Displaying reports 78521-78540 of 79140.Go to page Start 3923 3924 3925 3926 3927 3928 3929 3930 3931 End
Reports until 20:44, Monday 21 March 2011
H2 INS
michael.rodruck@LIGO.ORG - posted 20:44, Monday 21 March 2011 (644)
H2 PSL Installation

Linoleum was removed inside the grout dams and table legs were set inside, and leveled. We plan on grouting the legs into place tomorrow with hydrostone.

H2 General
david.barker@LIGO.ORG - posted 16:36, Monday 21 March 2011 (643)
new LDAS disk system for iLIGO fb0w

LDAS have replaced their aging 3511 disk systems (the ones fb0w uses) with a new Sataboy. The disk capacity has gone down to 18TB (from 30TB) but the new system will be immune to the disk crashes of S6. We copied the minute trend files across from the old disks, these are the only old DAQ data we will preserve. All other data (full frames, second trends) are starting from scratch.

So from nds0 which mounts the new disks, minute trends have a data gap from 08:46 Mar 16 to 11:50 Mar 21. All other data started from scratch at 11:50 today. If you need access to minute or second trends in this data gap, please use nds2 which mounts the fb1w system and which ran throughout this upgrade.

H2 General
jeffrey.garcia@LIGO.ORG - posted 16:15, Monday 21 March 2011 (642)
Ops Day Summary
~9:00 – Michael and contractors began leveling the PSL table

~9:00 - Richard and contractor working at Y-End.

~9:30 – Kyle to begin venting RGA volume and remove RGA components from BSC6

Work throughout the day:
bins being moved around in the LVEA
HEPI installation continuing on BSC 7
X1 SUS
betsy.weaver@LIGO.ORG - posted 09:15, Monday 21 March 2011 - last comment - 10:44, Tuesday 22 March 2011(640)
Q3 ECDs mounted
I installed the ECD blocks on the R0 Top Mass/Tablecloth.  Attached is a plot showing the TF taken just before the addition, as a reference, and with the ECDs set to within a mm of touching the mass.  The green and black peaks are with the ECDs, and show significant attenuation of peaks.  We need to determine if the placement of the blocks is acceptable, or if they need some in or out adjustment. - Plot to be uploaded when test stand power is recovered.
Comments related to this report
travis.sadecki@LIGO.ORG - 15:32, Monday 21 March 2011 (641)


		
		
travis.sadecki@LIGO.ORG - 07:50, Tuesday 22 March 2011 (645)


		
		
travis.sadecki@LIGO.ORG - 07:51, Tuesday 22 March 2011 (646)


		
		
travis.sadecki@LIGO.ORG - 10:44, Tuesday 22 March 2011 (647)


		
		
Non-image files attached to this comment
X1 SUS
betsy.weaver@LIGO.ORG - posted 16:32, Sunday 20 March 2011 (639)
SUS Test Stand Re-level
With the new Sokkia Autolevel, I rechecked the level of the Assembly Test Stand sighting on the Upper Structure base surface which is a referenced flat in the suspension build.  (Recall that we re-built the solid stack which the suspension hangs from in order to open up assembly real estate and mount a cross flow HEPA.)  On Friday, I determined that the structure was out by 0.008" over a 17" length along the Y direction (perp to beam line of the QUAD).  This equates to 0.5mRad.  The Test Stand was designed to be level to within 0.2mRad as per T050113, so today I adjusted the Test Stand feet to bring it in to 0.13mRad.  A quick check on the beam-line direction which looked better than than 0.13mRad, so no adjustments made for that direction.  The BOSEM signals showed a little bit of swing due to this releveling (~100 counts), but no bigger than the daily temperature drift of the signals (where a few degrees soften(?) the blades over the course of the day such that BOSEM LEFT and RIGHT change in the same directions on both chains by ~500 counts).
H2 INS
greg.grabeel@LIGO.ORG - posted 17:43, Friday 18 March 2011 (638)
HEPI install
Using the new HEPI alignment numbers BSC HEPIs 77 54 51 45 and HAM HEPIs 03 05 are now complete.
H2 INS
michael.rodruck@LIGO.ORG - posted 16:44, Friday 18 March 2011 (637)
H2 PSL installation

Grout dams were caulked into place, based off the layout Mick, Nicole and I set yesterday. These are only held into place by a bead of caulk, so take care not to kick them loose. Caution tape was set around the area. On Monday we will cut out the linoleum in the center of the dams and level our table legs.

Images attached to this report
LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:28, Friday 18 March 2011 (636)
IP12, X-end, IP6
Replaced IP12's non-working MultiVac ion pump controller with a DualVac controller yesterday and modified signal cabling pinouts to match.  Pumped X-end with MTP for awhile then switched over to IP12 (note IP12 status is still "RED" in CDS displays -> Dave B. will correct database parameters to match new controller's signal outputs before the next reboot at which point IP12 status will change to "GREEN" in CDS displays)

Spun down MTP at X-end and shut down QDP80 pump.  

Noticed IP6's high voltage output "FIXED" at 7000V -> Corrected to "STEP" output.  
H2 INS
michael.rodruck@LIGO.ORG - posted 16:18, Thursday 17 March 2011 (635)
H2 PSL installation

Linoleum work was finished today. Contractor came on site and welded the seams. There were some concerns about welding the new linoleum to the old linoleum, but he was able to do it no problem.

H2 INS
corey.gray@LIGO.ORG - posted 16:09, Thursday 17 March 2011 (634)
BSC HEPI Foot Adjustments Started On Next Set

[Corey, Greg, Hugh]

With new numbers, we went about setting the HEPI Foot to their nominal positions prior to installation.  This afternoon we made it through (2) HEPI's.  Tomorrow we'll finish the other two and then start on a HAM set.

LHO FMCS
mark.lubinski@LIGO.ORG - posted 15:07, Thursday 17 March 2011 (633)
Facilities
Replaced both check valves at X mid station control air compressors
Ran well pump to fill tank
Re-started Staging building booster fan
LHO FMCS
mark.lubinski@LIGO.ORG - posted 13:08, Thursday 17 March 2011 (632)
CS control air system
Changed out the CS control air compressor check valves.
H2 INS
patrick.thomas@LIGO.ORG - posted 16:22, Wednesday 16 March 2011 (630)
Ops Day Summary
Linoleum put down in H2 PSL area
HAM8 was moved
Tumbleweed bailing
Images attached to this report
X1 SEI
greg.grabeel@LIGO.ORG - posted 16:10, Wednesday 16 March 2011 (631)
Pitchfork Assembly
The remaining 2 pitchforks were assembled and put onto stage 1 today. What boxworks walls we do have were prepped with dowels and are sitting on the granite table.
H2 General
david.barker@LIGO.ORG - posted 11:43, Wednesday 16 March 2011 (629)
fb0w not writing frames as LDAS upgrades its disk system

The iLIGO primary framewriter (fb0w) was put into partial mode (not writing frame files) as LDAS upgrades this disk system. So only fb1w is writing frames, which are being served by nds2.

Please use nds2 for archived data until LDAS has completed their upgrade.

H2 General
jeffrey.garcia@LIGO.ORG - posted 15:52, Tuesday 15 March 2011 (628)
Ops Day Summary
10:45 – Kyle to X-end to continue yesterday's work.

contractors moving beams around in the LVEA

~3:00 – tumbleweed bailing completed
X1 SEI
corey.gray@LIGO.ORG - posted 15:46, Tuesday 15 March 2011 (627)
ISI Assembly Status

[Corey, Greg]

Received (3) big plates for the BSC ISI and unloaded at the VPW

Transferred Pitchfork & Boxwork Stage1 Walls from the VPW to Staging Building.  Started pre-assembly work on these walls (i.e. pressed dowel pins and inserted helicoils).  Assembled (1) Pitchfork (and installed on Stage1 [just pinned to Stage1]).

Moved pallet of HAM-ISI#3 BAD plates out near Fire Water Tank lay down area.

LHO FMCS
kyle.ryan@LIGO.ORG - posted 15:07, Tuesday 15 March 2011 (626)
Installed mechanical level guage for CP8
This completes the site, i.e., all 80K (LN2) pumps now have mechanical differential pressure gauges mounted beside the 80K vessels on the same stand used to mount the CDS pressure/electrical pump level and exhaust transducers. These will allow us to have an indication of the 80K pump levels in the event of a power outage or other CDS failure.  

As labeled, 38" H2O equates to 92% full which is the nominal level for the site LN2 (80K) pumps.  
Displaying reports 78521-78540 of 79140.Go to page Start 3923 3924 3925 3926 3927 3928 3929 3930 3931 End