor HEPI position--please respect these.
Comments related to this report
hugh.radkins@LIGO.ORG - 16:22, Wednesday 28 August 2013 (7567)
The HEPI suspension is now locked.  Other Chamber area preps have been completed.
jason.oberling@LIGO.ORG - 08:53, Thursday 29 August 2013 (7575)

Final measured XY position/yaw errors of WHAM6 ISI:

  • X-axis Position Error: -8.8 mm
  • Y-axis Position Error: +13.75 mm
  • ISI Yaw Error: 50 µrad CW
Displaying reports 77141-77160 of 84498.Go to page Start 3854 3855 3856 3857 3858 3859 3860 3861 3862 End